Appendix B: Capital Project Update Report
October 8, 2019Page 412 sections
Detailed status report for all 2019 capital projects, including costs to date and expected completion dates.
$900,000 budget for Rescue Truck$360,000 for Burnett Rd to VR Park sidewalksElectronic Records Mgmt Software scheduled for 2020
Capital Project Update Report
For period ending September 30, 2019
Transportation
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Sidewalk Projects | |||||||
| 11101 Sidewalks | 1193 | Pedestrian safety improvements - Burnett Rd to VR Park | 35,953 | 360,000 | 324,047 | 10% | Complete |
| Street Lighting Projects | |||||||
| 11103 Street Lighting | 1194 | Island Hwy LED lighting upgrade | - | 30,000 | 30,000 | 0% | October |
| Road Projects | |||||||
| 11105 Road Projects | 1111 | Island Hwy Stewart to Beaumont (2018 c/f design) | - | 27,066 | 27,066 | 0% | October |
| 11105 Road Projects | 1192 | Island Hwy upgrades - Hart Rd. to Wilfert Rd. | 5,716 | 30,000 | 24,284 | 19% | November |
| 11105 Road Projects | 1197 | Island Hwy protected ped path (PSB to Pr. Robert Dr.) | 3,115 | 40,000 | 36,885 | 8% | Complete |
| Other Transportation Projects | |||||||
| 11106 Other Transportation Projects | 1048 | Watkiss Way at Burnside Rd W blvd beautification | 27,783 | 25,000 | (2,783) | 111% | Complete |
| 11106 Other Transportation | 1074 | Watkiss Way improved ped walkway | 4,499 | - | (4,499) | Complete | |
| 11106 Other Transportation Projects | 1121 | Kayak launch on Shoreline Drive | 74,123 | 45,000 | (29,123) | 165% | Complete |
| 11106 Other Transportation Projects | 1196 | Electric vehicle charging stations | 37,270 | 45,000 | 7,730 | 83% | Complete |
| Signal Projects | |||||||
| 11108 Signals | 1198 | Pedestrian crossing signal - 102 Atkins Rd | 15,900 | 20,000 | 4,100 | 80% | Complete |
| SUB-TOTAL | 204,359 | 622,066 | 417,707 |
Sewer
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Lift Station Projects | |||||||
| 11702 Lift Stations | 1125 | Price Bay pump station upgrade | 67,288 | 69,000 | 1,712 | 98% | Complete |
| 11702 Lift Stations | 1187 | Hallowell pump station pump replacements | 27,458 | 30,000 | 2,542 | 92% | Complete |
| 11702 Lift Stations | 1188 | Hospital pump station kiosk replacement | 12,503 | 220,000 | 207,497 | 6% | December |
| Information Technology Projects | |||||||
| 13103 Information Technology | 4859 | Vadim iCity Utility Billing module | 10,213 | 43,600 | 33,387 | 23% | October |
| SUB-TOTAL | 117,462 | 362,600 | 245,138 |
Vehicles
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Vehicle Projects | |||||||
| 11111 Vehicles | 1058 | Electric fleet vehicle | 33,760 | 45,000 | 11,240 | 75% | Complete |
| SUB-TOTAL | 33,760 | 45,000 | 11,240 |
Collection System (Drainage)
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Collection System Projects | |||||||
| 11201 Collection System | 1190 | Drainage main replacement - Beaumont Avenue | 91,890 | 175,000 | 83,110 | 53% | October |
| 11201 Collection System | 1191 | Drainage upgrades - Chalmers Court | 4,484 | 15,000 | 10,516 | 30% | October |
| SUB-TOTAL | 96,374 | 190,000 | 93,626 |
Parks
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Park Improvement Projects | |||||||
| 11302 Park Improvements | 0705 | Portage Park stairs - from Glentana Road (2018 c/f) | 3,596 | 10,753 | 7,157 | 33% | Complete |
| 11302 Park Improvements | 1127 | MacLennan Trail improvements - guard rails and paving | - | 20,000 | 20,000 | 0% | October |
| 11302 Park Improvements | 1165 | Beaumont access improvements | - | 40,000 | 40,000 | 0% | November |
| 11302 Park Improvements | 1166 | Portage Inlet Linear Park improvements | 4,061 | 12,000 | 7,939 | 34% | October |
| 11302 Park Improvements | 1175 | Park signage and branding implementation (2018 c/f) | - | 5,000 | 5,000 | 0% | December |
| 11302 Park Improvements | 1176 | Eagle Creek trail - circular path completion | - | 55,000 | 55,000 | 0% | November |
| 11302 Park Improvements | 1177 | Playground replacement program - Marler Park | 8,163 | 85,000 | 76,837 | 10% | November |
| 11302 Park Improvements | 1178 | Centennial Park improvements - access & amenities | 5,515 | 16,000 | 10,485 | 34% | November |
| 11302 Park Improvements | 1179 | Garry Oak Meadows Park improvements | 2,726 | 6,000 | 3,274 | 45% | November |
| 11302 Park Improvements | 3145 | View Royal Park Bike Skills Park (2018 c/f) | 168,882 | 150,000 | (18,882) | 113% | October |
| 11302 Park Improvements | 3146 | View Royal Park toilets | 2,103 | 3,000 | 897 | 70% | Complete |
| Park Development Projects | |||||||
| 11303 Park Development | 1147 | Chilco trails implementation plan (2018 c/f) | 38,175 | 54,356 | 16,181 | 70% | Complete |
| Park Vehicle Projects | |||||||
| 11304 Park Vehicles | 1067 | Kubota tractor/backhoe | - | 81,600 | 81,600 | 0% | November |
| 11304 Park Vehicles | 1132 | 1/2 ton pickup replacement | - | 35,000 | 35,000 | 0% | November |
| 11305 Park Vehicles | 1167 | Ford F350 Additions | 8,862 | - | (8,862) | Complete | |
| Building Improvement Projects | |||||||
| 11401 Building Improvements | 1138 | Council Chamber - renovation | 4,289 | 23,837 | 19,548 | 18% | Complete |
| 11401 Building Improvements | 1195 | Town Hall change room expansion | 15,176 | 15,000 | (176) | 101% | Complete |
| SUB-TOTAL | 261,548 | 612,546 | 350,998 |
Fire Services
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Fire Building Projects | |||||||
| 12101 Fire - Buildings | 1046 | Parking lot expansion | - | 52,000 | 52,000 | 0% | November |
| Fire Vehicle Projects | |||||||
| 12102 Fire - Vehicles | 0834 | 2009 Chevy Tahoe replacement | 68,057 | 85,000 | 16,943 | 80% | November |
| 12102 Fire - Vehicles | 1033 | Rescue Truck (2018 c/f) | 379,796 | 900,000 | 520,204 | 42% | February 2020 |
| Fire Furniture and Equipment Projects | |||||||
| 12103 Fire - Furniture and Equip | 1032 | Public Safety Building - Public art (2018 c/f) | - | 35,000 | 35,000 | 0% | October |
| 12103 Fire - Furniture and Equip | 1101 | Self-contained breathing apparatus cylinders | 22,080 | 25,000 | 2,920 | 88% | Complete |
| 12103 Fire - Furniture and Equip | 1150 | Fire hose replacement | - | 12,000 | 12,000 | 0% | October |
| 12103 Fire - Furniture and Equip | 1181 | Fire dispatch - mobile terminal year 2 | 14,099 | 14,000 | (99) | 101% | Complete |
| SUB-TOTAL | 484,032 | 1,123,000 | 638,968 |
Emergency Services
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Emergency Program Equipment Projects | |||||||
| 12202 Emerg Prog Equipment | 0850 | EOC equipment and supplies | 11,170 | 14,000 | 2,830 | 80% | Complete |
| SUB-TOTAL | 11,170 | 14,000 | 2,830 |
Police Services
Page 41
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Police Machinery and Equipment Projects | |||||||
| 12301 Police Services | 1152 | RCMP building renovation | - | 154,000 | 154,000 | 0% | Ongoing |
| SUB-TOTAL | - | 154,000 | 154,000 |
Administration / General Government
| 2019 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion |
|---|---|---|---|---|---|---|---|
| Administration Projects | |||||||
| 13101 Administration - Softwate | 1038 | Electronic Records Mgmt Software implementation and training | - | 165,000 | 165,000 | 0% | 2020 |
| Information Technology Hardware Projects | |||||||
| 13103 Information Tech - Hardware | 1044 | IT infrastructure hardware replacements (server/switches) | 800 | 18,700 | 17,900 | 4% | October |
| 13103 Information Tech - Hardware | 1070 | IT workstation evergreening | 20,147 | 40,000 | 19,853 | 50% | October |
| 13103 Information Tech - Hardware | 1185 | Mobile inspection hardware and GIS (2018 c/f) | 884 | 5,000 | 4,116 | 18% | Complete |
| Information Technology Software Projects | |||||||
| 13103 Information Tech - Software | 1039 | Microsoft Office Productivity Suite upgrade | 60,291 | 129,400 | 69,109 | 47% | 2020 |
| 13103 Information Tech - Software | 1186 | Secondary suites online renewal (2018 c/f) | - | 25,000 | 25,000 | 0% | 2020 |
| 13103 Information Tech - Software | 4858 | Vadim iCity Online upgrade | - | 33,200 | 33,200 | 0% | November |
| Land Acquisition Projects | |||||||
| 13201 Land Acquisitions | 1054 | Land Acquisitions - Legal (2018 c/f) | 5,216 | 100,000 | 94,784 | 5% | December |
| SUB-TOTAL | 87,338 | 516,300 | 428,962 |
| Total 2019 Capital Projects | | | 1,296,043 | 3,639,512 | 2,343,469 | | |