Quarterly financial update report monitoring the results of Town operations and capital project progress.

6.2.3.b) Budget Variance and Capital Projects Update Report to June 30, 2019
$8,862 actual expenditure for Ford F350 additions$4,499 actual for Watkiss Way improved pedestrian walkwayVariances due to 2018 project carry-forwards

TOWN OF VIEW ROYAL

Page 62–63

Finance & Administration Report

TO: Committee of the Whole DATE: July 4, 2019 FROM: Steven Vella, Manager of Accounting MEETING DATE: July 9, 2019

Page 62–63

BUDGET VARIANCE AND CAPITAL PROJECTS UPDATE REPORT TO JUNE 30, 2019

RECOMMENDATION:

THAT the Committee receive the Budget Variance and Capital Projects Update Report to June 30, 2019 for information.

CHIEF ADMINISTRATIVE OFFICER COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding the financial results of operations and progress of capital projects to June 30, 2019.

BACKGROUND:

In April 2019 Council adopted a five-year financial plan (Bylaw 1018) that identifies revenue and expense targets and authorizes capital projects to further its strategic objectives. The attached Appendix A – Consolidated Budget Variance and Appendix B – Capital Projects Update are provided to inform Council of the financial results of delivering services and capital projects to the end of the second quarter this year.

DISCUSSION:

Analysis shows that revenues and expenses to date are within expected variances to the end of this quarter in the fiscal year with the exceptions noted below:

Project Budget Actual Variance Explanation
Ford F350 additions $0.00 $8,862 ($8,862) Project expenditures and funding not carried forward from 2018
Watkiss Way improved pedestrian walkway $0.00 $4,499 ($4,499) Project expenditures and funding not carried forward from 2018

Staff will continue to monitor financial results to ensure delivery of services and capital projects within the allocated budgets. Where applicable, staff will seek budget amendment approval in due course once the final funding requirements are known.

Should corrective measures be necessary, staff will inform Council of the effect, if any, on service levels or project completion timelines.

RECOMMENDATION:

THAT the Committee receive the Budget Variance and Capital Projects Update Report to June 30, 2019 for information.

SUBMITTED BY:

Steven Vella, CPA, CGA Manager of Finance

REVIEWED BY:

D. Christenson, Director of Finance

Attachments: Appendix A: Consolidated Budget Variance Appendix B: Capital Projects Update