Committee of the Whole/Documents/Finance and Administration Report - Capital Project Update
Staff Report

Finance and Administration Report - Capital Project Update

December 10, 2019Page 152 sections

Staff report providing an update on capital project expenditures and projected completion dates for the year 2019.

2 APPROVAL OF AGENDA
December 5, 2019$3,639,512 total approved capital expenditures82% of planned capital projects expected to be completed in 2019

TOWN OF VIEW ROYAL

Finance and Administration Report

TO: Committee of the Whole DATE: December 5, 2019 FROM: Steven Vella, Manager of Accounting MEETING: December 10, 2019


Page 15

Capital Project Update

RECOMMENDATION:

THAT the Committee receive the December 5, 2019 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION:

For 2019, the Town has approved capital expenditures of $3,639,512. The attached report outlines budgeted and actual expenditures to November 30, 2019 and current projected completion dates. Due to timing differences between internal reporting timelines and invoices from the vendor, there may exist variances between reported costs and actual costs of some projects. As invoices are processed, a more complete calculation of actual variances will be made.

It is expected that 82% of planned capital projects will be completed in 2019.

RECOMMENDATION:

THAT the Committee receive the December 5, 2019 Capital Project Update Report for information.

SUBMITTED BY: S. Vella, Manager of Accounting

REVIEWED BY: D. Christenson, Director of Finance