Project Summary: Information signs – three locations

September 18, 2018Page 612 sections

A discretionary project summary for increasing public awareness of park locations and amenities through signs.

2. APPROVAL OF AGENDA
Capital cost: $11,000Operational cost: $300/year for maintenance
Page 61

Project Summary

Financial Plan 2018 – 2022

Project Name: Information signs – three locations Project Number: 2-2-11106-310 CC1073 / 1-2-07250-580 Priority: Discretionary Submitted by: John Rosenberg, Director of Engineering

Executive Summary

An economic development project combining business advertising with park locations and directions for people in three strategic locations throughout View Royal.

Business problem and opportunity

n/a

Proposed project objectives

To increase awareness for public park locations and amenities.

Business risks

n/a

Proposed sources of funding

  • Capital: Casino revenue
  • Operational: Taxation

Note: Potential revenue generated from the sale of advertising space would reduce funding required from taxation.

Costs and benefits

Costs FY1 FY2 FY3 FY4 FY5 5-year Total
Capital 11,000 11,000
Operational 300 300 300 300 1,200
Total 11,000 300 300 300 300 12,200

Benefits

  • Tangible:
  • Intangible:

Recommendation

THAT the Committee recommend the 2018-2022 Financial Plan include the information signs – three locations project with capital costs to be funded by Casino revenue and ongoing maintenance funded by taxation.