Capital Projects Update

June 12, 2018Pages 44–455 sections

A staff report tracking the progress and budget of various 2018 capital projects including transportation, sewer, and park improvements.

2. APPROVAL OF AGENDA
June 5, 2018$3,099,085 total budget for 2018 capital projectsTotal expenditures to May 31, 2018 were $318,053

TOWN OF VIEW ROYAL

Page 44–45

Finance and Administration Report

TO: Committee of the Whole DATE: June 5, 2018 FROM: D. Christenson, Director of Finance MEETING: June 12, 2018

Page 44–45

Capital Projects Update

RECOMMENDATION:

THAT the Committee receive the June 5, 2018 Capital Projects Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To inform Council regarding the status of 2018 capital projects and anticipated completion dates.

INFORMATION:

Included in the approved 2018-2022 Financial Plan is a total of $3,099,085 for 2018 capital projects. The attached report outlines budgeted and actual expenditures by capital project to May 31, 2018 with anticipated completion dates. Note that in some instances a capital project may be listed as “Complete” but the year to date expenditures are significantly lower than the budget for that project. This is due to the practice of only processing payment after services are acceptably delivered and goods received. Future reports will show updated expenditures as they occur. Staff will continue to monitor progress and will inform Council in a timely manner of any anticipated significant variances from budget.

RECOMMENDATION:

THAT the Committee receive the June 5, 2018 Capital Project Update Report for information.

SUBMITTED BY: Dawn Christenson, Director of Finance

REVIEWED BY: K. Anema, Chief Administrative Officer


Page 44–45

Town of View Royal

Page 44–45

Capital Projects Update Report

For period ending May 31, 2018

2018 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
Transportation
Sidewalks
11101 Sidewalks 1139 Stoneridge Development Sidewalk Replcmt - 90,000 90,000 0% June
Bus Shelters
11104 Bus Shelters 058 Installation - Island Hwy at Shoreline School - 25,000 25,000 0% September
Road Reconstruction
11105 Road Projects 1111 Island Hwy Stewart to Beaumont - 50,000 50,000 0% July
11105 Road Projects 1182 Island Hwy Protected Path-Heddle - 50,000 50,000 0% August
Miscellaneous
11106 Other Transportation Projects 1074 Watkiss Way Improved Ped Walkway & Light - 20,000 20,000 0% August
11106 Other Transportation Projects 0603 Helmcken Rd - Blvd repair - 15,000 15,000 0% Complete
11106 Other Transportation Projects 1073 Signage Kiosks 3 locations - 11,000 11,000 0% September
11106 Other Transportation Projects 1121 Kayak launch on Shoreline Drive - 20,000 20,000 0% September
Electrical
11108 Signals 1118 Isl Hwy at Heddle ped crosswalk 18,752 80,600 61,848 23% Complete
11108 Signals 1158 Isl Hwy/Colwood Interchange Flash - 20,000 20,000 0% Complete
SUB-TOTAL 18,752 381,600 362,848 5%
Sewer
11702 Lift Stations 1125 Price Bay Pump Stn upgrade 8,962 385,970 377,008 2% December
11702 Lift Stations 1163 Packers and Wilfert Pump Stn pumps - 35,000 35,000 0% July
11702 Lift Stations 1180 Glenairlie Thetis Cove Pump Stn - 24,000 24,000 0% September
SUB-TOTAL 8,962 444,970 436,008 2%
Parks
Park Improvements
11302 Park Improvements 0705 Portage Park stairs - 25,000 25,000 0% October
11302 Park Improvements 0822 View Royal Park - Loop Trail E - 45,000 45,000 0% August
11302 Park Improvements 1127 MacLennan Trail Improvements - 20,000 20,000 0% November
11302 Park Improvements 1164 Centennial Park Playground 7,968 150,000 142,032 5% July
11302 Park Improvements 1166 Portage Inlet Linear Park - 30,000 30,000 0% October
11302 Park Improvements 1175 Park Signage and Branding Implementation - 5,000 5,000 0%
11302 Park Improvements 3145 View Royal Park Bike Skills Path - 50,000 50,000 0% September
Park Development
11303 Park Development 1028 View Royal Park 162,696 150,000 (12,696) 108% June
11303 Park Development 1147 Chilco Trails Implementation Plan - 140,000 140,000 0% September
Park Vehicles
11304 Park Vehicles 1167 Parks Vehicle Replacement Plan - 15,000 15,000 0% June
Improvement to Public Buildings
11401 Building Improvements 1138 Council Chamber - renovation - 30,000 30,000 0% September
SUB-TOTAL 170,664 660,000 489,336 26%
Fire Services
Buildings
12101 Fire - Buildings 1149 Training Ground 72,075 94,500 22,425 76% December
Vehicles
12102 Fire - Vehicles 1033 Fire Engine - 900,000 900,000 0% 2019
Furniture & Equipment
12103 Fire - Furniture and Equip 1032 Public Safety Building - Public art - 35,000 35,000 0% December
12103 Fire - Furniture and Equip 1181 Fire dispatch-mobile data term - 14,000 14,000 0% October
12103 Fire - Furniture and Equip 4450 Security Cameras 6,147 12,500 6,354 49% October
SUB-TOTAL 78,222 1,056,000 977,778 7%
Emergency Services
Program Equipment
12202 Emerg Prog Equipment 0849 Emerg Prog - Equipment and Supplies - 25,000 25,000 0% October
SUB-TOTAL - 25,000 25,000 0%
Police Services
12301 Police Services 1152 RCMP 2018 capital projects - 57,400 57,400 0% Ongoing
SUB-TOTAL - 57,400 57,400 0%
Administration / General Government
Administration
13101 Administration 1038 Electronic Records Mgmt System - 21,000 21,000 0% December
Information Technology
13103 Information Technology 1037 VOIP telephony upgrade - 11,000 11,000 0% September
13103 Information Technology 1044 Information technology infrastructure hardware replacement - 16,500 16,500 0% July
13103 Information Technology 1070 Information technology workstation ever-greening 17,488 40,000 22,512 44% June
13103 Information Technology 1183 Offsite business continuity - 15,300 15,300 0% September
13103 Information Technology 1184 Town Hall data cabling upgrade 23,964 33,800 9,836 71% Complete
13103 Information Technology 1185 Mobile inspection hardware and integration - 44,215 44,215 0% December
13103 Information Technology 1039 Microsoft Office productivity suite upgrade - 165,000 165,000 0% December
13103 Information Technology 1186 Secondary Suites online renewal - 20,300 20,300 0% December
Land Acquisitions
13201 Land Acquisitions 1013 Craigflower Manor frontage acquisition - 7,000 7,000 0% June
13201 Land Acquisitions 1054 Land Acquisitions - Legal - 100,000 100,000 0% Ongoing
SUB-TOTAL 41,452 474,115 432,663 9%
Total 2018 Capital Projects 318,053 3,099,085 2,781,032 10%