Staff Report
CAPITAL PROJECTS UPDATE – DECEMBER 2011
December 13, 2011Pages 31–322 sections
Staff report providing highlights on the status of major engineering projects, including the Island Highway and Craigflower Bridge.
December 9, 2011Island Highway Improvement Project - minor deficiencies being completedView Royal Park tender awarded
TOWN OF VIEW ROYAL COMMITTEE OF THE WHOLE REPORT
TO: Committee of the Whole DATE: December 9, 2011 FROM: E. McCusker, Director of Engineering MEETING DATE: December 13, 2011
Page 31–32
CAPITAL PROJECTS UPDATE – DECEMBER 2011
RECOMMENDATION:
THAT the Capital Projects Update Report – December, 2011 be received.
PURPOSE OF REPORT:
To inform the Committee of the status of Capital Projects
PROJECT INFORMATION:
The capital projects are listed in the spreadsheet attached to this report. The following items are highlighted for the Committee’s information:
- Island Highway Improvement Project – Minor deficiencies being completed
- Craigflower Bridge – Open House completed, compiling feedback.
- Council Chambers sound system – phase one complete – phase two to Budget
- View Royal Park – Tender awarded – work commencing week of Dec 12th
- Burnett Road Design – in review of 50% Design
RECOMMENDATION:
THAT the Capital Projects Update Report – December, 2011 be received.
SUBMITTED BY:
E. McCusker, Director of Engineering
REVIEWED BY:
K. Anema, Chief Administrative Officer