Committee of the Whole/Documents/Engineering Capital Projects 2011 Spreadsheet
Appendix

Engineering Capital Projects 2011 Spreadsheet

December 13, 2011Page 331 section

A detailed tracking list of 2011 engineering projects categorized by type (sidewalks, roads, sewer, etc.) with current status and next steps.

2 APPROVAL OF AGENDA
Craigflower Bridge Design: 2012 statusAdmirals Pump Station: Completed

Engineering Capital Projects 2011

Table of Engineering Capital Projects 2011
Table of Engineering Capital Projects 2011
Project Next Step Notes Status
Sidewalks / Cycling
Island Highway sidewalk - Pedestrian Overpass to Glentana Completed
Stormont sidewalk, side of Winemaker Completed
Chancellor sidewalk, drainage, lighting, bike lanes Completed
Burnett Rd sidewalk from OIH to View Royal Park Design is at 50% stage
Portage Park Cycling Trail (IHIP) Completed
Street Lighting - -
CHIP Lighting/Sidewalks - Poles and Bases (Cobra Head Davit Style) Completed
Relamping & service panel repairs - relamping only in 2014 and 2015 Completed
Road Reconstruction -
Island Highway - Beaumont to Ped Overpass (IHIP) minor deficiencies
IHIP Retaining Wall - public art feature 35,585 Completed
IHIP Non-Grant Capital Costs - house connections 110,000 Completed
Pheasant Lane Traffic Circle Apron Rebuild Completed
Norquay Rd - paving repairs Completed
Miscellaneous - -
Welcome sign Colwood Border awaiting brass plaques Dec31st
Speed Sign - automated and moveable - 2011 hardware mount 5 loc's Installed Watkiss/Talcott Completed
Orthophotos 16,500 Completed
Annual Pavement Rehabilitation -
Isl Hwy Colwood border to Six Mile Rd. (additional CHIP) 100,000 Final inspection
Glentana Rd from Admirals Rd to CT entrance (partner with Develop) Completed
Signals -
Hart Rd - Traffic Signal - Developer Contribution $185,000 Completed
Watkiss/Creed - Crosswalk Upgrade (signal) Completed
Bridge -
Craigflower Bridge Design Open House Completed Compiling feedback 2012
Sewer
Admirals Pump Station (134 Hallowell Rd) Completed
Lift station replacement - Midwood Pump Station Completed
Pump Station Upgrade - 2011 Design 4 Rebuilds Designs in progress Dec15th
Sewer pump upgrades Completed
Parks
Dukrill Trail Water Access / Stairs Tower fence will begin Nov 14th Nov 18th
Limekiln Cove - 2011 Viewing Platform/ 2012 - Dock & Kayak Launch Structural review Structural Review Completed Dec7 Dec 23rd
Stewart Access - Part 3 Completed
View Royal Park - Implementation of VR Park Plan Awarded Dec 23rd
Vehicle Decals Dec 31st
Town Hall Sign Awaiting brass plaque Dec 23rd
Welland Park Fencing and minor landscaping Dec 23rd
Computer - GIS system Ongoing Ongoing
Council Chambers sound system Installation Phase 2 of 2 in 2012 Dec 13th
Page 33
Extracted from: 2011 12 13 Committee of the Whole Agenda