Committee of the Whole/Documents/Finance and Administration Report: Capital Project Update
Staff Report

Finance and Administration Report: Capital Project Update

November 8, 2016Pages 38–392 sections

A financial report providing an update on the expenditures and projected completion dates for various municipal capital projects as of October 2016.

2. APPROVAL OF AGENDA
Total 2016 Capital Budget: $2,455,987Actual YTD expenditures to October 28: $1,281,771Island Highway Pedestrian overpass design project: $92,000 budget

FINANCE AND ADMINISTRATION REPORT

TO: Committee of the Whole FROM: Michael Dillabaugh, Director of Finance DATE: October 28, 2016 MEETING DATE: November 8, 2016

CAPITAL PROJECT UPDATE

Staff Recommendation: THAT the Committee receive the October 2016 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER'S COMMENTS

I concur with the recommendation.

PURPOSE OF REPORT

To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION

The attached report outlines expenditures to October 28, 2016 and current projected completion dates. Year to date expenditures are within budget and we will continue to closely monitor expenditures throughout the year to ensure capital projects are on time and on budget as at the end of the fiscal year.

Page 38–39

2016 Capital Projects

2016 Capital Projects table
2016 Capital Projects table
Project G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD Oct 28 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Transportation
Road Reconstruction
Watkiss Way at Burnside Road West Intersection Reconstruction (1900 Watkiss Way Dvlpmt) 2-2-11105 1085 39,925 37,986 - 1,939 Complete
Watkiss Way East of Burnside Road West Lot C Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1086 145,000 142,248 - 2,752 Complete
Watkiss Way at Eagle Creek Frontage Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1087 57,998 9,198 - 48,800 Complete
Burnett Rd-Pheasant Ln (Old Island Hwy to VR Park)-Construction 2-2-11105 1109 350,000 36,536 60,000 373,464 December
Island Highway Pedestrian overpass to Shoreline Drive- Design 2-2-11105 1110 35,000 - (35,000) - December
Island Highway Stewart to Beaumont- Design 2-2-11105 1111 35,000 - 57,000 92,000 December
Watkiss Way west of Burnside Road (asphalt curb and paved shoulder) 2-2-11105 1112 15,000 12,536 - 2,464 Complete
Annual Pavement Rehabilitation
Watkiss Way EB West of Helmcken Road (Eagle Creek) 2-2-11107 1107 55,000 49,915 - 5,085 Complete
Burnside Rd West: Kami Court to Border with Saanich) 2-2-11107 1114 45,000 43,755 - 1,245 Complete
Structures
Admirals Safety Improvements 2-2-11105 1072 200,000 159,624 - 40,376 Complete
Craigflower Bridge Replacement Project (CT) - Land Acquisition 2-2-11109 1013 65,000 55,148 - 9,852 Complete
Helmcken Rd at Burnside Rd West Traffic Island 2-2-11108 1115 25,000 26,422 - (1,422) Complete
E & N Trail stairs 2-2-11108 1108 15,000 114,577 - (99,577) Complete
Electrical
Seasonal Lighting on Helmcken Road North of TCH and Watkiss 2-2-11103 1093 12,712 1,614 - 11,098 December
Island Highway at Knollwood Rd/Kislingbury Ln UPS 2-2-11108 1116 11,000 10,979 - 21 Complete
Six Mile Road at Chilco Road Flashing Pedestrian Crossing 2-2-11108 1117 22,500 11,534 - 10,966 Complete
Island Highway at Heddle Ped Crosswalk 2-2-11108 1118 25,000 385 - 24,615 December
Kami Court & Burnside Crosswalk 2-2-11108 1119 30,000 22,472 - 7,528 Complete
Miscellaneous
ECV - To complete Park Trail (to Little Rd at North End) (phase 2) 2-2-11108 1120 15,000 - - 15,000 2017
Kayak Launch on Shoreline Drive 2-2-11108 1121 50,000 16,297 - 33,703 December
Quincy Street Pedestrian Access 2-2-11108 1122 1,000 - - 1,000 December
Banners 2-2-11108 1123 5,000 4,601 - 399 December
SUB-TOTAL TRANSPORTATION 1,255,135 755,828 82,000 581,307
Drainage
View Royal Avenue (Beaumont Avenue to Stewart Avenue) - Design 2-2-11201 1124 20,000 - - 20,000 December
SUB-TOTAL DRAINAGE 20,000 - - 20,000
Sewer
Price Bay Pump Station Upgrade (cost update) 5-2-11702 1125 425,000 8,917 - 416,083 December
Helmcken Bay and Helmcken Park Pump Station Pumps 5-2-11702 1105 45,000 37,728 - 7,272 Complete
SUB-TOTAL SEWER 470,000 46,645 - 423,355
Parks
Improvements to easements
Dukrill Trail Water Access / Stairs 2013 2-2-11301 1126 12,000 - - 12,000 November
Park Improvements
MacLennan Trail Improvements - Paving Trail Sections 2-2-11302 1127 20,000 15,987 - 4,013 November
Fencing - general fencing to start defining the Town's areas 2-2-11302 1128 15,000 - - 15,000 December
Playgrounds - replacement program 2-2-11302 1129 60,000 3,275 - 56,725 November
Robin Hill Park & Edwards Park - RHP - pave entrance from Haagensen Court. EP - pave entrance apron from BamfordCourt 2-2-11302 1130 8,500 7,586 - 914 Complete
Edwards Park Summit fence 2-2-11302 1131 5,000 2,539 - 2,461 November
Park Development
View Royal Park - implementation of VR Park Plan (Parking Lot Paving and tree irrigation) 2-2-11303 1028 50,000 41,760 - 8,240 Complete
View Royal Park (Preac) - Fitness Stations/Equipment 2-2-11302 1099 80,000 65,393 - 14,807 Complete
Park Vehicles
New 1/2 Ton Pickup and accessories 2-2-11304 1132 30,000 - - 30,000 December
Improvements to Public Buildings
Park Shop Shed Repair 2-2-11401 1133 13,500 - - 13,500 December
SUB-TOTAL PARKS 294,000 136,540 - 157,460
Fire Services
Buildings
Public Safety Building ($256,552 carryforward of approved budget from previous years) 2-2-12101 1032 - 193,183 256,552 63,369 December
Vehicles
Vehicle Replacement - Fire Engine Replacement 2-2-12102 1033 100,000 110,954 18,000 7,046 November
Bylaw
Bylaw Enforcement
Body Cameras 2-2-12401 1134 3,000 - - 3,000 September
Police Services
RCMP Building - Top Floor Works 2-2-12301 1103 5,000 - - 5,000 December
SUB-TOTAL (Public Safety) 108,000 304,137 274,552 78,415
Administration / General Government
Annual Information Services Replacement Program 2-2-13103 1070 50,000 10,336 - 39,664 December
IT Strategic Plan Implementation 2-2-13103 1135 154,852 26,773 - 128,079 First year of three year project
Flag Poles 2-2-13104 1136 2,000 - - 2,000 December
Aerial Photo 2-2-13104 1137 2,000 1,511 - 489 November
Land Acquisitions
Misc. Land Acquisition 2-2-13201 1045 100,000 - - 100,000 December
SUB-TOTAL ADMIN/LAND 308,852 38,620 - 270,232
TOTAL 2016 CAPITAL PROJECTS 2,455,987 1,281,771 356,552 1,530,768
Page 38–39

Document Images

(3)
Document image
Document image
Document image