A report providing an update on capital project expenditures and projected completion dates as of November 30, 2016.

6.2.3.a Capital Project Update (Report dated December 5, 2016 from the Director of Finance)
December 5, 2016Total 2016 Capital Projects Budget: $2,455,987YTD actual expenditures to Nov 30: $1,426,713Cancelled project: Island Highway Pedestrian overpass to Shoreline Drive

TOWN OF VIEW ROYAL Finance and Administration Report

TO: Committee of the Whole DATE: December 5, 2016 FROM: Michael Dillabaugh, Director of Finance MEETING DATE: December 13, 2016

Page 12–13

CAPITAL PROJECT UPDATE

RECOMMENDATION:

THAT the Committee receive the December 5, 2016 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION:

The attached report outlines expenditures to November 30, 2016 and current projected completion dates. Year to date expenditures are within budget and we will continue to closely monitor expenditures throughout the year to ensure capital projects are on time and on budget as at the end of the fiscal year.

SUBMITTED BY: M. Dillabaugh, Director of Finance

REVIEWED BY: K. Anema, Chief Administrative Officer

Page 12–13

2016 Capital Projects

Project Category / Description G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD Nov 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Transportation
Road Reconstruction
Watkiss Way at Burnside Road West Intersection Reconstruction (1900 Watkiss Way Dvlpmt) 2-2-11105 1085 39,925 49,266 (9,341) Complete
Watkiss Way East of Burnside Road West Lot C Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1086 145,000 145,308 (308) Complete
Watkiss Way at Eagle Creek Frontage Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1087 57,998 9,198 48,800 Complete
Burnett Rd-Pheasant Ln (Old Island Hwy to VR Park)-Construction 2-2-11105 1109 350,000 42,211 60,000 367,789 December
Island Highway Pedestrian overpass to Shoreline Drive- Design 2-2-11105 1110 35,000 - (35,000) - Cancelled
Island Highway Stewart to Beaumont- Design 2-2-11105 1111 35,000 - 57,000 92,000 2017
Watkiss Way west of Burnside Road (asphalt curb and paved shoulder) 2-2-11105 1112 15,000 15,826 (826) Complete
Annual Pavement Rehabilitation
Watkiss Way EB West of Helmcken Road (Eagle Creek) 2-2-11107 1107 55,000 49,915 5,085 Complete
Burnside Rd West: Kami Court to Border with Saanich) 2-2-11107 1114 45,000 43,755 1,245 Complete
Structures
Admirals Safety Improvements 2-2-11105 1072 200,000 200,433 (433) Complete
Craigflower Bridge Replacement Project (CT) - Land Acquisition 2-2-11109 1013 65,000 55,148 9,852 Complete
Helmcken Rd at Burnside Rd West Traffic Island 2-2-11106 1115 25,000 26,873 (1,873) Complete
E & N Trail stairs 2-2-11106 1108 15,000 114,577 (99,577) Complete
Electrical
Seasonal Lighting on Helmcken Road North of TCH and Watkiss 2-2-11103 1093 12,712 1,614 11,098 Complete
Island Highway at Knollwood Rd/Kislingbury Ln UPS 2-2-11108 1116 11,000 12,474 (1,474) Complete
Six Mile Road at Chilco Road Flashing Pedestrian Crossing 2-2-11108 1117 22,500 24,055 (1,555) Complete
Island Highway at Heddle Ped Crosswalk 2-2-11108 1118 25,000 385 24,615 2017
Kami Court & Burnside Crosswalk 2-2-11108 1119 30,000 36,543 (6,543) Complete
Miscellaneous
ECV - To complete Park Trail (to Little Rd at North End) (phase 2) 2-2-11106 1120 15,000 - 15,000 2017
Kayak Launch on Shoreline Drive 2-2-11106 1121 50,000 16,297 33,703 2017
Quincy Street Pedestrian Access 2-2-11106 1122 1,000 - 1,000 December
Banners 2-2-11106 1123 5,000 4,686 314 Complete
SUB-TOTAL 1,255,135 848,563 82,000 488,572
Drainage
View Royal Avenue (Beaumont Avenue to Stewart Avenue) - Design 2-2-11201 1124 20,000 833 19,167 December
SUB-TOTAL 20,000 833 - 19,167
Sewer
Price Bay Pump Station Upgrade (cost update) 5-2-11702 1125 425,000 33,767 391,233 December
Helmcken Bay and Helmcken Park Pump Station Pumps 5-2-11702 1105 45,000 37,728 7,272 Complete
SUB-TOTAL 470,000 71,495 - 398,505
Parks
Improvements to easements
Dukrill Trail Water Access / Stairs 2013 2-2-11301 1126 12,000 - 12,000 December
Park improvements
MacLennan Trail Improvements - Paving Trail Sections 2-2-11302 1127 20,000 21,044 (1,044) Complete
Fencing - General fencing to start defining the Town's areas 2-2-11302 1128 15,000 8,613 6,387 December
Playgrounds - replacement program 2-2-11302 1129 60,000 3,275 56,725 2017
Robin Hill Park & Edwards Park - RHP - pave entrance from Haagensen Court. EP - pave entrance apron from BamfordCourt 2-2-11302 1130 8,500 7,586 914 Complete
Edwards Park Summit fence 2-2-11302 1131 5,000 2,539 2,461 December
Park Development
View Royal Park - Implementation of VR Park Plan (Parking Lot Paving and tree irrigation) 2-2-11303 1028 50,000 41,760 8,240 Complete
View Royal Park (Preac) - Fitness Stations/Equipment 2-2-11302 1099 80,000 65,393 14,607 Complete
Park Vehicles
New 1/2 Ton Pickup and accessories 2-2-11304 1132 30,000 - 30,000 December
Improvements to Public Buildings
Park Shop Shed Repair 2-2-11401 1133 13,500 - 13,500 December
SUB-TOTAL 294,000 150,210 - 143,790
Fire Services
Buildings
Public Safety Building ($256,552 carryforward of approved budget from previous years) 2-2-12101 1032 192,437 256,552 64,115 December
Vehicles
Vehicle Replacement - Fire Engine Replacement 2-2-12102 1033 100,000 115,587 18,000 2,413 Complete
Bylaw
Bylaw Enforcement
Body Cameras 2-2-12401 1134 3,000 - 3,000 Complete
Police Services
RCMP Building - Top Floor Works 2-2-12301 1103 5,000 - 5,000 December
SUB-TOTAL 108,000 308,024 274,552 74,528
Administration / General Government
Annual Information Services Replacement Program 2-2-13103 1070 50,000 11,082 38,918 December
IT Strategic Plan implementation 2-2-13103 1135 154,852 33,070 121,782 First year of three year project
Flag Poles 2-2-13104 1136 2,000 1,925 76 December
Aerial Photo 2-2-13104 1137 2,000 1,511 489 December
Land Acquisitions
Misc. Land Acquisition 2-2-13201 1045 100,000 - 100,000 December
SUB-TOTAL 308,852 47,588 261,264
TOTAL 2016 CAPITAL PROJECTS 2,455,987 1,426,713 356,552 1,385,826