This site is in beta — data may be incomplete and features are still being added.
Committee of the Whole/Documents/Attachment 4. Underground Parking Plan – Alan Lowe Architect
Appendix

Attachment 4. Underground Parking Plan – Alan Lowe Architect

April 12, 2022Page 2552 sections

An architectural plan showing the layout of the underground parking area and bicycle rack placement at 280 Island Highway.

Address: 280 Island HighwayTotal stalls: 40 (33 underground, 7 surface)

RESIDENTIAL DEVELOPMENT

280 ISLAND HIGHWAY, VICTORIA, BC

UNDERGROUND PARKING

Project Information

  • Project No.: 15-445
  • Date: 25 OCT 2019
  • Scale: AS NOTED
  • Sheet No.: A2.0
  • Drawn by: JW-AA
  • Checked by: LOWE
  • Architect: alan lowe architect inc., 118 - 21 Erie Street, Victoria, British Columbia, t 250.360.2888

Issue / Revisions

No. Issued / Revisions Date
1 DEVELOPMENT PERMIT 11 MAY '16
2 DEVELOPMENT PERMIT 31 MAY '16
3 DEVELOPMENT PERMIT 9 JUNE '16
4 DEVELOPMENT PERMIT 9 SEPT '16
5 FOUNDATION PERMIT 30 MARCH '17
6 BUILDING PERMIT 20 JUNE '17
7 BUILDING PERMIT 18 AUG. '17
8 ISSUED FOR CONSTRUCTION 15 FEB. '18
9 ISSUED FOR CONSTRUCTION 19 APRIL '18
10 ISSUED FOR CONSTRUCTION 1 MAY '18
11 ISSUED FOR CONSTRUCTION 7 MAY '18
12 ISSUED FOR CONSTRUCTION 5 JULY '18
13 DP AMENDMENT 25 OCT '19
14 DEVELOPMENT VARIANCE 18 FEB '22

WALL ASSEMBLY SCHEDULE:

FLOOR ASSEMBLIES:

  • F1 SLAB ON GRADE:
    • REINFORCED CONCRETE SLAB AS PER STRUCTURAL DRAWINGS
    • 10 MIL POLY MOISTURE BARRIER
    • 2" [51] SAND BINDING
    • 6" [100] COMPACT GRANULAR FILL
    • UNDISTURBED BEARING OR COMPACT ENGINEERED FILL
  • F2 WOOD FLOOR ASSEMBLY:
    • (F.R.R. 1 HR. - STC.56)
    • FINISHED FLOORING AS PER FINISH SCHEDULE
    • 1 1/2" (38mm) CONCRETE OVERLAY
    • FLOOR SYSTEM (SEE STRUCTURAL)
    • METAL RESILIENT FURRING CHANNELS @ 600 O/C
    • 2 LAYERS 15.9 mm TYPE 'X' G.W.B.
    • FLOOR TYPE F19b B.C.B.C. 2012
  • F3a CONCRETE SUSPENDED SLAB (OCCUPIED SPACE - HEATED):
    • FINISHED FLOOR COVERING
    • REINFORCED CONCRETE SLAB - SEE STRUCTURAL
    • min. R-12 SPRAY APPLIED NON-COMBUSTIBLE INSULATION.
  • F3b CONCRETE SUSPENDED SLAB (LANDSCAPE AREA):
    • EARTH FILL (SEE LANDSCAPE)
    • 4" P GRAVEL WITH FILTER CLOTH
    • DRAINMAT
    • 2PLY TORCH-ON MEMBRANE
    • REINFORCED CONCRETE SLAB - SEE STRUCTURAL
  • F4 SUSPENDED DECK:
    • 60mil VINYL DECK MEMBRANE
    • FLOOR SYSTEM (SEE STRUCTURAL)
    • P.F.M. VENTED SOFFIT
  • F5 INTERIOR FLOOR OVER EXTERIOR SPACE:
    • (F.R.R. 1 HR. - STC.56)
    • FINISHED FLOORING AS PER FINISH SCHEDULE
    • 1 1/2" (38mm) CONCRETE OVERLAY
    • FLOOR SYSTEM (SEE STRUCTURAL)
    • SPRAY FOAM INSULATION TO JOIST CAVITIES (R30)
    • METAL SOFFIT
  • F6 DECK OVER INTERIOR SPACE:
    • CONCRETE PAVERS ON PEDESTALS
    • 2 PLY SBS MODIFIED BITUMINOUS MEMBRANE
    • 180 FR GRANULAR CAP SHEET ON 180 FLAM SHEET
    • 1/4" [6mm] PROTECTION BOARD
    • 5/8" [15.9] T&G PLY ON JOISTS AS PER STRUCTURAL
    • CROSS STRAPPING TO CREATE 2.5" min. BETWEEN INSUL. AND SHEATHING
    • BATT INSULATION TO ACHIEVE R31
    • RESILIENT METAL FURRING CHANNEL
    • 2 LAYER 5/8" [15.9] TYPE 'X' G.W.B.

FOUNDATION / EXTERIOR WALL ASSEMBLIES:

  • W1 FOUNDATION WALL ASSEMBLY (BELOW GRADE):
    • GRANULAR BACKFILL
    • DRAINMAT
    • 2PLY TORCH-ON MEMBRANE
    • REINFORCED CONCRETE WALL (SEE STRUC.)
  • W2 EXTERIOR WALL ASSEMBLY (T&G WOOD RAINSCREEN):
    • HORIZONTAL T&G WOOD SIDING ON 3/4" x 3 [19 x 76] P.T. VERT. STRAPPING AT 16" [400] O/C AT WOOD STUD LOCATIONS
    • NONWOVEN POLYETHYLENE BUILDING WRAP
    • 1/2" [12.7] PLY SHEATHING
    • 5 1/2" [140] WOOD STUD AT 16" [400] O/C
    • RSI 3.9 (R-20) BATT INSULATION TO STUD CAVITIES
    • 6 MIL POLY VAPOUR / AIR BARRIER
    • 5/8" [16] G.W.B.
  • W2s W2 WITH SEISMIC SHEATHING WHERE REQUIRED. SEE STRUCTURAL.
  • W3 EXTERIOR WALL ASSEMBLY (STUCCO RAINSCREEN FINISH):
    • ACRYLIC STUCCO (3 COATS)
    • WIRE LATH C/W BUILDING PAPER SLIP SHEET
    • BREATHER BACKER BOARD
    • 1 x 3 [19 x 76] P.W.T. VERT. STRAPPING AT 8" [200] O/C
    • NONWOVEN POLYETHYLENE BUILDING WRAP
    • 1/2" [12.7] PLY SHEATHING
    • 5 1/2" [140] WOOD STUD AT 16" [400] O/C
    • RSI 3.9 (R-20) BATT INSULATION TO STUD CAVITIES
    • 6 MIL POLY VAPOUR BARRIER
    • 5/8" [16] TYPE 'X' GYPSUM WALL BOARD
    • WALL FINISH AS PER FINISH SCHEDULE
  • W3s W3 WITH SEISMIC SHEATHING WHERE REQUIRED SEE STRUCTURAL.
  • W5 CONCRETE MASONRY:
    • (HOLLOW CORE CONCRETE MASONRY UNIT - CMU):
    • 8" CONCRETE MASONRY BLOCK
    • (F.R.R. 1 1/2 HR. - STC.50)
    • WALL TYPE B1b B.C.B.C. 2012
Page 255

INT. PARTITION / SHAFT WALL ASSEMBLIES:

  • P1 PARTITION ASSEMBLY:
    • WALL TYPE W1d - STC. 32 B.C.B.C. 2012
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
    • 1/2" [12.7] G.W.B. BOTH SIDES OF
    • P1 3 1/2" [90] WOOD STUDS AT 16" [400] O.C. OR
    • P1a 5 1/2" [140] WOOD STUDS AT 16" [400] O.C.
    • 3 1/2" [89] ACOUSTIC BATT INSUL. TO STUD CAVITIES
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
  • P2 PARTY WALL ASSEMBLY:
    • (1 HR. F.R.R. STC. 61) WALL TYPE W14a B.C.B.C. 2012
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
    • 1 LAYER 5/8" [15.9] TYPE 'X' G.W.B.
    • 1 1/2" [38] x 3 1/2" [89] WOOD STUDS AT 16" [400] O.C.
    • 1" [25] AIR SEPARATION
    • 1 1/2" [38] x 3 1/2" [89] WOOD STUDS AT 16" [400] O.C.
    • 3 1/2" [89] MINERAL FIBRE INSUL. TO EACH SIDE
    • 2 LAYERS 5/8" [15] TYPE 'X' G.W.B.
  • P2s PARTY WALL- SHEAR ASSEMBLY:
    • WALL P2 WITH SEISMIC SHEATHING WHERE REQUIRED. SEE STRUCTURAL. (TYPICALLY NOTED FOR ALL WALL TYPES)
  • P3 CORRIDOR WALL ASSEMBLY:
    • (1 HR. F.R.R. STC. 56) WALL TYPE W11a B.C.B.C. 2012
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
    • 1 LAYER 5/8" [15.9] TYPE 'X' G.W.B.
    • 2 ROWS 1 1/2" [38] x 3 1/2" [89] WOOD STUDS AT 16" [400] O.C. STAGGERED ON COMMON 1 1/2" [38] x 5 1/2" [140] PLATE WITH
    • 3 1/2" [89] MINERAL FIBRE INSUL. TO STUD CAVITIES
    • RESILIENT METAL CHANNELS @ 24" [600] O/C
    • 2 LAYERS 5/8" [15] TYPE 'X' G.W.B.
  • P3s CORRIDOR WALL- SHEAR ASSEMBLY:
    • WALL P3 WITH SEISMIC SHEATHING WHERE REQUIRED.
    • NOTE: WHERE CORRIDOR WALL IS SHEAR WALL, PLACE RESILIENT CHANNELS ON SUITE SIDE, PLYWOOD CORRIDOR SIDE. SEE STRUCTURAL.
  • P4 ELEVATOR SHAFT ASSEMBLY:
    • 190 mm CMU MASONRY BLOCK (2 HR. F.R.R.) (CONCRETE FILLED)
    • WOOD BEARING WALL AS REQUIRED
    • SEE STRUCTURAL
    • 5/8" [15.9] TYPE 'X' G.W.B. TO BE APPLIED TO ALL EXPOSED FACES
  • P4a ELEVATOR SHAFT ASSEMBLY - WOOD FRAME:
    • (1 HR. F.R.R.) (S.T.C. 55 REQUIRED)
    • 2x6 WOOD WALL AS REQUIRED
    • SEE STRUCTURAL
    • 5/8" [15.9] TYPE 'X' G.W.B. TO BE APPLIED TO ALL EXPOSED FACES
  • P5 RATED WALL ASSEMBLY:
    • (1 HR. F.R.R. STC. 54) WALL TYPE W4b B.C.B.C. 2012
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
    • 1 LAYER 5/8" [15.9] TYPE 'X' G.W.B.
    • SEISMIC SHEATHING IF REQUIRED. (SEE STRUC.)
    • 1 1/2" [38] x 5.5" [140] WOOD STUDS AT 16" [400] O.C.
    • 5 1/2" [140] ACOUSTIC BATT INSUL. TO STUD CAVITIES
    • RESILIENT METAL CHANNELS @ 24" [600] O/C
    • 2 LAYERS 5/8" [15] TYPE 'X' G.W.B.
  • P6 RATED SHAFT WALL ASSEMBLY:
    • (1 HR. F.R.R. STC. 39)
    • 15.9mm SHEETROCK GYPSUM FIRECODE CORE PANELS (JOINTS FINISHED)
    • 64mm CGC C-H STUDS 25 ga. (600mm O/C)
    • 25.4 SHEETROCK GYPSUM LINER PANELS
  • P7 CONCRETE WALL:
    • SEE STRUCTURAL
  • P8 PARTITION ASSEMBLY:
    • WALL TYPE W1a - 1HR.F.R.R. STC. 36 B.C.B.C. 2012
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
    • 5/8" [15.9] TYPE 'X' G.W.B. BOTH SIDES OF
    • 3 1/2" [89] WOOD STUDS AT 16" [400] O.C.
    • 3 1/2" [89] ACOUSTIC BATT INSUL. TO STUD CAVITIES
    • WALL FINISH AS PER ROOM FINISH SCHEDULE
  • P9 PARTITION ASSEMBLY:
    • WALL TYPE W2a - 2HR.F.R.R. STC. 38 B.C.B.C. 2012
    • 2 LAYERS 5/8" [15.9] TYPE 'X' G.W.B. BOTH SIDES OF
    • 3 1/2" [89] WOOD STUDS AT 16" [400] O.C.
    • 3 1/2" [89] ACOUSTIC BATT INSUL. TO STUD CAVITIES

ROOF ASSEMBLY:

  • R1 FLAT ROOF ASSEMBLY:
    • 2 PLY SBS MODIFIED BITUMINOUS MEMBRANE
    • 180 FR GRANULAR CAP SHEET ON 180 FLAM SHEET
    • 1/4" PROTECTION BOARD
    • POLY ISO RIGID INSULATION TO ACHIEVE R28
    • SELF ADHESIVE VAPOUR BARRIER
    • 5/8" [15.9] T&G PLY ON TJI's AS PER STRUCTURAL
    • 6 mil. POLY VAPOUR BARRIER
    • 1 LAYER 5/8" [15.9] TYPE 'X' G.W.B.
  • R2 SLOPED ROOF ASSEMBLY:
    • 2 PLY SBS MODIFIED BITUMINOUS MEMBRANE
    • 180 FR GRANULAR CAP SHEET ON 180 FLAM SHEET
    • 1/4" PROTECTION BOARD
    • 5/8" [15.9] T&G PLY SHEATHING (AS PER STRUCTURAL) ON TJI's (SEE STRUCTURAL)
    • CROSS STRAPPING TO FOR 2.5" min. CLEARANCE BETWEEN INSULATION AND SHEATHING
    • R40 BATT INSUL TO JOIST CAVITIES
    • T&G WOOD SOFFIT (EXTERIOR)
    • 6 mil POLY VAPOUR / AIR BARRIER
    • 1 LAYER 5/8" [15.9] TYPE 'X' G.W.B. (INTERIOR)
    • 1/150 OF ROOF AREA TO BE VENTED 2" FROM TOP OF INSULATION TO U/S SHEATHING

Legend: BH = U-HOOK BIKE RACK

Page 255
Extracted from: 2022 04 12 Committee of the Whole Agenda - Agenda - Pdf