Council Meeting/Documents/Attachment 15. Phase 3 - Plan A5.2
Appendix

Attachment 15. Phase 3 - Plan A5.2

February 19, 2013Page 371 section

Site phasing plan for the third stage of development construction.

1 CALL TO ORDER
5 temporary car stalls for Phase 3Phase 3 under construction

VIEW ROYAL TOWNHOUSE

Rezoning Development Permit Application

Architectural site plan for View Royal Townhouse showing Phase 1 (Completed), Phase 2 (Completed), and Phase 3 (Under Construction). The plan includes building footprints, unit layouts, parking stalls, and existing structures.
Architectural site plan for View Royal Townhouse showing Phase 1 (Completed), Phase 2 (Completed), and Phase 3 (Under Construction). The plan includes building footprints, unit layouts, parking stalls, and existing structures.

Phase 3

Project number 211070
Date Oct/30/2012
Drawn by Xavier Crepe
Checked by Checker
Scale 1:200
Drawing Number A-5.2

Revision History

No. Date Description
3 Oct-30-2012 DP Revision
2 April-30-2012 DP Revision
1 Sep-08-2011 DP Revision

Note: R:/Current_drawings/211070 View Royal Townhouse/Development Permit Submission/rev# Drawing/revisions 2012/31_Oct30 DP Revision.rvt

Site Plan Details

  • PHASE 1: Completed
  • PHASE 2: Completed
  • PHASE 3: Under Construction
  • Existing House: Under Renovation
  • Parking Notes:
    • 5 Temporary Car stalls Operating on Phase 2 (2.75m x 6.0m)
    • 9 permanent Car stalls operating on Phase 2 (14 stalls in total)
  • Surrounding Features:
    • Old Island HWY
    • DRIVEWAY
    • P33