This site is in beta — data may be incomplete and features are still being added.
Public Hearing/Documents/Appendix C: Conceptual Design Estimates
Appendix

Appendix C: Conceptual Design Estimates

June 27, 2017Pages 213–2172 sections

Itemized cost estimates for proposed off-site road, sidewalk, and infrastructure improvements.

4.1.a Rezoning - 2951 Craigowan Road (Christie Point)
Date: 11-Apr-17Total Estimated Cost for Island Hwy Improvements: $635,000.00Total Estimated Cost for Shoreline Drive Road Improvements: $140,000.00

Christie Point | Responses to TIA Review | April 11, 2017 S:\PROJECTS\JP\6143-01 Christie Pt. TIA\20170410_Bunt Reponses to TIA Remaining Issues.docx

Page 213–217

Appendix C: Conceptual Design Estimates

Conceptual Design Estimate

Bunt & Associates Engineering Ltd.

Project: Christie Point - Shoreline Drive/Island Hwy Improvements Job No: 6143.01 Date: 11-Apr-17 By: DEM Sheet: 1 of 2 Note: To be read in conjunction with Appendix A - Conceptual Road Design

Item Approximate Quantity Unit Unit Price Amount
1.00 REMOVALS/RELOCATIONS
1.01 Concrete Curb & Gutter 180 m $35.00 $6,300.00
1.02 Concrete Median 85 m $35.00 $2,975.00
1.03 Stone Retaining Wall 65 m $50.00 $3,250.00
1.04 Concrete Sidewalk 10 m $30.00 $300.00
1.05 Pavement Marking 1130 m $15.00 $16,950.00
1.06 Utility Pole 3 each $40,000.00 $120,000.00
1.07 Signs 2 each $200.00 $400.00
Subtotal $150,175.00
2.00 NEW CONSTRUCTION
2.01 Concrete Curb & Gutter 185 m $110.00 $20,350.00
2.02 Concrete Sidewalk 10 m $100.00 $1,000.00
2.03 Retaining Wall 65 m $250 $16,250
2.04 Pavement Marking (line) 1130 m $15.00 $16,950.00
2.05 Pavement Marking (sym) 27 each $110 $2,970
2.06 Roadway Asphalt 120 t $160.00 $19,200.00
2.07 Tack Coat 265 $20.00 $5,300.00
2.08 Roadway Granular 180 t $80 $14,400.00
2.09 Misc Earth Excavation 1 lump sum $5,000.00 $5,000.00
2.10 Intersection Signalization 1 lump sum $150,000.00 $150,000.00
2.11 Singal Advanced Warning EB 1 lump sum $40,000.00 $40,000.00
Subtotal $291,420.00
3.00 MISCELLANEOUS
3.01 Traffic Control 1 lump sum $10,000.00 $10,000.00
3.02 Tree Protection 1 lump sum $5,000.00 $5,000.00
3.03 Environmental Protection 1 lump sum $5,000.00 $5,000.00
Subtotal $20,000.00
Total $461,595.00
Contingencies 15% $69,239.25
Sub total $530,834.25
Engineering and Administration 15% $79,625.14
TOTAL $610,459.39
City Inspection 4% $24,418.38
GRAND TOTAL $634,877.76
SAY $635,000.00

Notes:

  • Prices, quantities and items are approximate and for discussion purposes only.
  • This estimate does NOT include applicable taxes.
  • Utility pole relocations are approximate. Alignment of existing poles and available line slack may require additional pole relocations and/or new overhead line to be run.
  • Removal and reinstatement of existing retaining wall requires detailed review.
  • No underground utilities have been confirmed as part of this estimate.
  • Estimate does not include any additional intersection lighting hardware that may be required as part of signalization.
  • Roadway material composition not determined.
  • Proposed design of road in Appendix A is conceptual only.

Conceptual Design Estimate

Bunt & Associates Engineering Ltd.

Project: Christie Point - Shoreline Drive Road Improvements Job No: 6143.01 Date: 11-Apr-17 By: DEM Sheet: 2 of 2 Note: Includes sidewalk on Shoreline Drive and "sharrow" bicycle markings

Item Approximate Quantity Unit Unit Price Amount
1.00 REMOVALS/RELOCATIONS
1.01 Asphalt (driveways) 180 $20.00 $3,600.00
1.02 Earth/Gravel/Top Soil 1 lump sum $5,000.00 $5,000.00
1.03 Pavement Marking (line) 200 m $15.00 $3,000.00
Subtotal $11,600.00
2.00 NEW CONSTRUCTION
2.01 Concrete Curb & Gutter 122 m $110.00 $13,420.00
2.02 Concrete Sidewalk 122 m $100.00 $12,200.00
2.04 Pavement Marking (line) 60 m $15.00 $900.00
2.05 Pavement Marking (sym) 6 each $110 $660
2.06 Misc Granular and Top Soil 1 lump sum $15,000.00 $15,000.00
2.09 Misc Earth Excavation 1 lump sum $5,000.00 $5,000.00
2.10 Illumination on Hydro Pole 8 each $1,500.00 $12,000.00
2.11 Pave Existing Trail 275 m $65.00 $17,875.00
2.12 Yellow Centre Line on Trail 275 m $10.00 $2,750.00
Subtotal $77,055.00
3.00 MISCELLANEOUS
3.01 Traffic Control 1 lump sum $5,000.00 $5,000.00
3.02 Tree Protection 1 lump sum $3,000.00 $3,000.00
3.03 Environmental Protection 1 lump sum $5,000.00 $5,000.00
Subtotal $13,000.00
Total $101,655.00
Contingencies 15% $15,248.25
Sub total $116,903.25
Engineering and Administration 15% $17,535.49
TOTAL $134,438.74
City Inspection 4% $5,377.55
GRAND TOTAL $139,816.29
SAY $140,000.00

Notes:

  • Prices, quantities and items are approximate and for discussion purposes only.
  • This estimate does NOT include applicable taxes.
  • Location of proposed sidewalk is currently along/overtop of an existing ditch, culverts and catch basins. This estimate does NOT include relocation or construction of new drainage infrastructure.
  • No underground utilities have been confirmed as part of this estimate.
  • Feasibility of "sharrow" bicycle facility on Shoreline Dr. is conceptual and requires further review.
Page 213–217

Document Images

(1)
Document image
Extracted from: 2017 06 27 Public Hearing Agenda - Agenda - Pdf