Public Hearing/Documents/Appendix: Proposed Road Layout
Appendix

Appendix: Proposed Road Layout

November 17, 2020Page 2511 section

Engineering drawing detail for the proposed road layout and building footprints (Buildings A through D) for the rezoning application.

1 CALL TO ORDER
9 Erskine LaneAugust 11, 2020Herold Engineering Ltd.Building A and B: 79 units eachBuilding C and D: 89 units each

9 Erskine Lane Multi-Family Development - Rezoning Application

Town of View Royal Westurban Developments Ltd.

Project Information

  • Developer: Westurban Developments Ltd.
  • Engineer: Herold Engineering (1051 Vancouver St, Victoria, BC V8V 4T6)
  • Drawing Title: Proposed Road Layout
  • Project No: 4689-006
  • Drawing No: SK-01
  • Scale: 1:500
  • Date Issued: 2020.08.11 (Issued for Rezoning)

Notes

  1. For discussion purposes only.
  2. See legal survey drawing for site details and elevations.
  3. See architectural drawings for building details.
  4. Existing information provided by others.

Issues / Revisions

No. Date Description
1 2020.08.11 ISSUED FOR REZONING

Building Data

Building Unit Count Main Floor Elevation
Building A 79 Units 29m
Building B 79 Units 29m
Building C 89 Units 21m
Building D 89 Units 21m

Site Annotations and Infrastructure Requirements

Roadways and Access

  • Watkiss Way:
    • Road section as per TOVR Std. Dwg. No. VRSD-R14: Barrier Curb and Gutter, 1.50m Boulevard, 1.80m Concrete Sidewalk, 1.50m Boulevard, Streetlighting.
    • Wheelchair access ramp as per MMCD Std. Dwg. No. C8.
    • Extent of potential intersection roundabout.
  • Erskine Lane / Internal Access:
    • Road section as per TOVR Std. Dwg. No. VRSD-R10: Barrier Curb and Gutter, 2.50m Boulevard, 2.00m Concrete Sidewalk, 1.50m Boulevard, Streetlighting.
    • Driveway crossings as per TOVR Std. Dwg. No. VRSD-C7b (Width between 5.00m to 10.00m).
    • Provide curb letdown and access for CRD/MD maintenance vehicles, as per CRD/MD requirements.
    • Reinstate "No Parking" signs as required.

Storm Drain and Utilities

  • Storm drain infrastructure required for installation of barrier curb.
  • SDMH 1: Storm Drain Manhole as per MMCD Std. Dwg. No. S1 (Typ. 3).
  • 35.85m of Storm Drain Main.
  • Tie storm drain into existing manhole.
  • Existing utility pole to remain; anchor to be relocated.
  • Relocate existing bus stop; details to be established by TOVR and BC Transit.
  • Community mailbox to be relocated as per Canada Post requirements.
  • Catch basins to be relocated.
  • Existing water gate valves to be adjusted to suit or relocated (Typ. 2).
  • Electrical kiosks to be adjusted in boulevard.
  • New barrier curb as per MMCD Std. Dwg. No. C5 (Typ.).

Other Site Features

  • Parking structure outline (Typ.).
  • Retaining walls by others (Typ.).
  • Existing trees to be removed (Typ.).
  • Galloping Goose Regional Trail (bordering south property line).
  • Parkade ramp below locations noted for Building A and Building D.
Page 251