Appendix
Attachment 1 - SPF Program Guide Project Categories
July 15, 2025Pages 47–481 section
Excerpts from the Strategic Priorities Fund program guide outlining eligible and ineligible project categories.
Eligible stream: Capital Infrastructure Stream including Local Roads and Active TransportationIneligible: Projects that have already started before grant approval.
3 PROJECTS
3.1 PROJECT CATEGORIES
| CAPITAL INFRASTRUCTURE STREAM | |
|---|---|
| Local Roads, Bridges and Active Transportation | Recreation and Sport Infrastructure |
| Wastewater and Stormwater | Drinking Water |
| Tourism and Culture Infrastructure | Community Energy Systems |
| Solid Waste | Public Transit |
| Short-sea Shipping and Short-line Rail | Resilience |
| Fire Hall and Fire Trucks | Broadband Connectivity |
| Regional and Local Airports | Brownfield Redevelopment |
| CAPACITY BUILDING STREAM |
|---|
| Asset Management Planning |
| Long-term Infrastructure Planning |
| Integrated Community Sustainability Planning - Housing Planning |
Examples of eligible projects under each category can be found in Annex A of this program guide.
3.2 INELIGIBLE PROJECTS
Project works, which would otherwise be eligible, become ineligible if the project works have started prior to the date the project is included in a submitted SPF application. The project is deemed to have been started if a tender has been awarded, or work has commenced.
Furthermore, a SPF project will be deemed ineligible if:
- The project start date is later than two years after grant approval
- The project completion date is later than five years after grant approval
3.2.1 Ineligible Capital Infrastructure Stream Projects
- National Airport System
- Social Housing / Social Services
- Childcare / Daycare Centres
- Emergency Response Services (excluding fire hall infrastructure)
- City Halls / Public Works Buildings / Other Administrative Buildings
- Health Care Infrastructure (hospitals, convalescent and seniors’ centers, care facilities)
- Facilities, including arenas, which would be used as the home of professional sports teams
3.2.2 Ineligible Capacity Building Stream Projects
- Projects that have been approved under the UBCM Asset Management Planning (AMP) grant program unless they are identified as a distinct or phased component of the overall project.
Page 47–48
Extracted from: 2025 07 15 Council Agenda - Agenda - Pdf