This site is in beta — data may be incomplete and features are still being added.
Council Meeting/Documents/WSPR STAFF REPORT - 2025 May Progress Report
Staff Report

WSPR STAFF REPORT - 2025 May Progress Report

July 15, 2025Page 1133 sections

Progress report for the West Shore Regional Parks & Recreation Facilities Master Plan.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 6:00 p.m.
Approved Budget: $140,000Actual Expenditure to date: $66,353Final Master Plan expected: Early December 2025
Page 113

MUNICIPAL OWNER REPRESENTATIVES

Page 113

WSPR STAFF REPORT

TO: West Shore Parks & Recreation Society Members
FROM: Grant Brown, Chief Administrative Officer
DATE: July 10th, 2025
SUBJECT: 2025 May Progress Report - West Shore Regional Parks & Recreation Facilities Master Plan

RECOMMENDATION:

That the West Shore Parks & Recreation Society Members receive this report for information.

BACKGROUND:

The West Shore Parks & Recreation Society members (WSPRS) approved funding for a regional parks & recreation facilities master plan that will evaluate the current state of parks & recreation facilities on the Westshore and develop a 10- to 20- year road map to address the growing sporting and recreational needs of the community.

Progress updates will be provided by the WSPRS CAO quarterly or following key project milestones.

DISCUSSION:

Since the last update, Phase 2 – Engagement and Phase 3 – Analysis have been completed. The project has entered the fourth phase of the project which involves drafting of the report. The first draft will be made available to staff by July 30th for an initial review and revision, and the second draft will be presented to councils on September 29th. The opportunity for public feedback will follow any further revisions resulting from the council session and will take place in late October through early November.

The project remains on schedule and the final master plan is expected to be available for council consideration in early December.

BUDGET IMPLICATIONS:

The approved budget for the West Shore Parks & Recreation Facilities Master Plan project is $140,000. To date, $66,353 has been incurred, which has been included in the quarterly financial status report for the Society members’ financial officers.

Respectfully Submitted,

Grant Brown, Chief Administrative Officer

1767 Island Highway, Victoria BC V9B 1J1 | PHONE 250-478-8384 | www.wspr.ca