A proposal by Gwyer Webber advocating for passenger rail service on the Island Rail Corridor, including phase-in costs and proposed transit times.

Estimated cost for Phase 1 (Victoria to Duncan) was $151 million prior to CovidTravel time from View Royal to Victoria: approximately 10 minutesProposed Victoria station at Douglas St/View StProposes battery electric multiple units (BEMU) for rolling stock

Vancouver Island Rail Transit

Written by Gwyer Webber (2018-2024) www.railtransit.ca

  • The Island Rail Corridor would be preserved for Passenger Rail Service and a Multi-Use Trail alongside the rail line.
  • The rail line would be upgraded with new rail and concrete ties to allow for scheduled passenger rail service throughout the day.
  • The rail line would be built in phases when funding is available.

[Map: Stylized overview of the Vancouver Island Rail Transit system showing station names and distances from Victoria (0km) to Campbell River (264km) and Port Alberni (63.4km)]

Page 40–56

Phase 1: Victoria - Duncan

  • Negotiate with the Songhees, Esquimalt, and Cowichan Tribes First Nations to allow Passenger Rail to run through the reserve.
  • Stations at Duncan, Cobble Hill, Shawnigan Lake, Langford Exchange, Thetis Lake (Six Mile Rd), View Royal (Portage Park), Esquimalt (Lampson St), and Victoria (Douglas St/View St). Station platform length at 225m.
  • Initially two trains would run every 90 to 120 minutes in each direction with both vehicles starting in Duncan.
    • Two additional trains would allow for a frequency of every 30 minute from Langford to Victoria.
    • Four additional trains would allow for a frequency of every 15 minute from Langford to Victoria
  • The travel time between Duncan and Victoria is approximately 60 minutes.
  • Travel time from Langford Exchange to Victoria is approximately 20 minutes.
  • Travel time from View Royal to Victoria is approximately 10 minutes.

[Diagram: Linear station map for Phase 1 from Duncan to Victoria]

Page 40–56

Phase 1 Cost

  • The cost of the Ultimate Phase in the IRCCA Report from Victoria to Duncan was $151 million dollars prior to Covid.
  • Additional cost for stations, rail vehicles, a maintenance building near Duncan, a signaling system, overhead power from Victoria to Langford, and a tunnel to downtown Victoria.

Island Rail Corridor Condition Assessment Report (Table 24, Page 74)

Table showing costs for combining sequential phases including MoTI contingencies
Table showing costs for combining sequential phases including MoTI contingencies
Phase Segment 1 (Victoria to Langford) Segment 2 (Langford to Duncan) Segment 3 (Duncan to Nanaimo) Segment 4 (Nanaimo to Parksville) Segment 5 (Parksville to Courtenay) Sub Total (Victoria Subdivision) Sub Total (Port Alberni Subdivision, Segment 6) Island Rail Corridor Total
Initial Phase $14,513,749 $47,748,423 $64,038,799 $32,611,106 $68,397,313 $227,309,391 $99,139,001 $326,448,391
Intermediate = Initial + Intermediate $28,281,783 $81,035,713 $114,912,185 $60,376,966 $121,031,367 $405,638,013 $146,385,919 $552,023,932
Ultimate = Initial + Intermediate + Ultimate $35,469,950 $114,569,344 $150,660,506 $82,979,158 $164,694,045 $548,373,004 $180,405,300 $728,778,304
Page 40–56

Downtown Victoria Station

A single-bore single track underground tunnel to a double track with centre platform would eliminate 7 level crossings and reduce travel time. The platform length would be 225m and the tunnel diameter would accommodate Bi Level EMUs with overhead power.

Map of downtown Victoria showing the proposed underground tunnel route and station location
Map of downtown Victoria showing the proposed underground tunnel route and station location
Page 40–56

Victoria Area Stations

The stations in the Victoria area would be the passing sidings and located at Langford Exchange, Six Mile Rd, Portage Park, Lampson St, and Downtown Victoria. Overhead power from Langford Exchange to Downtown Victoria.

Aerial map of the Victoria area highlighting station locations and the rail corridor
Aerial map of the Victoria area highlighting station locations and the rail corridor
Page 40–56

Rolling Stock

The picture below shows a Stadler FLIRT single-level DEMU. The Battery Electric Multiple Unit (BEMU) would be similar and include pantographs. Overhead power from Langford to Victoria and at the station platform in Duncan would be used to charge the trains.

[Rendering: Stadler FLIRT single-level train]

Bi-Level EMU

The picture below shows a Stadler KISS Bi-Level EMU. Caltrain has ordered a battery electric version with pantographs to test on sections with no overhead power.

Rendering of a Stadler KISS Bi-Level EMU train on tracks
Rendering of a Stadler KISS Bi-Level EMU train on tracks
Page 40–56

Esquimalt and Songhees First Nation Reserve

If required, the line would run underground (cut and cover) through Esquimalt and Songhees First Nations reserves.

Map detailing the rail corridor through the Esquimalt and Songhees First Nation reserves
Map detailing the rail corridor through the Esquimalt and Songhees First Nation reserves
Page 40–56

Halalt First Nation Reserve

The existing right of way can be returned to the Halalt First Nations and a new right of way built to the west of the reserve.

Map showing the existing rail line and the proposed new right of way west of the Halalt First Nation reserve
Map showing the existing rail line and the proposed new right of way west of the Halalt First Nation reserve
Page 40–56

Stz’uminus First Nation Reserve

  • Negotiate with the Stz’uminus First Nations to allow or move the existing right of way farther west.
Map of the rail corridor passing through the Stz’uminus First Nation reserve area
Map of the rail corridor passing through the Stz’uminus First Nation reserve area
Page 40–56

Snuneymuxw First Nations Reserve

  • The existing freight rail operations would be moved to Duke Point including the propane depot.
  • A rail link from Duke Point to the mainline is not required initially and could be done at a later date. When the link is built, freight would run at night only so as not to interfere with passenger rail service.
  • The right of way can then be returned to Snuneymuxw First Nations and the Nanaimo Waterfront can be redeveloped.
Map showing the rail line and the Snuneymuxw First Nation reserve area near Nanaimo
Map showing the rail line and the Snuneymuxw First Nation reserve area near Nanaimo
Page 40–56

Snaw-Naw-As First Nation Reserve

The line would be underground around the reserve.

Map showing the rail line route near the Snaw-Naw-As First Nation reserve
Map showing the rail line route near the Snaw-Naw-As First Nation reserve
Page 40–56

Extension to Campbell River

Overview map showing the proposed rail extension from Courtenay to Campbell River
Overview map showing the proposed rail extension from Courtenay to Campbell River
Page 40–56

Campbell River Station

Map showing the proposed station location and rail terminus in Campbell River
Map showing the proposed station location and rail terminus in Campbell River
Page 40–56

Parksville Station

Blue denotes Victoria Sub and Green denotes Port Alberni Sub. Purple denotes Maintenance and Freight Link.

Detailed map of the Parksville station area showing the junction of different rail subdivisions
Detailed map of the Parksville station area showing the junction of different rail subdivisions
Page 40–56

All Fare Zones

Fares are based on BC Transit Victoria single ticket price. BC Transit is proposing a single ticket price of $3 by 2025.

Zone 1 2 3 4 5 6 7
City CRD Shawnigan, Cobble Hill, Duncan Chemainus, Ladysmith, YCD Nanaimo, Lantzville Parksville, Qualicum, Coombs Buckley Bay, Courtenay, Pt Alberni Campbell River
Zones 1 2 3 4 5 6 7
Fares $3.00 $6.00 $9.00 $12.00 $15.00 $18.00 $21.00
Monthly Pass $90 $130 $170 $210 $250 $290 $330

Note: Children 12 years and under ride free. Children 5 years and under must be accompanied by someone 12 years and older.

Example

Individual Ticket: Courtenay-Victoria $18.00 / Nanaimo-Victoria $12.00 / Parksville-Duncan $12.00

Page 40–56

Colwood Rapid Transit

This is an option for a Colwood Rapid Bus when the E&N is upgraded and running a train every 15 minutes from Langford Exchange to Downtown Victoria. The roads would be upgraded to allow for bus only lanes.

Map showing proposed Colwood Rapid Transit bus route and its connection to the rail line
Map showing proposed Colwood Rapid Transit bus route and its connection to the rail line
Page 40–56

Future Victoria Metro

The line would eventually extend from Sooke to Sidney. Travel time from Langford Exchange to Downtown Victoria (13.5km) would be approximately 18 minutes. Travel time from Kelly Rd/Sooke Rd to Downtown Victoria (11.5km) would be approximately 15 minutes.

Map showing the potential long-term expansion of the Victoria Metro system to Sooke and Sidney