ATTACHMENT 2: C-080 Project Summary: Jedburgh Road sidewalk
October 15, 2024Page 1481 section
Project summary document detailing the scope and funding for Jedburgh Road sidewalks.
From 12 Jedburgh Road to Helmcken RoadFunding from Capital Works and Land reserve
Project Summary
Project Name: Jedburgh Road sidewalk
ATTACHMENT 2 C-080 Financial Plan 2024 – 2028 Priority: Optimal
2-2-11101-310 CC1204 1-2-03310-630 CC331-01
Submitted by: I. Leung, Director of Engineering
| Executive Summary | This project was included in the 2022-2026 Financial Plan. To complete the sidewalk from 12 Jedburgh Road to Helmcken Road. Design commenced in 2023 and construction is expected in 2024. | ||||||||||||||||||||||||||||||||||
| Business problem and opportunity | The section of sidewalk will be included for consideration in the Active Transportation Network Plan (finalized in spring 2023). | ||||||||||||||||||||||||||||||||||
| Proposed project objectives | Provide safe walking facilities and promote alternative transportation modes. | ||||||||||||||||||||||||||||||||||
| Business risks | The project will be part of the contemplated connections in the Active Transportation Network Plan (completion in spring 2023). | ||||||||||||||||||||||||||||||||||
| Proposed sources of funding | Capital Works and Land reserve | ||||||||||||||||||||||||||||||||||
| Costs and benefits | Costs
Benefits
|
||||||||||||||||||||||||||||||||||
| Recommendation | THAT the Committee recommend the 2024-2028 Financial Plan include Jedburgh Road sidewalk in 2024 to be funded by Capital Works and Land reserve. |