Staff Report

COUNCIL REPORT: ISLAND HIGHWAY SIDEWALK UPGRADES CONSTRUCTION AWARD

December 3, 2024Pages 31–332 sections

Staff recommendation to award the construction contract for the Island Highway Sidewalk Upgrades project to the low bidder.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 7:00 p.m.
Recommended Bidder: Ramida Enterprises Ltd.Contract amount: $362,800.82 net of GSTTotal of 11 bids received

TOWN OF VIEW ROYAL COUNCIL REPORT

TO: Council
DATE: November 20, 2024
FROM: Ivan Leung, P.Eng, Director of Engineering
MEETING DATE: December 3, 2024

Page 31–33

ISLAND HIGHWAY SIDEWALK UPGRADES CONSTRUCTION AWARD

RECOMMENDATION:

THAT Council approve the award of the Island Highway sidewalk project (Project C-066) to Ramida Enterprises Ltd. in the amount of $362,800.82 net of GST.

PURPOSE:

The purpose of this report is to seek approval from Council to award the Island Highway Sidewalk Upgrades to the recommended bidder.

BACKGROUND:

Eleven (11) bidders submitted bids to the Town of View Royal, which was opened on November 15, 2024 at 2:00PM. A summary of the bid prices, upon verification by the Town’s Contract Administrator (ISL Engineering and Land Services Ltd.), is as follows:

Bidder Bid Price (Net GST)
Ramida Enterprises Ltd. $362,800.82
Hoel Contracting Ltd. $379,200.83
Don Mann Excavating Ltd. $405,130.95
Milestone Equipment Contracting Ltd. $417,576.00
Sparker Construction Ltd. $456,821.00
Socor Contracting Ltd. $465,810.00
Copcan Civil LP (Copcan Holdings Ltd.) $485,295.60
Hazelwood Construction Services Inc. $536,914.51
Chew Excavating Ltd. $538,581.00
Draycor Construction Ltd. $552,313.50
Despard Contracting Ltd. $647,775.77

ISL has confirmed that all bids are compliant with the tender requirements and recommend that the project be awarded to Ramida Enterprises Ltd. as the low bid.

ANALYSIS:

Impacts and implications can be summarized as follows:

Category Description
Community Impact: Improved pedestrian accessibility by continuing to close the gap in sidewalks along the Island Highway.
Financial Implication: The low bid, contract administration costs and moderate contingencies are within the current budget. No additional implications are present.
Inter-governmental Relations Impact: Improved pedestrian accessibility towards the City of Colwood’s sidewalk network that ultimately leads to the Juan de Fuca Recreation Centre. Improved accessibility to rapid transit.

ALIGNMENT:

The recommended option aligns with the Town’s following core guiding documents as follows:

Document Description
Strategic Plan: Strategic Priority A, Goal 1: Shift primary mode within View Royal away from vehicles to walking, cycling and transit.
Official Community Plan: Objective LU13.: Support the revitalization of the western gateway through improvements along the Island Highway.
Other Policy Documents: Active Transportation Network Plan (2023), Action Item 1M (Immediate): Implement Island Highway sidewalk facilities.

PUBLIC PARTICIPATION GOAL:

The desired level of public participation for the recommended option is:

[X] Inform
[ ] Consult
[ ] Involve
[ ] Collaborate
[ ] Empower
[ ] N/A

TIME CRITICAL:

Bids are valid for 60 Days, starting from the Tender opening date (November 15, 2024).

CONCURRENCE: Initials Comments
Chief Administrative Officer SS I concur with the recommendation.
REVIEWED BY: Initials
Director of Corporate Administration/Deputy CAO NR
Director of Finance & Technology NR
Director of Development Services NR
Director of Engineering IL
Director of Protective Services NR

ATTACHMENTS:

  1. Project Summary C-066: Island Highway Upgrades – Hart Road to Wilfert Road
Page 31–33

Document Images

(1)
Document image
Extracted from: 2024 12 03 Council Agenda - Agenda - Pdf