This site is in beta — data may be incomplete and features are still being added.
Council Meeting/Documents/Project Summary C-137: West Shore RCMP building expansion
Staff Report

Project Summary C-137: West Shore RCMP building expansion

November 21, 2023Pages 66–715 sections

A detailed summary for the capital construction of the expanded RCMP facility, including debt servicing costs and population projections.

8.1.b West Shore RCMP Detachment Expansion Project Funding
$12,800,000 View Royal capital share20-year term4.67% indicative interest rate92,417 square feet proposed size

Project Summary

Project Name: West Shore RCMP building expansion Project Number: 2-2-12301-310 CC1103/1-2-08300-75x CC101-99 Submitted by: K. Anema, Chief Administrative Officer Priority: Required

Executive Summary

Jointly owned by The Town of View Royal and the Cities of Langford and Colwood (“the Communities”), the West Shore RCMP Detachment is located at 698 Atkins Avenue in Langford. The existing detachment is approximately 37,000 ft², comprised of two largely separate facilities: one built in the 1960s (approx. 10,600 ft²), and a newer structure built in 1999 (approx. 26,400 ft²). Investments have been made in the current detachment, but the facility is nearing capacity. Projections by the RCMP show the need for increased space in the next one to four years. As the Communities continue to grow, so too does the need for specialized and diversified policing services, increased use of technology, modern facilities, and a larger staff contingent to maintain the current level of service in the region.

Business problem and opportunity

A feasibility study explored the need for an expanded RCMP facility together with a review of redevelopment of the existing site versus options to relocate elsewhere within the Communities. A recommendation is made to remain at, and redevelop, the existing location on Atkins Avenue, as it is deemed to be more economical than relocating and building new.

Proposed project objectives

A twenty-year planning horizon was used:

  • to align with the minimum debt financing that will likely accompany this project
  • to mirror the estimated capacity needs with the financing horizon
  • assuming a 2023/2024 construction start, occupancy would be 2025/2026
  • near-term “excess space” could be leased to other agencies
  • construction cost escalation supports building now vs later

Business risks

The Police Unit Agreement between the Municipality and Canada includes a requirement that the Town supply accommodation for the Royal Canadian Mounted Police. Failure to provide suitable accommodation can result in Canada supplying the building with the Town paying the cost of provision.

Proposed sources of funding

Municipal Finance Authority 20-year debt financing

Costs and benefits

Costs FY1 FY2 FY3 FY4 FY5 5-year Total
Capital 12,800,000 12,800,000
Operational 1,049,369 1,049,369 1,049,369 3,148,107
Total 0 12,800,000 1,049,369 1,049,369 1,049,369 15,948,107
Benefits
Tangible
Intangible

Recommendation

THAT the Committee recommend the 2023-2027 Financial Plan include the West Shore RCMP building expansion in 2024 to be funded by MFA long term debt.

Page 66–71

Additional Information

Population projections were needed to help determine future space requirements and are assumed as follows in Table 1.

Table 1

2021 Population 2045 Population Estimate Annual Growth Assumption
View Royal 11,575 16,692 1.86%
Colwood 18,961 34,295 2.50%
Langford 45,584 103,133 6% (2022-2025)
4% (2026-2030)
3% (2031-2035)
2.5% (2036-2045)
Metchosin 5,067 7,034 1.53%
Highlands, Songhees Nation, Esquimalt Nation 4,645 6,147 2.31% Highlands
0.00% for Songhees and Esquimalt
Total 85,832 167,301

Police to population ratios were also needed to help determine future space requirements. The ratios assumed in Table 2 are estimates. Each community will likely determine their police to population ratios annually as part of their financial planning processes.

Table 2

2045 Population Estimate Police:Population Estimate Corresponding Headcount Current
View Royal 16,692 1:875 19
Colwood 34,295 1:875 39
Langford 103,133 1:750 138
Metchosin 7,034 1:875 8
Highlands, Songhees Nation, Esquimalt Nation 6,147 1:930 6
RCMP FTE total 210 96
Administrative 70 51
Total FTE 281 147

The RCMP then provided space requirement estimates based on future RCMP FTE counts.

Table 3

Square feet
General Units 39,042
Common Units-Major Crimes/Serious Crime 13,719
Special Units/Large Detachment 7,250
Sub Total 60,011
Gross Up 32,406
Total Required 92,417

We then benchmarked future space requirements against a comparable (Kelowna) and current West Shore facilities on a per capita and per FTE basis.

Table 4

West Shore Current West Shore 2045 Kelowna
Population served 85,832 167,301 142,000
RCMP FTE 96 210 214
Total FTE 147 281 314
Policing Ratio 1:885 1:795 1:664
Square Footage 37,067 92,417 106,000
Sq.ft./capita 0.44 .55 .75
Sq.ft/Total FTE 252 329 338

The feasibility study ultimately recommended a building size of 92,417 ft² together with 2.5 acres of parking to support our policing functions 20 years hence. In the near term, portions of an expanded facility would be leased to other agencies (likely policing related) until such time that occupancy is needed for Communities policing purposes.

A further recommendation was returned to remain at, and redevelop, the existing location on Atkins Avenue, as it was deemed to be more economical than relocating and building new. Additionally, it was noted to be the preferred site over alternative options due to its central location and ease of access to major transportation routes.

Table 5: Estimated Capital Costs

Item Cost
Demolition $633,346
Site Servicing $647,080
Surface Parking $1,767,131
Building Construction $44,443,329*
Sub Total $47,490,886
Net Zero Standard (5%) $1,939,573
Post Disaster Standard (10%) $3,702,433
Furniture, Fixtures, & Equipment (2.5%) $1,187,272
Land Acquisition (6 properties) $5,400,000
Price Escalation to 2024 (3.5% per year) $4,253,569
Project Delivery Services (12%) $7,676,848
Contingency (15%) $10,747,587
Estimated capital cost (+/- 25%) $82.4M

*Includes $6m in seismic upgrades for the 1999 facility (approximately 26,000 ft²) together with approximately 66,000 ft² in new construction.

Table 6: Estimated Municipal Contributions

Municipality 50% Population (2021) 50% Assessment (2021) Capital Cost Contributions
Langford 60.13% $49.6M
View Royal 15.56% $12.8M
Colwood 24.31% $20.1M
Page 66–71

Next Steps

The Joint Steering Committee (3 CAOs) has recommended to pursue a Integrated Project Delivery (IPD) procurement approach, which will enable the Communities to come to a proposed budget while meeting project requirements in the most efficient manner.

With approval of the recommended budget of $1,200,000, the Communities will proceed with procuring an IPD Advisor and IPD team to develop a Validation Report in mid-2023. A Validation Report reflects the IPD Team’s commitment to achieve the target cost, budget, appropriate level of design, contingency, risk, schedule and other details to ensure owner requirements will be met. One community (likely Langford) will act is fiscal agent for the Communities through this process.

This work will enable the collective Communities stakeholder group to make a decision on whether to proceed with the proposed project.

Page 66–71

Project Financing

Long-term borrowing will be required for Colwood’s contribution to this project, and we may determine to begin the borrowing process parallel with the Validation stage of procurement. Long-term borrowing is secured through a loan authorization bylaw, which requires approval of the electors, and the Inspector of Municipalities. Steps in the borrowing process are as follows:

  1. Loan authorization bylaw drafted, and council or board gives it three readings
  2. Municipal council or electoral area director provide consent (if applicable)
  3. Provincial review and statutory approval by the Inspector of Municipalities (6-8 weeks)
  4. Approval of the electors (if applicable, 8-11 weeks)
  5. Adoption of the bylaw by the council or board
  6. Challenge period (1 month)
  7. Provincial review and certificate of approval by the Inspector of Municipalities (2-4 weeks)
  8. Municipal council passes security issuing resolution and agreement (municipal borrowing only)
  9. Regional district drafts security issuing bylaw and board gives it three readings and adoption
  10. Challenge period for security issuing bylaw (10 days)
  11. Provincial review of the security issuing bylaw and certificate of approval by the Inspector of Municipalities (2-4 weeks)
  12. Security issuing by the Municipal Finance Authority
Page 66–71

Debt Servicing

Should the project proceed as currently envisioned, View Royal will need to build into our annual budgets the costs of principal and interest repayment over time and determine a borrowing period for the loan. The capacity and capability of the building is being scaled for the 20-year horizon, however the building itself should provide useful life over a 50-year time scale.

20-Year 30-Year
Amount to borrow $12,800,000 $12,800,000
Indicative interest rate 4.67% 4.67%
Annual Payment $1,049,369 $844,123
Estimated interest cost $8,911,416 $7,209,749

20-year debt amortization schedule (includes required 1% debt reserve fund contribution):

20 Year Term Estimated Annual Debt Payments: 1,049,369 Principal: 12,929,300 Interest Rate: 4.67% Capitalization Rate: 3.75% S/F Factor: 0.034462097

20-year debt amortization schedule
20-year debt amortization schedule
Period Estimated Principal Payment Estimated Interest Payment Estimated Total Payment Estimated Actuarial Reducing Balance
12,929,300
Yr 1 Semi Annual 301,899 301,899 12,929,300
Yr 1 Annual 445,571 301,899 747,470 12,483,729
Yr 2 Semi Annual 301,899 301,899 12,483,729
Yr 2 Annual 445,571 301,899 747,470 16,709 12,021,450
Yr 3 Semi Annual 301,899 301,899 12,021,450
Yr 3 Annual 445,571 301,899 747,470 34,044 11,541,834
Yr 4 Semi Annual 301,899 301,899 11,541,834
Yr 4 Annual 445,571 301,899 747,470 52,030 11,044,234
Yr 5 Semi Annual 301,899 301,899 11,044,234
Yr 5 Annual 445,571 301,899 747,470 70,690 10,527,973
Yr 6 Semi Annual 301,899 301,899 10,527,973
Yr 6 Annual 445,571 301,899 747,470 90,050 9,992,352
Yr 7 Semi Annual 301,899 301,899 9,992,352
Yr 7 Annual 445,571 301,899 747,470 110,136 9,436,646
Yr 8 Semi Annual 301,899 301,899 9,436,646
Yr 8 Annual 445,571 301,899 747,470 130,975 8,860,101
Yr 9 Semi Annual 301,899 301,899 8,860,101
Yr 9 Annual 445,571 301,899 747,470 152,595 8,261,935
Yr 10 Semi Annual 301,899 301,899 8,261,935
Yr 10 Annual 445,571 301,899 747,470 175,026 7,641,338
Yr 11 Semi Annual 301,899 301,899 7,641,338
Yr 11 Annual 445,571 301,899 747,470 198,299 6,997,468
Yr 12 Semi Annual 301,899 301,899 6,997,468
Yr 12 Annual 445,571 301,899 747,470 222,444 6,329,454
Yr 13 Semi Annual 301,899 301,899 6,329,454
Yr 13 Annual 445,571 301,899 747,470 247,494 5,636,389
Yr 14 Semi Annual 301,899 301,899 5,636,389
Yr 14 Annual 445,571 301,899 747,470 273,484 4,917,334
Yr 15 Semi Annual 301,899 301,899 4,917,334
Yr 15 Annual 445,571 301,899 747,470 300,449 4,171,314
Yr 16 Semi Annual 301,899 301,899 4,171,314
Yr 16 Annual 445,571 301,899 747,470 328,424 3,397,319
Yr 17 Semi Annual 301,899 301,899 3,397,319
Yr 17 Annual 445,571 301,899 747,470 357,449 2,594,299
Yr 18 Semi Annual 301,899 301,899 2,594,299
Yr 18 Annual 445,571 301,899 747,470 387,563 1,761,166
Yr 19 Semi Annual 301,899 301,899 1,761,166
Yr 19 Annual 445,571 301,899 747,470 418,805 896,790
Yr 20 Semi Annual 301,899 301,899 896,790
Yr 20 Annual 445,571 301,899 747,470 451,219 -0
TOTALS: 8,911,416 12,075,966 20,987,382 4,017,884
Page 66–71
Extracted from: 2023 11 21 Council Agenda - Agenda - Pdf