Revised Site Plan - COHO Phase 2
Updated architectural site plan for the development permit amendment application.
Attachment 8
AS APPROVED (TO BE AMENDED)

Key Notes
- AREA DRAIN. SLOPE SUBGRADE TO DRAIN. REFER TO MECH/LANDSCAPE DWGS AS APPLIC.
- HARDSCAPING (REFER TO LANDSCAPE ARCH. DWGS.)
- CONCRETE RAMP - C/W HERRINGBONE PATTERN
- GARBAGE ENCLOSURE
- GARBAGE/RECYCLE/COMPOSTS ENCLOSURE
- BUILDING BAGGAGE ENTRANCE
- RETAINING CONCRETE FOR RED GUARD (PROV'D BY OTHERS) BY B.C. BUILDING CODE. REFER TO ARCH, STRUCT, CIVIL & LANDSCAPE DWGS.) SEE NOTE 'B' ON SITE.
- CONCRETE CURB (S.L.D. - S-C.E.D)
- 4"x4" CORRUGATED METAL WELLS C/W DRAINAGE AT WINDOW WELLS. BACKFILL C/W CLEAN DRAIN FILL.
- TRANSFORMER ON CONC. PAD (REFER TO S.C. & ELEC DWGS.) PROVIDE ARCHITECTURAL BOULDERS & GRAVEL SURROUND AS REQUIRED BY B.C. HYDRO.
- FIRE STANDPIPE SIAMESE CONNECTION LOCATION (S.I.P.C.)
- LANDSCAPING (REFER TO LANDSCAPE DWGS.)
- BIKE HOIST - S.C.E.D.
- FIRE HYDRANT - S.C.E.D.
- PATHWAY (REFER TO LANDSCAPE DWGS.)
- HANDRAIL / GUARD RAIL - PRE-MANUFACTURED ALUMINUM
- GAS METER - REFER TO MECH DWGS
- LIGHT FIXTURE - REFER TO ELEC DWGS
- INDICATES FIRE TRUCK PATH OF TRAVEL
- ARCHAEOLOGICAL PROTECTED AREAS (REFER TO SITE SURVEY)
Sheet Notes
A. ALL SITE INFORMATION TAKEN FROM INFORMATION PROVIDED BY SITE SURVEYOR AND CIVIL ENGINEER. CONSULT SITE + CIVIL ENGINEER PRIOR TO ESTABLISHING LAYOUT FOR GRADING AND DRAINAGE PURPOSES. B. GENERAL CONTRACTOR TO COORDINATE ALL UTILITY SITE SERVICE ENTRANCES WITH UTILITY PROVIDERS. C. S.L.D. - S.C.E.D. AND SPEC'S FOR ALL LANDSCAPING, SITE SERVICES AND WATER STORMWATER MANAGEMENT. D. BUILDING OUTLINE REPRESENTS EDGE OF SLAB MAIN LEVEL AND PARKADE. ALL DIMENSION SHOWN ARE TO GRID LINES. E. COORDINATE ALL MECHANICAL, DRAINAGE DRAWINGS AND SPEC'S FOR ALL RETAINING, ROADWORKS, RAMPING AND CAR PARK AREA. COORDINATE ALL SOIL EROSION RETENTION USING FILTER CLOTH FROM EXCAVATION. F. REFER TO ALL CIVIL AND ELECTRICAL DRAWINGS FOR ALL UTILITY CONNECTIONS. G. GENERAL CONTRACTOR TO PATCH AND MAKE GOOD ALL DISTURBED SURFACES OF THE ADJACENT GARAGES DURING CONSTRUCTION. H. THIS PLAN IS ISSUED FOR THE PURPOSE OF POSITIONING THE BUILDING IN RELATION TO THE SITE. REFER TO ENGINEER'S AND ARCHITECT'S DRAWINGS FOR ALL OTHER SITE INFORMATION. J. UNLESS OTHERWISE NOTED ALL DIMENSIONS TO THE PROPERTY LINE ARE PERPENDICULAR TO THE PROPERTY LINE. K. GENERAL CONTRACTOR TO REPORT ALL DISCREPANCIES TO THE ARCHITECT. L. BARRIER-FREE ACCESS, CLUB SUITE AND RAMPS TO CONFORM TO B.C. BUILDING CODE. M. CROSSWALKS AND HANDICAP PARKING SYMBOLS TO BE PAINTED. REFER TO LANDSCAPE ARCHITECT'S DESIGNS AND SPEC'S. N. CONTRACTOR TO PROVIDE ADDITIONAL DRY WELLS AS REQUIRED.
Parking Count
| Description | Count |
|---|---|
| HANDICAPPED PARKING STALLS | 2 |
| STANDARD PARKING STALLS | 36 |
| SHORT TERM STALLS (TURNING CIRCLE) | 38 |
| TOTAL STALLS ON SITE | 76 |
Legend
- CONCRETE SIDEWALK (S.L.D): [Hatched rectangle]
- CONCRETE PAVING (S.L.D): [Clear rectangle]
Project Information
- Owner: HEADWATER PROPERTIES LIMITED PARTNERSHIP
- Project Name: COHO Condominiums
- Drawing Title: PHASE 1 & PHASE 2 SITE PLAN - REVISED DP
- Project Number: 11 11 020
- Drawn: KT
- Designed: CZ
- Checked: KN
- Checked: IM
- Drawing Number: DP1.0.1
- Stamp: SITE PLAN AS SUBMITTED WITH THE MAY 24, 2013 DP AMENDMENT APPLICATION