Council Meeting/Documents/Attachment 8: Section Through Site (South-East Elev.)
Appendix

Attachment 8: Section Through Site (South-East Elev.)

May 15, 2012Page 401 section

Cross-section elevation showing the tower, equipment shelter, and surrounding trees.

1. CALL TO ORDER
55m self support tower

SECTION THROUGH SITE (SOUTH-EAST ELEV.)

South elevation technical drawing of a 55m self-support telecommunications tower showing antenna levels, equipment shelter, and surrounding terrain.
South elevation technical drawing of a 55m self-support telecommunications tower showing antenna levels, equipment shelter, and surrounding terrain.

South Elevation Details (Scale 1:300)

  • Level 1 (54.2m): 6-INITIAL PANEL ANTENNAS. SEE LEVEL 1 ANTENNA ORIENTATION PLAN ON DRAWING 104 FOR DETAILS
  • Level 2 (52.1m): 6-INITIAL PANEL ANTENNAS, 6-RRU'S & 1-COMBINER. SEE LEVEL 2 ANTENNA ORIENTATION PLAN ON DRAWING 104 FOR DETAILS
  • Level 3 (50.0m): 6-FUTURE PANEL ANTENNAS, 3-RRU'S & 1-COMBINER. SEE LEVEL 3 ANTENNA ORIENTATION PLAN ON DRAWING 105 FOR DETAILS
  • Antenna Mount Support: FRAMING BY WESTOWER
  • Tower: 55m SELF SUPPORT TOWER AND FOUNDATION BY WESTOWER
  • Perimeter: NEW CHAIN LINK FENCE
  • Equipment: TELUS 2.7x3.4m EQUIPMENT SHELTER
  • Access: STAIRS TO SUIT GROUND
  • Ground Elevation: ELEV. 95m
  • Terrain Heights: 126m

Revisions

No. REVISIONS DATE
1 PRELIMINARY APR 11, 2007
2 BUILDING RELOCATED JUN 25, 2007
3 BUILDING PERMIT JULY 16, 2007
4 REV. TOWER & BLDG. FOOT PRINT AUG 10, 2007
5 CLIENT REVIEW/COMMENT OCT 26, 2007
6 REMOVED M/W ANTENNA FEB 27, 2009
7 ISSUED FOR CONSTRUCTION APRIL 20, 2011
8 TOWER HEIGHT REVISED MAY 4, 2012

Project Information

  • Consulting Engineers: ROBERTSON KOLBEINS TEEVAN GALLAHER ASSOCIATES LTD
    • 1955 W. 4TH AVE., VANCOUVER, BRITISH COLUMBIA V6J 1M5
  • Project Name: RKTG BC0553 — MUNNS ROAD
  • Drawing Title: SECTION THROUGH SITE (SOUTH-EAST ELEV.)
  • Drawing No.: B19-3027-103
  • Revision: REV. 8
  • ENG: G. ANDERSEN
  • DATE: APR 2007
  • DR: RJ/ANP
  • PLOT: 1 : 1
  • CHK: G. ANDERSEN
  • PLOT DATE: MAY 4, 2012
  • APP: R. CARTER