STAFF REPORT: Chilco Trails Update

November 6, 2012Pages 34–359 sections

Report advising Council of a budget shortfall for the Chilco Trail project and recommending completion of Phase 1 only for now.

1. CALL TO ORDER
November 1, 2012$28,500.00 budget shortfall for Phases 1 and 2Total estimated construction cost $110,000.00

TOWN OF VIEW ROYAL COUNCIL REPORT

TO: Council
DATE: November 1, 2012
FROM: Lindsay Chase
MEETING DATE: November 5, 2012
FILE NO.:

Chilco Trails Update

Page 34–35

RECOMMENDATION:

THAT this report be received for information;

AND THAT Council consider additional funds for Phase 2 in the 2013 budget.

Page 34–35

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

Page 34–35

PURPOSE OF REPORT:

To advise Council of a project budget shortfall and as a result, that only Phase 1 of the project will be completed at this time.

Page 34–35

TIME CRITICAL:

Only if Council wishes for Phase 1 and 2 to proceed this year.

Page 34–35

BACKGROUND:

The Chilco Trail plan was completed earlier in 2012. The Plan was funded through a developer contribution. Based on the adopted plan, Phases 1 and 2 will cost approximately $110,000.00 to construct which will include the purchase and storage of extra rock and a 20% contingency. Based on the amount budgeted and the remaining developer contribution, there is only $81,500.00 available at this time, resulting in a shortfall of $28,500.00.

If the extra rock intended to be purchased as part of phase 1 is deferred to a future phase, the budget shortfall is approximately $22,500.00. Staff do not recommend removing the contingency from the budget as it is anticipated that unexpected site conditions will be encountered during the construction process.

Page 34–35

PROJECT INFORMATION:

Staff are prepared to issue an RFP immediately for Phase 1 and anticipate that work will commence in December.

Page 34–35

BUDGET IMPLICATIONS:

There are sufficient funds to complete Phase 1. Staff will bring forward a budget request to fund future phases as part of the 2013 budget considerations.

It is possible that not all capital projects that were budgeted in 2012 will be started (meaning all committed funds may not actually be expended), however there is no way to be certain of this.

Page 34–35

RECOMMENDATION:

THAT this report be received for information;

AND THAT Council consider additional funds for Phase 2 in the 2013 budget.

SUBMITTED BY: Lindsay Chase, Director of Development Services