Capital Regional Hospital District Board Meeting Minutes - August 2, 2017
Minutes of the special meeting of the Capital Regional Hospital District Board focused on awarding multiple construction contracts for The Summit at Quadra Village Project.
Capital Regional Hospital District Board Meeting Minutes
Wednesday, August 2, 2017 | 10:00 AM 6th Floor Boardroom, 625 Fisgard Street, Victoria, BC
Special Meeting
PRESENT: DIRECTORS: B. Desjardins (Chair), M Alto (Vice-Chair), R. Atwell, D. Blackwell, S. Brice, J. Brownoff, C. Stock (for A. Finall), S. Brice, C. Hamilton, L. Helps, M. Hicks, D. Howe, B. Isitt, K. Murdoch (for N. Jensen), W. McIntyre, V. Sanders (for D. Murdock), C. Plant, J. Ranns, J. Rogers (for D. Screech), M. Tait, K. Williams, R. Windsor, and G. Young
STAFF: R. Lapham, Chief Administrative Officer; N. Chan, Chief Financial Officer; D. Wilkinson; M. Walton, Acting General Manager, Parks and Environmental Services; S. Bagh, Acting General Manager, Planning and Protective Services; M. McCrank, Acting General Manager, Integrated Water Services; M. Barnes, Manager, Health and Capital Planning Strategies; D. Wilkinson, Project Manager; D. Green, Environmental Science Officer; B. Reems, Corporate Officer; and E. Gorman, Deputy Corporate Officer (Recorder).
Regrets: Directors Isitt, Blackwell, and Seaton.
The meeting was called to order at 10:09 am.
1. APPROVAL OF THE AGENDA
MOVED by Director Helps, SECONDED by Director Tait, That the agenda be approved as circulated. CARRIED
2. PRESENTATIONS/DELEGATIONS
2.1 Presentations
There were none.
2.2 Delegations
There were none.
3. SPECIAL MEETING MATTERS
3.1. 17-589 The Summit at Quadra Village Project Main Works Packages Award of Contracts CRHD.2017-4-007 through CRHD.2017-11-014
In response to questions, staff advised that:
- construction management approach was used to get bids under original budgeted/projected cost amount
- reporting on how the position (consultant) works with the project director to ensure the tendering process is achieved
- construction oversight executive to scope the project with an affordability ceiling
- confirmation regarding contingency, that these are fixed price contracts and contingency covers increase in scope
- forward health requisitions may be impacted positively as a result
- a summary report will be included in the cash flow projections for hospital district budget and service plan
MOVED by Director Howe, SECONDED by Director Helps, a) That Contract CRHD.2017-04-007-Concrete Unit Masonry for the Summit at Quadra Village Project be awarded to Rob Tournour Masonry Ltd. in the amount of $857,400 [excluding GST] and that a project contingency of $25,722 [excluding GST] be approved. b) That Contract CRHD.2017-05-008-Structural Steel for the Summit at Quadra Village Project be awarded to Alliance Engineering Works [1985] Ltd. in the amount of $539,000 [excluding GST] and that a project contingency of $16,170 [excluding GST] be approved. c) That Contract CRHD.2017-06-009-Cabinetwork for the Summit at Quadra Village Project be awarded to Fraser Valley Industries Ltd. in the amount of $1,116,293 [excluding GST] and that a project contingency of $33,489 [excluding GST] be approved. d) That Contract CRHD.2017-07-010-Preformed Metal Siding for the Summit at Quadra Village Project be awarded to Topline Roofing Ltd. in the amount of $2,025,881 [excluding GST] and that a project contingency of $60,776 [excluding GST] be approved. e) That Contract CRHD.2017-08-011-Modified Bituminous Membrane Roofing for the Summit at Quadra Village Project be awarded to Topline Roofing Ltd. in the amount of $1,459,258 [excluding GST] and that a project contingency of $43,778 [excluding GST] be approved. f) That Contract CRHD.2017-09-012-Gypsum Board for the Summit at Quadra Village Project be awarded to Dryco Systems Inc. in the amount of $4,775,000 [excluding GST] and that a project contingency of $143,250 [excluding GST] be approved. g) That Contract CRHD.2017-10-013-Wall and Door Protection for the Summit at Quadra Village Project be awarded to McGregor & Thompson Hardware Ltd. in the amount of $617,770 [excluding GST] and that a project contingency of $18,533 [excluding GST] be approved. h) That Contract CRHD.2017-11-014-Electrical for the Summit at Quadra Village Project be awarded to Canem Systems Ltd. in the amount of $5,879,172 [excluding GST] and that a project contingency of $176,375 [excluding GST] be approved. CARRIED
4. MOTION TO CLOSE THE MEETING
There was none.
5. ADJOURNMENT
MOVED by Director Tait, SECONDED by Director Helps, That the meeting be adjourned at 10:21 a.m. CARRIED
