Council Meeting/Documents/Appendix B - Capital Project Update Report
Appendix

Appendix B - Capital Project Update Report

October 17, 2017Page 512 sections

Status report for 2017 capital projects, showing budget amounts, year-to-date spending, and expected completion dates.

Total 2017 Capital Projects Budget: $3,024,635

Capital Project Update Report as at October 11, 2017 Appendix B

Transportation

Road Reconstruction

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11105 Road Projects 1109 Burnett Rd-Pheasant Ln (ld Isl Hwy) Cons 185,465 190,000 4,535 98% Complete
11105 Road Projects 1111 Island Hwy Stewart to Beaumont - Design 50,644 93,330 42,686 54% 2018
11105 Road Projects 1139 Stoneridge Development Sidewalk Replcmt 44,310 45,000 690 98% Complete
11105 Road Projects 1140 Watkiss Way Median East of Talcott Road 52,387 55,000 2,613 95% Complete

Miscellaneous

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11106 Other Transportation Projects 1074 Watkiss Way Improved Ped Walkway & Light - 20,000 20,000 0% 2018
11106 Other Transportation Projects 1120 ECV - Park Trail to Little Rd N end ph 2 48,767 70,000 21,233 70% Complete
11106 Other Transportation Projects 1121 Kayak launch on Shoreline Drive (250) 24,000 24,250 -1% 2018
11106 Other Transportation Projects 1122 Quincy St Pedestrian Access 3,731 35,000 31,269 11% Complete

Annual Pavement Rehabilitation

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11107 Repaving 1141 Westoby Road Seal Coating 40,974 40,000 (974) 102% Complete
11107 Repaving 1142 Atkins Road East of Six Mile Road repair 62,806 70,000 7,194 90% Complete
11107 Repaving 1143 Hospital Way 36,737 37,500 763 98% Complete

Electrical

| 2017 Capital Projects | Cost Centre | Description | Year to Date | Budget Amount | Variance | % Var | Expected Completion | | :--- | :--- | : :--- | :--- | :--- | :--- | :--- | :--- | | 11108 Signals | 1118 | Isl Hwy at Heddle ped crosswalk | 56,667 | 150,000 | 93,333 | 38% | December | | 11108 Signals | 1144 | Isl Hwy Knollwood/Kislinbury ped heads | 36,223 | 30,000 | (6,223) | 121% | Complete | | 11108 Signals | 1145 | Burnside Rd W at High St Flashing Ped X | 47,084 | 40,000 | (7,084) | 118% | November |

Structures

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11109 Bridges 1013 Craigflower Bridge Construction - Land - 10,000 10,000 0% December
SUB-TOTAL 665,545 909,830 244,285 73%

Drainage

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11201 Collection System (Drainage) 1124 VR Ave-Beaumont Ave to Stew. Ave design 8,398 14,000 5,602 60% December
SUB-TOTAL 8,398 14,000 5,602

Sewer

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11702 Lift Stations 1125 Price Bay Pump Stn upgrade 132,345 378,500 246,155 35% 2018
11702 Lift Stations 1146 Stoneridge and Wilfert Pump Stn Pumps 29,293 35,000 5,707 84% Complete
SUB-TOTAL 161,638 413,500 251,862

Parks

Park Improvements

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11302 Park Improvements 1129 Playgrounds - replacement program 17,010 52,000 34,990 33% Complete

Park Development

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11303 Park Development 1028 View Royal Park 299 150,000 149,701 0% December
11303 Park Development 1147 Chilco Trails Implementation Plan - 75,000 75,000 0% November

Park Vehicles

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11304 Park Vehicles 1132 New 1/2 Ton Park Pick up and accessories 39,982 21,756 (18,226) 184% Complete

Improvement to Public Buildings

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
11401 Building Improvements 1133 Park Shop repair 12,060 - (12,060) 0% Complete
11401 Building Improvements 1136 Flag poles 2,678 5,000 2,322 54% November
11401 Building Improvements 1138 Council Chamber - renovation 2,347 27,000 24,653 9% On Hold
SUB-TOTAL 74,376 330,756 256,380

Fire Services

Buildings

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
12101 Fire - Buildings 1149 Training Ground 3,154 100,000 96,846 3% December
12101 Fire - Buildings 1032 Public Safety Building 52,784 - (52,784) 0% Complete

Vehicles

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
12102 Fire - Vehicles 1033 Fire Engine - 750,000 750,000 0% Deferred

Furniture & Equipment

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
12103 Fire - Furniture and Equipment 1150 Hose Replacement 9,787 15,000 5,213 65% Complete
12103 Fire - Furniture and Equipment 1151 Tires 9,038 15,000 5,962 60% October
SUB-TOTAL 74,763 880,000 805,237

Police Services

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
12301 Police Services 1152 RCMP 2017 capital projects - 47,400 47,400 0% TBD
SUB-TOTAL - 47,400 47,400

Administration / General Government

Page 51

Information Technology

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
13103 Information Technology 1070 Annual IS Replacement Program - 51,000 51,000 0% December
13103 Information Technology 1135 IT strategic plan implementation 10,308 278,149 267,841 4% December

Land Acquisitions

2017 Capital Projects Cost Centre Description Year to Date Budget Amount Variance % Var Expected Completion
13201 Land Acquisitions 1045 Misc Land Acquisitions - 100,000 100,000 0% Ongoing
SUB-TOTAL 10,308 429,149 418,841

Year to Date Budget Amount Variance
Total 2017 Capital Projects 995,029 3,024,635 2,029,606
Page 51
Extracted from: 2017 10 17 Council Agenda - Agenda - Pdf