This site is in beta — data may be incomplete and features are still being added.
Council Meeting/Documents/Appendix E - Transit Priority Measures Construction Cost Estimate
Appendix

Appendix E - Transit Priority Measures Construction Cost Estimate

January 15, 2019Pages 93–10910 sections

A detailed line-item breakdown of construction costs for the various infrastructure packages (S1 through N3) involved in the transit priority plan.

1 CALL TO ORDER
Package S1 total: $512,500Package S3 total: $1,086,890Package N3 total: $608,760Date of estimates: 9 July '18

Island Highway Transit Priority Plan and Park & Ride Study

Page 93–109

Final Report

BC Transit

July 2018

Appendix E - Transit Priority Measures Construction Cost Estimate

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: S1

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 60,496
10.1.01 Remove Existing Pavement 58.9 M2 15.0 884
10.1.02 Remove Existing Concrete Sidewalk 383.0 M2 20.0 7,661
10.1.03 Remove Existing Curb & Gutter 192.0 M 15.0 2,880
10.1.04 Saw Cut 196.4 M 8.0 1,571
10.1.05 Relocate Existing Street Lighting Pole 2.0 EA 6,000.0 12,000
10.1.06 Relocate Existing Traffic Signal 1.0 EA 10,000.0 10,000
10.1.07 Relocate Existing OH Hydro Pole 1.0 EA 15,000.0 15,000
10.1.08 Relocate Existing Hydro Box & MHs 1.0 EA 2,000.0 2,000
10.1.09 Relocate Existing CB 2.0 EA 2,500.0 5,000
10.1.10 Protect Water Main 1.0 LS 1,000.0 1,000
10.1.11 Adjust unknow Boxes & MHs 5.0 EA 500.0 2,500
10 SUB-TOTAL: Site Removal & Utility Work 60,496
20 Grading & Paving Work
20.1 Grading & Paving Work 192,530
20.1.01 Clearing & Topsoil Stripping 916.8 M2 6.0 5,501
20.1.02 Soil Excavation & Disposal 458.4 M3 25.0 11,460
20.1.03 Granular Subbase SGSB 300mm thk 289.0 M3 50.0 14,449
20.1.04 Granular Base Course 300mm thk 289.0 M3 60.0 17,339
20.1.05 Primer and Tack Coat 963.3 M2 2.0 1,927
20.1.05 HMA Asphalt 150mm 354.0 MT 200.0 70,802
20.1.06 Pavement Joint 191.0 M 10.0 1,910
20.1.07 New Curb & Gutter 191.5 M 160.0 30,638
20.1.08 New Concrete Sidewalk 287.2 M2 110.0 31,594
20.1.09 Pavement Marking 1.0 LS 5,000.0 5,000
20.1.10 Landcape (Sod/Seeding Restoration) 191.0 M2 10.0 1,910
20 SUB-TOTAL: Grading & Paving Work 192,530
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 20.4 M3 650.00 13,231
30.1.03 Bus Station Concrete Platform 24.2 M3 900.00 21,748
30.1.04 Tactile Warning Tiles 28.0 LM 170.00 4,760
30.1.05 Granular Base 150mm thk 14.7 M3 50.00 735
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 156,974
DIRECT COST SUB- TOTAL : 410,000
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 16,400.00 16,400
40.1.02 Traffic Management (5%) 1.0 LS 20,500.00 20,500
40.1.03 Risk & Contigency (8%) 1.0 LS 32,800.00 32,800
40.1.04 Detail Engingeering Cost (8%) 1.0 LS 32,800.00 32,800
40 SUB-TOTAL: INDIRECT COST 102,500
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE S1 512,500

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: S2

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 16,335
10.1.01 Remove Existing Pavement 42.9 M2 15.0 644
10.1.02 Remove Existing Curb & Gutter 143.1 M 15.0 2,146
10.1.03 Saw Cut 143.1 M 8.0 1,145
10.1.04 Relocate Existing Street Lighting Pole 2.0 EA 6,000.0 12,000
10.1.05 Relocate Existing Small Signs 1.0 EA 400.0 400
10 SUB-TOTAL: Site Removal & Utility Work 16,335
20 Grading & Paving Work
20.1 Grading & Paving Work 68,259
20.1.01 Clearing & Topsoil Stripping 227.0 M2 6.0 1,362
20.1.02 Soil Excavation & Disposal 113.5 M3 25.0 2,838
20.1.03 Granular Subbase SGSB 300mm thk 68.0 M3 50.0 3,401
20.1.04 Granular Base Course 300mm thk 68.0 M3 60.0 4,081
20.1.05 Primer and Tack Coat 226.7 M2 2.0 453
20.1.06 HMA Asphalt 150mm 83.3 MT 200.0 16,664
20.1.07 Pavement Joint 144.0 M 20.0 2,880
20.1.08 Mill & Overlay Asphlat Pavement 200.0 M2 55.0 11,000
20.1.09 New Curb & Gutter 144.0 M 160.0 23,040
20.1.10 Pavement Marking 1.0 LS 1,100.0 1,100
20.1.11 Landcape (Sod/Seeding Restoration) 144.0 M2 10.0 1,440
20 SUB-TOTAL: Grading & Paving Work 68,259
DIRECT COST SUB- TOTAL : 84,590
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 3,380.00 3,380
40.1.02 Traffic Management (5%) 1.0 LS 4,230.00 4,230
40.1.03 Risk & Contigency (8%) 1.0 LS 6,770.00 6,770
40.1.04 Detail Engineering Cost (8%) 1.0 LS 6,770.00 6,770
40 SUB-TOTAL: INDIRECT COST 21,150
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE S2 105,740

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: S3

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 84,838
10.1.01 Remove Existing Pavement 112.4 M2 15.0 1,687
10.1.02 Remove Existing Concrete Sidewalk 383.0 M2 20.0 7,661
10.1.03 Remove Existing Curb & Gutter 372.8 M 15.0 5,592
10.1.04 Saw Cut 374.8 M 8.0 2,998
10.1.05 Remove Conc. Barrier 20.0 M 50.0 1,000
10.1.06 Relocate Existing Street Lighting Pole 5.0 EA 6,000.0 30,000
10.1.07 Relocate Existing Traffic Signal 1.0 EA 10,000.0 10,000
10.1.08 Relocate Existing OH Hydro Pole 1.0 EA 15,000.0 15,000
10.1.09 Relocate Existing Hydro Box & MHs 1.0 EA 2,000.0 2,000
10.1.10 Relocate Existing CB 2.0 EA 2,500.0 5,000
10.1.11 Protect Water Main 1.0 LS 1,000.0 1,000
10.1.12 Adjust unknow Boxes & MHs 5.0 EA 500.0 2,500
10.1.13 Relocate Existing Small Signs 1.0 EA 400.0 400
10 SUB-TOTAL: Site Removal & Utility Work 84,838
20 Grading & Paving Work
20.1 Grading & Paving Work 330,602
20.1.01 Clearing & Topsoil Stripping 1,403.0 M2 6.0 8,418
20.1.02 Soil Excavation & Disposal 701.5 M3 25.0 17,538
20.1.03 Granular Subbase SGSB 300mm thk 507.2 M3 50.0 25,359
20.1.04 Granular Base Course 300mm thk 507.2 M3 60.0 30,431
20.1.05 Primer and Tack Coat 1,690.6 M2 2.0 3,381
20.1.06 HMA Asphalt 150mm 621.3 MT 200.0 124,259
20.1.07 Pavement Joint 335.0 M 20.0 6,700
20.1.08 Mill & Overlay Asphlat Pavement 200.0 M2 55.0 11,000
20.1.09 New Curb & Gutter 350.6 M 160.0 56,101
20.1.10 New Concrete Sidewalk 282.4 M2 110.0 31,065
20.1.11 Pavement Marking 1.0 LS 13,000.0 13,000
20.1.12 Landcape (Sod/Seeding Restoration) 335.0 M2 10.0 3,350
20 SUB-TOTAL: Grading & Paving Work 330,602
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 20.4 M3 650.00 13,231
30.1.03 Bus Station Concrete Platform 24.2 M3 900.00 21,748
30.1.04 Tactile Warning Tiles 28.0 LM 170.00 4,760
30.1.05 Granular Base 150mm thk 14.7 M3 50.00 735
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 156,974
35 Bridge Widening
35.1 Bridge Widening
35.1.01 Remove Bridge Conc. Barrier 35.0 M 60.00 2,100
35.1.02 New Galloping Goose Trail Pedestrian Bridge 90.0 M2 2,500.00 225,000
35.1.03 Pedstrian Bridge Approach 70.0 M2 1,000.00 70,000
35 SUB-TOTAL: Bridge Widening 297,100
DIRECT COST SUB- TOTAL : 869,510
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 34,780.00 34,780
40.1.02 Traffic Management (5%) 1.0 LS 43,480.00 43,480
40.1.03 Risk & Contigency (8%) 1.0 LS 69,560.00 69,560
40.1.04 Detail Engineering Cost (8%) 1.0 LS 69,560.00 69,560
40 SUB-TOTAL: INDIRECT COST 217,380
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE S3 1,086,890

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: S4

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 164,897
10.1.01 Remove Existing Pavement 150.1 M2 15.0 2,252
10.1.02 Remove Existing Concrete Sidewalk 1,037.7 M2 20.0 20,753
10.1.03 Remove Existing Curb & Gutter 492.6 M 15.0 7,389
10.1.04 Saw Cut 500.4 M 8.0 4,003
10.1.05 Relocate Existing Street Lighting Pole 8.0 EA 6,000.0 48,000
10.1.06 Relocate Existing Traffic Signal 1.0 EA 10,000.0 10,000
10.1.07 Relocate Existing Ped. Traffic Signal 2.0 EA 5,000.0 10,000
10.1.08 Relocate Existing OH Hydro Pole 3.0 EA 15,000.0 45,000
10.1.09 Relocate Existing Hydro Box & MHs 1.0 EA 2,000.0 2,000
10.1.10 Relocate Existing CB 4.0 EA 2,500.0 10,000
10.1.11 Protect Water Main 1.0 LS 500.0 500
10.1.12 Relocate Hydrant 1.0 EA 5,000.0 5,000
10 SUB-TOTAL: Site Removal & Utility Work 164,897
20 Grading & Paving Work
20.1 Grading & Paving Work 403,372
20.1.01 Clearing & Topsoil Stripping 916.8 M2 6.0 5,501
20.1.02 Soil Excavation & Disposal 458.4 M3 25.0 11,460
20.1.03 Granular Subbase SGSB 300mm thk 562.8 M3 50.0 28,138
20.1.04 Granular Base Course 300mm thk 562.8 M3 60.0 33,765
20.1.05 Primer and Tack Coat 1,875.8 M2 2.0 3,752
20.1.06 HMA Asphalt 150mm 689.4 MT 200.0 137,874
20.1.07 Pavement Joint 500.0 M 20.0 10,000
20.1.08 New Curb & Gutter 487.2 M 160.0 77,946
20.1.09 New Concrete Sidewalk 744.9 M2 110.0 81,936
20.1.10 Pavement Marking 1.0 LS 8,000.0 8,000
20.1.11 Landcape (Sod/Seeding Restoration) 500.0 M2 10.0 5,000
20 SUB-TOTAL: Grading & Paving Work 403,372
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 20.4 M3 650.00 13,231
30.1.03 Bus Station Concrete Platform 24.2 M3 900.00 21,748
30.1.04 Tactile Warning Tiles 28.0 LM 170.00 4,760
30.1.05 Granular Base 150mm thk 14.7 M3 50.00 735
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 156,974
DIRECT COST SUB- TOTAL : 725,240
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 29,010.00 29,010
40.1.02 Traffic Management (5%) 1.0 LS 36,260.00 36,260
40.1.03 Risk & Contigency (8%) 1.0 LS 58,020.00 58,020
40.1.04 Detail Engineering Cost (8%) 1.0 LS 58,020.00 58,020
40 SUB-TOTAL: INDIRECT COST 181,310
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE S4 906,550

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: S5

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 69,927
10.1.01 Remove Existing Pavement 58.9 M2 15.0 883
10.1.02 Remove Existing Concrete Sidewalk 345.5 M2 20.0 6,910
10.1.03 Remove Existing Curb & Gutter 184.4 M 15.0 2,766
10.1.04 Remove Existing Island 39.9 M2 20.0 798
10.1.05 Saw Cut 196.3 M 8.0 1,570
10.1.07 Relocate Existing Traffic Signal 2.0 EA 10,000.0 20,000
10.1.08 Relocate Existing OH Hydro Pole 2.0 EA 15,000.0 30,000
10.1.09 Relocate Existing Hydro Box & MHs 1.0 EA 2,000.0 2,000
10.1.10 Relocate Existing CB 2.0 EA 2,500.0 5,000
10 SUB-TOTAL: Site Removal & Utility Work 69,927
20 Grading & Paving Work
20.1 Grading & Paving Work 124,599
20.1.01 Remove Sod 60.0 M2 3.0 180
20.1.02 Soil Excavation & Disposal 30.0 M3 25.0 750
20.1.03 Granular Subbase SGSB 300mm thk 90.9 M3 50.0 4,547
20.1.04 Granular Base Course 300mm thk 90.9 M3 60.0 5,456
20.1.05 Primer and Tack Coat 303.1 M2 2.0 606
20.1.06 HMA Asphalt 150mm 111.4 MT 200.0 22,280
20.1.07 Pavement Joint 200.0 M 20.0 4,000
20.1.08 Mill & Overlay Asphlat Pavement 43.1 M2 55.0 2,370
20.1.09 New Curb & Gutter 179.6 M 160.0 28,729
20.1.10 New Concrete Sidewalk 300.1 M2 110.0 33,010
20.1.11 New Island Perimeter Curb 36.7 M 90.0 3,304
20.1.12 New Island Infill 53.1 M2 90.0 4,775
20.1.13 New Truck Apron 79.9 M2 120.0 9,592
20.1.14 Pavement Marking 1.0 LS 4,000.0 4,000
20.1.15 Landcape (Sod/Seeding Restoration) 100.0 M2 10.0 1,000
20 SUB-TOTAL: Grading & Paving Work 124,599
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 20.4 M3 650.00 13,231
30.1.03 Bus Station Concrete Platform 24.2 M3 900.00 21,748
30.1.04 Tactile Warning Tiles 28.0 LM 170.00 4,760
30.1.05 Granular Base 150mm thk 14.7 M3 50.00 735
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 156,974
DIRECT COST SUB- TOTAL : 351,500
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 14,060.00 14,060
40.1.02 Traffic Management (5%) 1.0 LS 17,580.00 17,580
40.1.03 Risk & Contigency (8%) 1.0 LS 28,120.00 28,120
40.1.04 Detail Engineering Cost (8%) 1.0 LS 28,120.00 28,120
40 SUB-TOTAL: INDIRECT COST 87,880
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE S5 439,380

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: N1

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 59,020
10.1.01 Remove Existing Pavement 77.6 M2 15.0 1,165
10.1.02 Remove Existing Concrete Sidewalk 413.3 M2 20.0 8,266
10.1.03 Remove Existing Curb & Gutter 251.1 M 15.0 3,766
10.1.04 Remove Existing Island 37.7 M2 20.0 753
10.1.05 Saw Cut 258.8 M 8.0 2,070
10.1.06 Relocate Existing Street Lighting Pole 1.0 EA 6,000.0 6,000
10.1.07 Relocate Existing Traffic Signal 1.0 EA 10,000.0 10,000
10.1.08 Relocate Existing Ped. Traffic Signal 2.0 EA 5,000.0 10,000
10.1.09 Relocate Existing OH Hydro Pole 1.0 EA 15,000.0 15,000
10.1.10 Relocate Existing Hydro Box & MHs 1.0 EA 2,000.0 2,000
10 SUB-TOTAL: Site Removal & Utility Work 59,020
20 Grading & Paving Work
20.1 Grading & Paving Work 172,036
20.1.01 Remove Sod & Others 200.0 M2 6.0 1,200
20.1.02 Soil Excavation & Disposal 100.0 M3 25.0 2,500
20.1.03 Granular Subbase SGSB 300mm thk 210.0 M3 40.0 8,402
20.1.04 Granular Base Course 300mm thk 210.0 M3 50.0 10,502
20.1.05 Primer and Tack Coat 700.2 M2 2.0 1,400
20.1.05 HMA Asphalt 150mm 257.3 MT 200.0 51,461
20.1.06 Pavement Joint 250.0 M 20.0 5,000
20.1.07 Mill & Overlay Asphlat Pavement 35.1 M2 55.0 1,932
20.1.08 New Curb & Gutter 243.3 M 160.0 38,935
20.1.09 New Concrete Sidewalk 369.9 M2 110.0 40,685
20.1.10 New Island Perimeter Curb 23.4 M 90.0 2,109
20.1.11 New Island Infill 29.0 M2 90.0 2,610
20.1.13 Pavement Marking 1.0 LS 4,500.0 4,500
20.1.14 Landcape (Sod/Seeding Restoration) 80.0 M2 10.0 800
20 SUB-TOTAL: Grading & Paving Work 172,036
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 10.2 M3 650.00 6,616
30.1.03 Bus Station Concrete Platform 12.1 M3 900.00 10,874
30.1.04 Tactile Warning Tiles 14.0 LM 170.00 2,380
30.1.05 Granular Base 150mm thk 7.4 M3 50.00 368
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 136,738
DIRECT COST SUB- TOTAL : 367,790
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 14,710.00 14,710
40.1.02 Traffic Management (5%) 1.0 LS 18,390.00 18,390
40.1.03 Risk & Contigency (8%) 1.0 LS 29,420.00 29,420
40.1.04 Detail Engineering Cost (8%) 1.0 LS 29,420.00 29,420
40 SUB-TOTAL: INDIRECT COST 91,940
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE N1 459,730

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: N2

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 27,093
10.1.01 Remove Existing Pavement 35.3 M2 15.0 530
10.1.02 Remove Existing Concrete Sidewalk 210.5 M2 20.0 4,211
10.1.03 Remove Existing Curb & Gutter 112.2 M 15.0 1,683
10.1.04 Remove Existing Island 61.3 M2 20.0 1,227
10.1.05 Saw Cut 117.7 M 8.0 942
10.1.05 Relocate Existing Street Lighting Pole 1.0 EA 6,000.0 6,000
10.1.07 Relocate Existing Traffic Signal 1.0 EA 10,000.0 10,000
10.1.10 Relocate Existing CB 1.0 EA 2,500.0 2,500
10 SUB-TOTAL: Site Removal & Utility Work 27,093
20 Grading & Paving Work
20.1 Grading & Paving Work 110,086
20.1.01 Remove Sod & Others 20.0 M2 6.0 120
20.1.02 Soil Excavation & Disposal 10.0 M3 25.0 250
20.1.03 Granular Subbase SGSB 300mm thk 90.6 M3 50.0 4,530
20.1.04 Granular Base Course 300mm thk 90.6 M3 60.0 5,436
20.1.05 Primer and Tack Coat 302.0 M2 2.0 604
20.1.06 HMA Asphalt 150mm 111.0 MT 200.0 22,195
20.1.07 Pavement Joint 145.0 M 20.0 2,900
20.1.08 Mill & Overlay Asphlat Pavement 42.7 M2 55.0 2,349
20.1.09 New Curb & Gutter 143.3 M 160.0 22,933
20.1.10 New Concrete Sidewalk 183.6 M2 110.0 20,192
20.1.11 New Island Perimeter Curb 60.9 M 90.0 5,481
20.1.12 New Island Infill 69.5 M2 90.0 6,252
20.1.13 New Truck Apron 104.5 M2 120.0 12,544
20.1.14 Pavement Marking 1.0 LS 3,500.0 3,500
20.1.15 Landcape (Sod/Seeding Restoration) 80.0 M2 10.0 800
20 SUB-TOTAL: Grading & Paving Work 110,086
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 20.4 M3 650.00 13,231
30.1.03 Bus Station Concrete Platform 24.2 M3 900.00 21,748
30.1.04 Tactile Warning Tiles 28.0 LM 170.00 4,760
30.1.05 Granular Base 150mm thk 14.7 M3 50.00 735
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 1,000.00 1,000
30.1.07 Electrical Feeds 1.0 LS 500.00 500
30.1.08 New Bus Shelter Type T5 1.0 EA 110,000.00 110,000
30 SUB-TOTAL: Bus Station 156,974
DIRECT COST SUB- TOTAL : 294,150
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 11,770.00 11,770
40.1.02 Traffic Management (5%) 1.0 LS 14,710.00 14,710
40.1.03 Risk & Contigency (8%) 1.0 LS 23,530.00 23,530
40.1.04 Detail Engineering Cost (8%) 1.0 LS 23,530.00 23,530
40 SUB-TOTAL: INDIRECT COST 73,540
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE N2 367,690

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST

Page 93–109

Project: Island Hwy Transit Priority Plan

Client: BC Transit

Date: 9 July '18

Package: N3

Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 33,362
10.1.01 Remove Existing Pavement 342.7 M2 15.0 5,140
10.1.02 Remove Existing Concrete Sidewalk 305.7 M2 20.0 6,113
10.1.03 Remove Existing Curb & Gutter 207.1 M 15.0 3,107
10.1.04 Remove Existing Island 96.3 M2 20.0 1,927
10.1.05 Saw Cut 321.9 M 8.0 2,575
10.1.06 Relocate Existing Street Lighting Pole 1.0 EA 6,000.0 6,000
10.1.07 Relocate Existing Traffic Signal 0.0 EA 10,000.0 ---
10.1.10 Protect Water Main 1.0 LS 1,000.0 1,000
10.1.11 Relocate Existing CB 3.0 EA 2,500.0 7,500
10 SUB-TOTAL: Site Removal & Utility Work 33,362
20 Grading & Paving Work
20.1 Grading & Paving Work 164,936
20.1.01 Remove Sod & Others 60.0 M2 6.0 360
20.1.02 Soil Excavation & Disposal 30.0 M3 25.0 750
20.1.03 Granular Subbase SGSB 300mm thk 168.7 M3 50.0 8,437
20.1.04 Granular Base Course 300mm thk 168.7 M3 60.0 10,125
20.1.05 Primer and Tack Coat 562.5 M2 2.0 1,125
20.1.05 HMA Asphalt 150mm 206.7 MT 200.0 41,343
20.1.06 Pavement Joint 205.0 M 20.0 4,100
20.1.08 New Curb & Gutter 205.1 M 160.0 32,820
20.1.09 New Concrete Sidewalk 321.6 M2 110.0 35,379
20.1.10 New Island Perimeter Curb 86.0 M 90.0 7,742
20.1.11 New Island Infill 177.3 M2 90.0 15,955
20.1.13 Pavement Marking 1.0 LS 6,000.0 6,000
20.1.14 Landcape (Sod/Seeding Restoration) 80.0 M2 10.0 800
20 SUB-TOTAL: Grading & Paving Work 164,936
30 Bus Station
30.1 Bus Station
30.1.01 Remove & Store Existing Bus Shelter 1.0 EA 5,000.00 5,000
30.1.02 Concrete Bus Pad with Curb 30.5 M3 650.00 19,847
30.1.03 Bus Station Concrete Platform 36.2 M3 900.00 32,621
30.1.04 Tactile Warning Tiles 42.0 LM 170.00 7,140
30.1.05 Granular Base 150mm thk 22.1 M3 50.00 1,103
30.1.06 Storm Drain Pipe & Tie-in 1.0 LS 2,000.00 2,000
30.1.07 Electrical Feeds 1.0 LS 1,000.00 1,000
30.1.08 New Bus Shelter Type T5 2.0 EA 110,000.00 220,000
30 SUB-TOTAL: Bus Station 288,711
DIRECT COST SUB- TOTAL : 487,010
40 INDIRECT COST
40.1 Indirect Cost
40.1.01 Mobilzation (4%) 1.0 LS 19,480.00 19,480
40.1.02 Traffic Management (5%) 1.0 LS 24,350.00 24,350
40.1.03 Risk & Contigency (8%) 1.0 LS 38,960.00 38,960
40.1.04 Detail Engineering Cost (8%) 1.0 LS 38,960.00 38,960
40 SUB-TOTAL: INDIRECT COST 121,750
TOTAL - ISLAND HWY TRANSIT PRIORITY PLAN PACKAGE N3 608,760

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST
Page 93–109

Document Images

(2)
Document image
Document image
Extracted from: 2019 01 15 Council Agenda - Agenda - Pdf