Council Meeting/Documents/Appendix H: Conceptual Construction Cost Estimate - 6-Mile Park & Ride
Appendix

Appendix H: Conceptual Construction Cost Estimate - 6-Mile Park & Ride

January 15, 2019Pages 141–1432 sections

Detailed cost breakdown for site removal, grading, paving, and signaling for the 6-Mile Park & Ride project.

1 CALL TO ORDER
Total Estimated Cost: $2,270,890Date: 23 July '18Includes $200,000 for traffic signals

Island Highway Transit Priority Plan and Park & Ride Study

Final Report

BC Transit July 2018

Page 141–143

Appendix H – Conceptual Construction Cost Estimate - Park & Ride Facilities

6-Mile Park & Ride

PROJECT: ISLAND HWY TRANSIT PRIORITY PLAN
CLIENT: BC TRANSIT
DATE: 23 JULY '18
PACKAGE: 6-Mile Park & Ride
Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 46,705
10.1.01 Remove Existing Pavement 1,373.0 M2 15.0 20,595
10.1.02 Remove Existing Curb & Gutter 106.0 M 15.0 1,590
10.1.03 Saw Cut 190.0 M 8.0 1,520
10.1.04 Relocate Existing Street Lighting Pole 1.0 EA 6,000.0 6,000
10.1.05 Relocate Trail Signage and Bench 2.0 EA 7,500.0 15,000
10.1.06 Remove others 1.0 LS 2,000.0 2,000
10 SUB-TOTAL: Site Removal & Utility Work 46,705
20 Grading & Drainage Work
20.1 Grading & Drainage Work 409,540
20.1.01 Clearing & Grubbing 7,300.00 M2 8.00 58,400
20.1.01 Topsoil Stripping 7,300.00 M2 5.0 36,500
20.1.02 Soil Import Fill 7,300.0 M3 25.0 182,500
20.1.03 PVC 200mm Pipe 592.0 M 120.0 71,040
20.1.04 PVC 300mm Pipe 150.0 M 150.0 22,500
20.1.05 Catch Basin 26.0 EA 1,000.0 26,000
20.1.05 Oil/ water Separator 3.0 EA 20,000.0 60,000
20.1.06 Manhole 1.0 EA 5,000.0 5,000
20.1.07 Headwall/Rip Rap 1.0 EA 6,000.0 6,000
20 SUB-TOTAL: Grading & Drainage Work 409,540
30 Paving & Concrete Flat Work
30.1 Paving & Concrete Flat Work 1,035,606
30.1.01 Granular Subbase SGSB 300mm thk 3,575.9 M3 45.0 160,915
30.1.02 Granular Base Course 300mm/250mm thk 3,156.6 M3 55.0 173,612
30.1.03 Primer and Tack Coat 12,680.4 M2 2.0 25,361
30.1.04 HMA Asphalt 75mm 2,330.0 MT 180.0 419,403
30.1.05 Pavement Joint 190.0 M 10.0 1,900
30.1.06 New Curb & Gutter 693.6 M 160.0 110,973
30.1.07 New Concrete Sidewalk 380.0 M2 110.0 41,800
30.1.08 Median 168.9 M2 100.0 16,895
30.1.09 Island 41.1 M2 100.0 4,110
30.1.10 Pavement Marking 1.0 LS 10,000.0 10,000
30.1.11 Landcape (Sod/Seeding Restoration) 600.0 M2 10.0 6,000
30.1.12 Fence 108.0 M 120.0 12,960
30.1.13 Railing 18.6 M 90.0 1,677
30.1.14 Bike Shelter for 36 Bikes 1.0 EA 50,000.0 50,000
30 SUB-TOTAL: Paving & Concrete Flat Work 1,035,606
40 Traffic Signalling & Lighting
40.1 Traffic Signalling & Lighting
40.1.01 Traffic Signals 1.0 EA 200,000.00 200,000
40.1.02 Lighting 24.0 EA 4,000.0 96,000
40 SUB-TOTAL: Traffic Signalling & Lighting 296,000
DIRECT COST SUB- TOTAL : 1,846,250
50 INDIRECT COST
50.1 Indirect Cost
50.1.01 Mobilzation (4%) 1.0 LS 73,850.00 73,850
50.1.02 Traffic Management (3%) 1.0 LS 55,390.00 55,390
50.1.03 Risk & Contigency (8%) 1.0 LS 147,700.00 147,700
50.1.04 Detail Engingeering Cost (8%) 1.0 LS 147,700.00 147,700
50 SUB-TOTAL: INDIRECT COST 424,640
TOTAL - 6 MILE PARK & RIDE 2,270,890

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST
Page 141–143