Council Meeting/Documents/Conceptual Construction Cost Estimate - Station Ave P&R
Appendix

Conceptual Construction Cost Estimate - Station Ave P&R

January 15, 2019Pages 144–1451 section

Construction cost estimate for the Station Ave P&R facility.

1 CALL TO ORDER
Total Estimated Cost: $1,060,770Date: 23 July '18Includes $198,350 in indirect costs

PROJECT: ISLAND HWY TRANSIT PRIORITY PLAN

CLIENT: BC TRANSIT
DATE: 23 JULY '18
PACKAGE: Station Ave P&R Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 29,210
10.1.01 Remove Existing Pavement 600.0 M2 15.0 9,000
10.1.02 Remove Existing Concrete Block Sidewalk 90.0 M2 20.0 1,800
10.1.03 Remove Existing Curb & Gutter 142.0 M 15.0 2,130
10.1.04 Saw Cut 460.0 M 8.0 3,680
10.1.05 Remove Trees 4.0 EA 500.0 2,000
10.1.06 Remove Existing MHs 3.0 EA 2,500.0 7,500
10.1.07 Adjust CBs 1.0 EA 500.0 500
10.1.08 Remove others 1.0 LS 2,600.0 2,600
10 SUB-TOTAL: Site Removal & Utility Work 29,210
20 Grading & Drainage Work
20.1 Grading & Drainage Work 137,240
20.1.01 Clearing 800.00 M2 3.00 2,400
20.1.02 Topsoil Stripping 800.00 M2 5.0 4,000
20.1.03 Soil Import Fill 400.0 M3 25.0 10,000
20.1.04 PVC 200mm Pipe 427.0 M 120.0 51,240
20.1.05 Catch Basin 16.0 EA 1,000.0 16,000
20.1.06 Cisterns 8.0 EA 7,000.0 56,000
20 SUB-TOTAL: Grading & Drainage Work 137,240
30 Paving & Concrete Flat Work
30.1 Paving & Concrete Flat Work 637,572
30.1.01 Granular Subbase SGSB 300mm thk 1,739.6 M3 45.0 78,281
30.1.02 Granular Base Course 250mm thk 1,449.7 M3 55.0 79,731
30.1.03 Primer and Tack Coat 5,798.6 M2 2.0 11,597
30.1.04 HMA Asphalt 75mm 1,065.5 MT 180.0 191,789
30.1.05 Pavement Joint 460.0 M 10.0 4,600
30.1.06 New Curb & Gutter 458.2 M 160.0 73,319
30.1.07 New Concrete Sidewalk 781.6 M2 110.0 85,979
30.1.08 Pavement Marking 1.0 LS 5,000.0 5,000
30.1.09 Landcape (Sod/Seeding Restoration) 300.0 M2 10.0 3,000
30.1.10 Fence 869.0 M 120.0 104,276
30 SUB-TOTAL: Paving & Concrete Flat Work 637,572
40 Traffic Signalling & Lighting
40.1 Traffic Signalling & Lighting
40.1.02 Lighting 14.0 EA 4,000.00 56,000
40 SUB-TOTAL: Traffic Signalling & Lighting 56,000
DIRECT COST SUB- TOTAL : 862,420
50 INDIRECT COST
50.1 Indirect Cost
50.1.01 Mobilzation (4%) 1.0 LS 34,500.00 34,500
50.1.02 Traffic Management (3%) 1.0 LS 25,870.00 25,870
50.1.03 Risk & Contigency (8%) 1.0 LS 68,990.00 68,990
50.1.04 Detail Engingeering Cost (8%) 1.0 LS 68,990.00 68,990
50 SUB-TOTAL: INDIRECT COST 198,350
TOTAL - STATION AVE PARK & RIDE 1,060,770

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST
Page 144–145