Council Meeting/Documents/Conceptual Construction Cost Estimate - Luxton P&R
Appendix

Conceptual Construction Cost Estimate - Luxton P&R

January 15, 2019Pages 146–1472 sections

Construction cost estimate for the Luxton P&R facility.

1 CALL TO ORDER
Total Estimated Cost: $1,123,300Date: 23 July '18Includes $210,050 in indirect costs

PROJECT: ISLAND HWY TRANSIT PRIORITY PLAN CLIENT: BC TRANSIT DATE: 23 JULY '18 PACKAGE: Luxton P&R Rev. 0

TRADE ITEM DESCRIPTION QTY UNIT UNIT RATE TOTAL COST
10 Site Removal & Utility Work
10.1 Site Removal & Utility Work 10,595
10.1.01 Remove Concrete Barrier 135.0 M 35.0 4,725
10.1.02 Remove Existing Curb & Gutter 106.0 M 15.0 1,590
10.1.03 Saw Cut 60.0 M 8.0 480
10.1.04 Remove Gate 2.0 EA 500.0 1,000
10.1.05 Remove Signage 1.0 EA 800.0 800
10.1.06 Remove others 1.0 LS 2,000.0 2,000
10 SUB-TOTAL: Site Removal & Utility Work 10,595
20 Grading & Drainage Work
20.1 Grading & Drainage Work 183,290
20.1.01 Clearing 4,634.87 M2 3.00 13,905
20.1.01 Topsoil Stripping 4,634.87 M2 5.0 23,174
20.1.02 Soil Import Fill 2,317.4 M3 25.0 57,936
20.1.03 PVC 200mm Pipe 314.0 M 120.0 37,680
20.1.04 PVC 300mm Pipe 30.0 M 150.0 4,500
20.1.05 Catch Basin 14.0 EA 1,000.0 14,000
20.1.06 Oil/ water Separator 2.0 EA 20,000.0 40,000
20.1.07 Headwall/Rip Rap 1.0 EA 6,000.0 6,000
20 SUB-TOTAL: Grading & Drainage Work 183,290
30 Paving & Concrete Flat Work
30.1 Paving & Concrete Flat Work 469,461
30.1.01 Granular Subbase SGSB 300mm thk 1,555.0 M3 45.0 69,974
30.1.02 Granular Base Course 300mm/250mm thk 1,323.2 M3 55.0 72,778
30.1.03 Primer and Tack Coat 5,183.3 M2 2.0 10,367
30.1.04 HMA Asphalt 75mm/150mm 1,053.2 MT 180.0 189,574
30.1.05 Pavement Joint 60.0 M 10.0 600
30.1.06 New Curb & Gutter 258.7 M 160.0 41,396
30.1.07 New Concrete Sidewalk 235.0 M2 110.0 25,852
30.1.08 Pavement Marking 1.0 LS 6,000.0 6,000
30.1.09 Landcape (Sod/Seeding Restoration) 600.0 M2 10.0 6,000
30.1.10 Fence 391.0 M 120.0 46,920
30 SUB-TOTAL: Paving & Concrete Flat Work 469,461
40 Traffic Signalling & Lighting
40.1 Traffic Signalling & Lighting
40.1.01 Traffic Signals 1.0 EA 200,000.00 200,000
40.1.02 Lighting 9.0 EA 4,000.00 36,000
40 SUB-TOTAL: Traffic Signalling & Lighting 236,000
DIRECT COST SUB- TOTAL : 913,250
50 INDIRECT COST
50.1 Indirect Cost
50.1.01 Mobilzation (4%) 1.0 LS 36,530.00 36,530
50.1.02 Traffic Management (3%) 1.0 LS 27,400.00 27,400
50.1.03 Risk & Contigency (8%) 1.0 LS 73,060.00 73,060
50.1.04 Detail Engingeering Cost (8%) 1.0 LS 73,060.00 73,060
50 SUB-TOTAL: INDIRECT COST 210,050
TOTAL - LUXTON PARK & RIDE 1,123,300
Page 146–147

EXCLUSIONS :

  • Client's Project Administration
  • GST
  • PST
Page 146–147