CORE AREA TRUNK SEWERS - SCHEDULE 'A' TO BYLAW 2312
June 16, 2020Pages 191–1922 sections
Detailed engineering maps (Schedule 'A') showing the trunk sewer network and maximum allocated capacities for regional participants.
January 16, 2006Macaulay Point Service AreaMaximum allocated capacities for 2045
CORE AREA TRUNK SEWERS
SCHEDULE 'A' TO BYLAW 2312 AS AMENDED BY BYLAW 3319. - MACAULAY POINT SERVICE AREA AND MAXIMUM ALLOCATED CAPACITIES
Allocation Tables (Litres per Second - L/s)
ALDEANE (MEAFORD) WEIR
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Langford | 370 | 370 |
PARSONS MAG METER
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Langford | 370 | 370 |
| Colwood | 347 | 347 |
| Total (see note 4) | 651 | 651 |
CRAIGFLOWER PUMP STATION
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Langford | 210 | 370 |
| Colwood | 192 | 347 |
| View Royal | 173 | 274 |
| Songhees IR | 22 | 45 |
| Esquimalt IR | 13 | 17 |
| Esquimalt | 7 | 8 |
| Total (see note 4) | 522 | 894 |
- EXISTING PUMP STATION IS SCHEDULED TO BE REPLACED TO MEET CAPACITY.
MARIGOLD PUMP STATION
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 568 | 806 * |
- MARIGOLD TANK TO STORE FLOW IN EXCESS OF 568 L/s. BENEFIT TO DOWNSTREAM MUNICIPALITIES FROM FLOW STORAGE.
SHORELINE TRUNK SEWER
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| View Royal | 10 | 25 |
| Songhees IR | 22 | 45 |
| Esquimalt IR | 13 | 17 |
| Esquimalt | 7 | 8 |
| Total | **52 | 95** |
HARRIET FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 210 | 226 |
CITY BOUNDARY FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 350 | 365 |
CECELIA FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Victoria | 105 | 633 |
SELKIRK CONNECTION
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 1 | 1 |
| Victoria | 8 | 31 |
| Total | 9 | 32 |
HEREWARD / LANGFORD FLUMES
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Victoria | 60 | 271 |
WILSON FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 7 | 116 |
SEA TERRACE FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Victoria | 28 | 64 |
HEAD STREET FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 49 | 262 |
| DND | 21 | 21 |
| Total | 70 | 283 |
LANG COVE PUMP STATION
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 27 | 128 |
| DND | 46 | 76 |
| Total | 73 | 204 |
CONSTANCE / LYALL MAG METER
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 20 | 87 |
| DND | 53 | 102 |
| Total | 73 | 189 |
KINVER MAG METER
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 0 | 100 |
DEVONSHIRE FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 54 | 247 |
| Songhees IR | 1 | 1 |
| Total | 55 | 248 |
NORTHWEST TRUNK WESTERN AT MACAULAY
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Langford | - | 370 |
| Colwood | - | 347 |
| View Royal | 173 | 274 |
| Esquimalt | 109 | 323 |
| DND | 136 | 178 |
| Songhees IR | 22 | 45 |
| Esquimalt IR | 13 | 17 |
| Total | 453 | 1554 |
NORTHWEST TRUNK NORTHERN AT MACAULAY
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 1128 | 1397 * |
| Victoria | 442 | 1080 |
| Esquimalt | 194 | 644 |
| Songhees IR | 1 | 1 |
| DND | 37 | 37 |
| Total | 1802 | 2890 |
- SEE NOTE 6
MACAULAY POINT PUMP STATION & OUTFALL
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 1128 | 1397 * |
| Victoria | 442 | 1080 |
| Esquimalt | 427 | 967 |
| Langford | - | 370 |
| Colwood | - | 347 |
| View Royal | 173 | 274 |
| DND | 185 | 215 |
| Songhees IR | 23 | 46 |
| Esquimalt IR | 13 | 17 |
| Total (see note 4) | 1787 | 4452 * |
- SEE NOTE 6
NORTHWEST TRUNK NORTHERN AT LYALL
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Saanich | 1128 | 1397 * |
| Esquimalt | 111 | 626 |
| Esq. Credit for Lyall Diversion | 65 | |
| Victoria | 201 | 1080 |
| Victoria credit for Lyall Diversion | 241 | |
| Songhees IR | 1 | 1 |
| DND | 21 | 21 |
| Total | 1768 | 2856 |
- SEE NOTE 6
KINVER / ANSON FLUME
| Participant | Current Allocation (L/s) | 2045 Allocation (L/s) |
|---|---|---|
| Esquimalt | 18 | 18 |
| DND | 16 | 16 |
| Total | 34 | 34 |
NOTES:
- ALL FLOWS SHOWN ARE PEAK, IN LITRES PER SECOND (L/s).
- CURRENT FLOW ALLOCATIONS ARE BASED ON 1973 PRIESTMAN REPORT AND 1994 WESTERN COMMUNITIES TRUNK SEWER COST SHARING REPORT.
- 2045 FLOW ALLOCATIONS ARE BASED ON REGIONAL GROWTH STRATEGY AND 2004 INFLOW & INFILTRATION RATES. THESE ALLOCATIONS WILL BE AVAILABLE WHEN ALL LIQUID WASTE MANAGEMENT PLAN (LWMP - CHAPTER 16) UPGRADES ARE COMPLETED.
- TOTAL PEAK FLOWS MAY NOT ADD CUMULATIVELY DUE TO POPULATION-BASED HARMON PEAKING FACTOR.
- LOCATION AND EXTENT OF CRD SEWERS AND FACILITIES AS DEPICTED ARE PRELIMINARY AND MAY CHANGE IN ACCORDANCE WITH THE FINAL SYSTEM DESIGN. PROPOSED UPGRADES AS SHOWN ARE REQUIRED TO MEET 2045 FLOW ALLOCATIONS.
- SAANICH'S ALLOCATED FLOW AT MACAULAY REMAINS AT 1128 L/s AS EXCESS IS STORED IN MARIGOLD TANK.
DESIGN FLOW LEGEND
- INFLOW ALLOTMENT AT INDICATED LOCATION
- DESIGN CAPACITY ALLOTMENT AT INDICATED LOCATION
- EXIST. / PROP. (Legend for Sewer Lines and Facilities)
- TRUNK SEWER: [Solid Line / Dashed Line]
- BYPASS OUTFALL: [Line with arrows]
- PUMP STA.: [Solid square / Dashed square]
- PUMP STA. UPGRADE: [Solid square with star / Dashed square with star]
- PEAK FLOW STORAGE TANK: [Solid hexagon / Dashed hexagon]
LAST REVISED: JAN. 16, 2006 DWG. NO. 8-S184-1 SHT 1 OF 2
SCHEDULE 'A' TO BYLAW 2312 AS AMENDED BY BYLAW 3319. - CLOVER POINT SERVICE AREA AND MAXIMUM ALLOCATED CAPACITIES
Allocation Tables (2045 Allocation L/s)
NORTHEAST TRUNK BOWKER AT FINLAYSON
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 14 |
| Victoria | 152 |
| Total (see note 3) | 158 |
NORTHEAST TRUNK BOWKER UPSTREAM OF TRENT P.S.
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 396 |
| Victoria | 1461 |
| Total (see note 3) | 1824 |
TRENT PUMP STATION
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 365 |
| Victoria | 1155 |
| Total | 1520 |
- BENEFIT TO OAK BAY FROM FLOW DIVERSION
NORTHEAST TRUNK BOWKER DOWNSTREAM OF TRENT P.S.
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 37 |
| Victoria | 320 |
| Oak Bay | 237 |
| Total (see note 3) | 560 |
NORTHEAST TRUNK BOWKER UPSTREAM OF CURRIE ROAD
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 37 |
| Victoria | 320 |
| Oak Bay | 1155 |
| Total (see note 3) | 1450 |
Page 191–192
CURRIE ROAD PUMP STATION
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 552 |
| Victoria | 320 * |
| Oak Bay | 1109 |
| Total (see note 3) | 1509 ** |
- *CURRIE ROAD P.S. IS ONLY REQUIRED TO CONVEY SAANICH'S 5 YEAR FLOW FROM EDI, & OAK BAY'S 5 YEAR FLOW FROM NETB AND ECI (ALL FLOW IN EXCESS OF 1509 L/s CAN BE DIVERTED OUT MCMICKING BYPASS OUTFALL.
EAST COAST INTERCEPTOR UPSTREAM OF CURRIE ROAD
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 552 * |
| Oak Bay | 318 |
| Total (see note 3) | 856 |
- *ARBUTUS TANK IS UTILIZED DURING STORM EVENTS TO THROTTLE SAANICH'S FLOW TO 552 L/s.
CLOVER POINT PUMP STATION & OUTFALL
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 552 * |
| Victoria | 2420 |
| Oak Bay | 1223 |
| Total (see note 3) | 4100 ** |
- *ARBUTUS TANK IS UTILIZED DURING STORM EVENTS TO THROTTLE SAANICH'S FLOW TO 552 L/s MAX.
- **CLOVER POINT P.S. IS ONLY REQUIRED TO CONVEY AND DISCHARGE 5 YEAR FLOWS (ALL FLOW IN EXCESS OF 4100 L/s CAN BE DIVERTED OUT THE EMERGENCY BYPASS OUTFALL.
HARLING POINT PUMP STATION
| Participant | 2045 Allocation (L/s) |
|---|---|
| Oak Bay | 61.5 |
CITY TRUNK (BUSHBY)
| Participant | 2045 Allocation (L/s) |
|---|---|
| Victoria | 2372 |
ARBUTUS FLUME
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 1040 * |
- *ARBUTUS TANK STORES FLOW IN EXCESS OF 1040 L/s.
UNIVERSITY OF VICTORIA
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich * | 134 |
- *SAANICH HAS SEWER USE AGREEMENT WITH UVIC.
PENRHYN PUMP STATION
| Participant | 2045 Allocation (L/s) |
|---|---|
| Saanich | 552 * |
- *ARBUTUS TANK IS ACTIVATED DURING STORM EVENTS TO THROTTLE SAANICH'S FLOW TO 552 L/s MAX.
HUMBER & RUTLAND PUMP STATIONS
| Participant | 2045 Allocation (L/s) |
|---|---|
| Oak Bay | 25 * |
- *WHEN COMBINED SEWERS ARE SEPARATED. (SEE NOTE 5)
PROPOSED ARBUTUS PEAK FLOW STORAGE TANK 17,900 m³
- ARBUTUS TANK WILL STORE ALL FLOW IN EXCESS OF 1040 L/s FROM ARBUTUS OR 134 L/s FROM UVIC.
- *BENEFIT TO OAK BAY & VICTORIA FROM FLOW STORAGE.
NOTES:
- ALL FLOWS SHOWN ARE PEAK, IN LITRES PER SECOND (L/s).
- 2045 FLOW ALLOCATIONS ARE BASED ON REGIONAL GROWTH STRATEGY AND INCLUDE INFLOW & INFILTRATION RATES FOR A 5 YEAR OR 100 YEAR STORM EVENT WHERE APPLICABLE MODELED IN 2004. THESE ALLOCATIONS WILL BE AVAILABLE WHEN ALL LIQUID WASTE MANAGEMENT PLAN (LWMP CH. 16) UPGRADES ARE COMPLETED.
- TOTAL PEAK FLOWS MAY NOT ADD CUMULATIVELY DUE TO POPULATION-BASED HARMON PEAKING FACTOR.
- LOCATION AND EXTENT OF CRD SEWERS AND FACILITIES AS DEPICTED ARE PRELIMINARY AND MAY CHANGE IN ACCORDANCE WITH THE FINAL SYSTEM DESIGN. PROPOSED UPGRADES AS SHOWN ARE REQUIRED TO MEET 2045 FLOW ALLOCATIONS.
- BYPASS OUTFALLS WILL ONLY BE ACTIVATED DURING A STORM EVENT THAT EXCEEDS A 5 YEAR RETURN PERIOD.
DESIGN FLOW LEGEND
- INFLOW ALLOTMENT AT INDICATED LOCATION
- DESIGN CAPACITY ALLOTMENT AT INDICATED LOCATION
- EXIST. / PROP. (Legend for Sewer Lines and Facilities)
- TRUNK SEWER: [Solid Line / Dashed Line]
- BYPASS OUTFALL: [Line with arrows]
- PUMP STA.: [Solid square / Dashed square]
- PUMP STA. UPGRADE: [Solid square with star / Dashed square with star]
- PEAK FLOW STORAGE TANK: [Solid hexagon / Dashed hexagon]
LAST REVISED: JAN. 16, 2006 DWG. NO. 8-S184-2 SHT 2 OF 2
Page 191–192