APPENDIX D - Long Term Capital Plan Budgetary Figures

June 16, 2020Page 1951 section

Financial projections for the CRD liquid waste management long-term capital plan from 2020 through 2050.

1 CALL TO ORDER
$116,405,000 total cumulative cost (2020-2050)Pump Stations: $19,335,000Trunk Sewers: $26,150,000

APPENDIX D

Long Term Capital Plan

Budgetary Figures

PRIMARY LEVEL WITHIN 5 years (by 2025) WITHIN 10 years (by 2030) WITHIN 20 years (by 2040) WITHIN 30 years (by 2050) CUMULATIVE Total (2020-2050)
AIR & DRAIN VALVES $0 $115,000 $0 $0 $115,000
ATTENUATION TANKS $0 $690,000 $1,400,000 $1,700,000 $3,790,000
FLOW METERING $940,000 $500,000 $600,000 $600,000 $2,640,000
GENERAL ENGINEERING, PLANNING, POLICY $5,725,000 $2,000,000 $4,000,000 $11,725,000
MANHOLES $2,500,000 $3,140,000 $0 $0 $5,640,000
MCLOUGHLIN $0 $0 $0 $0
ODOUR and CORROSION PROTECTION $2,200,000 $1,800,000 $0 $0 $4,000,000
OUTFALLS $1,250,000 $2,750,000 $10,000,000 $0 $14,000,000
PRESSURE PIPE (Forcemains/Siphons) $17,900,000 $9,230,000 $0 $0 $27,130,000
PUMP STATIONS $8,085,000 $2,378,000 $2,800,000 $6,072,000 $19,335,000
RESIDUAL SOLIDS AND CENTRATE RETURN SYSTEM $0 $80,000 $600,000 $1,200,000 $1,880,000
TRUNK SEWERS $14,630,000 $7,420,000 $4,100,000 $0 $26,150,000
TOTAL $53,230,000 $30,103,000 $23,500,000 $9,572,000 $116,405,000