Status update on playground equipment delivery delayed by a factory fire at the supplier's facility.

8.1d Centennial Park Playground Replacement Equipment
Delay of 6 to 8 weeks expectedNo impact to budgetsJuly 12, 2018

TOWN OF VIEW ROYAL COUNCIL REPORT

TO: Council DATE: July 12, 2018
FROM: J. Rosenberg, Director of Engineering MEETING DATE: July 17, 2018

CENTENNIAL PARK PLAYGROUND REPLACEMENT EQUIPMENT

RECOMMENDATION:

THAT Council receives the report for information.

CHIEF ADMINISTRATIVE OFFICER’S COMMENTS:

I concur with the recommendation.

PURPOSE OF REPORT:

To provide Council with an update on the project scheduling.

BACKGROUND:

The initial installation date for the Equipment was scheduled for completion in August of 2018.

PROJECT INFORMATION:

Staff received news from the supplier that their factory had received extensive fire damage, 62 orders that were scheduled to be shipped the week of July 4 were damaged in the fire. The resupply is a 6 to 8 week period. Depending on our order queue, we could wait an additional several weeks until production of the Town’s order starts. Staff are awaiting confirmation of our expected production date as well as the new delivery date.

BUDGET IMPLICATIONS:

There will be no impact to budgets because of the fire.

RECOMMENDATION:

THAT Council receives the report for information.

SUBMITTED BY:

J. Rosenberg, Director of Engineering

REVIEWED BY:

K. Anema, Chief Administrative Officer

Page 60–61

Document Images

(3)
Document image
Document image
Document image
Extracted from: 2018 07 17 Council Agenda - Agenda - Pdf