Schedule C – 2023 Capital Projects

January 9, 2024Page 1022 sections

Detailed status and budget list for 2023 capital improvements including infrastructure, transportation, and parks.

6.3.3 c) Budget Variance and Projects Update Report to December 31, 2023
Total Capital Project Budget: $6,663,270Six Mile Rd Roundabout budget: $2,385,000Packers pump station upgrade budget: $670,000

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to December 31, 2023 Meeting Date: January 9, 2023

Page 102

Schedule C – 2023 Capital Projects

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Administration
Records information management system 1038 Dec 2023 $ 168,000 $ 1,050 $ 166,950 99% budget remaining
Building Improvements
Council Chambers modifications 1138 Jan 2023 34,200 38,353 (4,153) 12% over budget
Ergonomic workstation replacement 1226 Dec 2023 145,000 - 145,000 100% budget remaining
Town Hall HVAC replacements 1272 Aug 2023 110,000 97,743 12,257 11% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Dec 2023 96,700 80,846 15,854 16% budget remaining
IT workstation ever-greening 1070 Dec 2023 42,500 28,241 14,259 34% budget remaining
Phone service replacement 1037 Nov 2023 35,000 40,500 (5,500) 16% over budget
Protective Services
Emerg Prog Equipment
Emergency Operations Centre equipment 0850 Apr 2023 5,000 4,776 224 4% budget remaining
Fire - Buildings
Fire training ground improvements 1149 Dec 2023 50,000 48,321 1,679 3% budget remaining
Public Safety Building envelope repairs 1032 Oct 2023 100,000 - 100,000 100% budget remaining
Public Safety Building landscaping 1208 Jul 2023 35,000 - 35,000 100% budget remaining
Public Safety Building security gate 1264 Sep 2023 25,000 27,831 (2,831) 11% over budget
Fire - Furniture and Equipment
Firefighting hose replacement 1150 Apr 2024 25,000 - 25,000 100% budget remaining
SCBA cylinder and battery replacements 1101 Jun 2023 35,000 26,232 8,768 25% budget remaining
Police Services
RCMP building capital projects 1152 Dec 2023 20,000 5,363 14,637 73% budget remaining
RCMP building design validation 1266 Dec 2023 186,720 - 186,720 100% budget remaining
Transportation Services
Bus Shelters
Bus shelter installation program 0058 Dec 2023 45,000 12,895 32,105 71% budget remaining
Other Transportation Projects
Intersection safety improvements at trail crossings 1265 Dec 2023 20,000 14,600 5,400 27% budget remaining
Road Projects
Intersection improvements-Helmcken Rd at Watkiss Way 1085 Dec 2023 60,000 4,023 55,977 93% budget remaining
Island Hwy upgrades-Helmcken Rd to Beaumont Ave 1111 Dec 2023 100,000 - 100,000 100% budget remaining
Six Mile Rd hydro works 1260 Dec 2023 300,000 88,460 211,540 71% budget remaining
Six Mile Rd roundabout 1252 May 2024 2,385,000 378,377 2,006,623 84% budget remaining
Six Mile Road cross-section review 1168 Dec 2023 5,000 - 5,000 100% budget remaining
Sidewalks
Atkins Road sidewalk-Anya Court to Langford border 1234 Dec 2023 30,000 10,996 19,004 63% budget remaining
Curb & sidewalk replacement-Eagle Creek Village to Helmcken/Burnside 1189 Dec 2023 100,000 5,957 94,043 94% budget remaining
Jedburgh Rd sidewalk 1204 Dec 2023 28,000 4,067 23,933 85% budget remaining
Signals
Traffic signal upgrades-collector road intersections 1270 Dec 2023 16,700 - 16,700 100% budget remaining
Traffic signal upgrades-Island Hwy 1261 Dec 2023 68,000 46,600 21,400 31% budget remaining
Street Lighting
LED lighting upgrade 1194 Dec 2023 30,000 29,935 65 0% budget remaining
Pedestrian lighting improvements 1236 Dec 2023 22,700 - 22,700 100% budget remaining
St. Giles Street lighting improvements 1269 Dec 2023 20,000 - 20,000 100% budget remaining
Environmental Services
Lift Stations
Helmcken Bay pump station upgrade 1211 Apr 2023 301,500 301,497 3 0% budget remaining
Packers pump station upgrade 1163 Dec 2023 670,000 7,277 662,723 99% budget remaining
Parks Services
Park Development
View Royal Park-design 1028 Dec 2023 13,875 13,823 52 0% budget remaining
View Royal Park-fencing & garbage receptacles 1268 Dec 2023 78,700 - 78,700 100% budget remaining
View Royal Park-saltwater marsh/wetland 1267 Dec 2023 272,625 - 272,625 100% budget remaining
View Royal Park-soft landscaping 1258 Dec 2023 232,800 58,379 174,421 75% budget remaining
Watkiss Way Community Park development 1241 Dec 2023 15,000 - 15,000 100% budget remaining
Park Improvements
Centennial Park diamond #4 fencing improvement 1218 Dec 2023 40,250 - 40,250 100% budget remaining
Chancellor Park playground replacement 1254 Dec 2023 300,000 - 300,000 100% budget remaining
Knollwood Park playground replacement 1199 Dec 2023 100,000 21,977 78,023 78% budget remaining
Stillwater Road waterfront access 1245 Dec 2023 40,000 2,460 37,540 94% budget remaining
Thomas Road waterfront access 1244 Dec 2023 40,000 2,096 37,904 95% budget remaining
Park Vehicles
1996 Kubota replacement 1067 Apr 2023 33,000 32,779 221 1% budget remaining
2006 Ford F350 replacement 1253 May 2023 62,000 61,330 670 1% budget remaining
2007 Chev 1-ton pickup replacement 1271 Dec 2023 85,000 69,769 15,231 18% budget remaining
Riding mower replacement 1250 Apr 2023 25,000 24,028 972 4% budget remaining
Small trailer with cargo rack 1221 Dec 2023 10,000 10,041 (41) 0% over budget
Grand Total $6,663,270 $1,600,622 $5,062,648 76% budget remaining