RapidBus Westshore Line Infrastructure Update Presentation
BC Transit presentation regarding the implementation of the Westshore RapidBus line (Route 95) and associated infrastructure improvements.
RapidBus Westshore Line Infrastructure Update
April 2023




Presentation Overview
Objectives:
- Provide an update on Implementation and Planning Activities to advance the RapidBus Implementation Strategy
Overview:
- Regional Context
- RapidBus
- Transit Service Planning
- Transit Infrastructure Planning
- RapidBus
- Transit Priority
- Next Steps

Regional Context

2028 Projections Summary:
- West Shore: 103,918 Population (up 22%), 27,837 Employment (up 22%)
- Peninsula: 46,394 Population (up 7%), 25,369 Employment (up 9%)
- Core: 288,301 Population (up 7%), 183,617 Employment (up 9%)

Transit Future Plan
BC Transit developed a 25-year transit plan for the region.
The Plan uses four layers of transit service:
- Rapid Transit
- Frequent Transit
- Local Transit
- Targeted Services
Identified strategic changes to the transit network and supporting infrastructure.

What is RapidBus?
CONNECTED, FREQUENT, FAST AND RELIABLE
- RapidBus is a bus delivered rapid transit service designed to connect and support designated urban centres of high density, mixed-use areas of the region.
- Features include branded services, corridor treatments, unique stations, limited stops and high frequencies.


RapidBus Implementation Strategy
The RapidBus Implementation Strategy identifies three top priority RapidBus lines separated into two phases:
- West Shore RapidBus Line (Phase 1)
- McKenzie RapidBus Line (Phase 2)
- Peninsula RapidBus Line (Phase 2)
Phase 3 identifies other RapidBus candidates including Hillside, Quadra and Esquimalt.

West Shore RapidBus Line Launch
The flagship Blink West Shore RapidBus Line was launched on April 10th.
- Introduced the new Route 95 Langford/ Downtown
- Route 95 replaced Route 50, operating along the same route, but with added service and fewer bus stops
- 7-8 minute frequency at peak periods on weekdays
- Minimum of 15 minute service from 7am-10pm Monday to Saturday and 8am-10pm Sunday
- New Blink RapidBus branding at RapidBus stations

Timeline Milestones:
- Douglas Street Bus Lanes Installed: COMPLETED 2015
- Douglas Street Bus Lanes Extended: COMPLETED 2018
- Douglas Street Bus Lane Extended to McKenzie Interchange: COMPLETED 2020
- First Blink RapidBus Line Launched: COMPLETED 2023
- Transit Priority and Rapidbus Station Infrastructure
- Victoria/Swartz Bay and Uptown/UVic RapidBus Lines
95 Langford / 95 Downtown Route Map

PROPOSED STATION SIGNAGE


RapidBus Station Branding
STATION SIGNAGE



Infrastructure Development Process
| Process Stage | Key Activities | Estimated Timeline |
|---|---|---|
| Transit Future Vision RapidBus Strategy | • Future Transit Network Vision • Prioritization |
- |
| Study – Conceptual Options | • Study budgeting & agreement • Develop and evaluate conceptual options |
12 months |
| Approval of Conceptual Options | • Local Government Approval in principle of street design concepts • Transit Commission Approval in principle of concept and local share of funding |
6 - 18 months |
| Business Case Development and Approval | • BC Transit/Province Funding • Federal Funding |
6 - 9 months |
| Project Delivery | • Detail Design • Construction Tendering • Construction |
18 - 24 months |
- Major infrastructure improvements typically take 3-7 years to plan and implement.
- Coordinated project planning with local governments and the Province to advance design concepts, cost estimates, cost sharing.
- Capital Programming, preparation of business cases and applications for funding.
- Project approvals by Local Government, Victoria Regional Transit Commission and BC Transit Board.
RapidBus Infrastructure Projects – Island Highway
Island Highway Priority Project
- Supports the Westshore Rapid Bus Strategy.
- Transit priority improvements for Island Highway between Highway 1 in the Town of View Royal and Wale Road in the City of Colwood.
- ICIP application for $14.9M budget and the local share is funded by the VRTC.
- If the application is successful next step would be project construction tendering.
- Construction 2024 and in-service in 2025.


Island Hwy Transit Priority : View Royal
- Westbound: partial dedicated bus lanes (510m) from Colwood Interchange to 6 Mile intersection and queue jump at 6 Mile intersection.
- Eastbound: partial dedicated bus lane (375m) from Dukrill to Colwood Interchange and queue jump to on-ramp.
- Transit Signal Priority at 6 Mile Intersection and Colwood Interchange.
- New 1.8m bike lanes in both directions.
- Signalized intersection at Atkins Road to support safe connections to RapidBus Stops and Business Access.

Island Hwy Transit Priority Project: Colwood
Goldstream Intersection

Wale/Ocean Blvd Intersection

Westshore RapidBus Station Study
- Developed preliminary designs and cost estimates for 22 RapidBus Stations along the Westshore Line.
- Concepts includes shelters, sidewalk improvements, bus bays, ancillary improvements
- Substantially completed technical study in February 2023 for Langford, Colwood, View Royal, North Douglas.
- Developed conceptual drawings for each location
- Provided cost estimates for delivery
- Several desired locations are under long term contract with 3rd party advertisers.
- There are 6 Station Plans being developed for View Royal – Helmcken, Atkins & Wilfret.

RapidBus Planning City of Victoria
Attended Council in September 2022 to discuss moving forward.
- Council endorsed the concept of 24/7 bus lanes in Downtown on Douglas Street
- In the process of establishing a Downtown Douglas Street Vision
Developing a multi-modal corridor vision to allow for preliminary designs and cost estimates for RapidBus Stations and Bus Priority in Downtown Victoria.
Report to Victoria Council in late spring on a preferred option and recommended actions. Study schedule to be complete in July.


Infrastructure Development – Next Steps

- Island Hwy Transit Priority Project
- Funding Application
- Construction
- Rapid Bus Stations
- Secure local government support
- Secure VRTC support for funding
- Business Case and Grant Application
Successes
Thank you
Contact:
Lindsay Byers – Senior Manager, Government Relations (Victoria) lbyers@bctransit.com
James Wadsworth – Manager, Project Development jwadsorth@bctransit.com
Levi Megenbir – Senior Transit Planner Work Lead lmegenbir@bctransit.com

Document Images
(16)

Example of a "Blink" branded shelter poster

Detailed view of a bus stop "Flag Sign" for station 100076 showing Route 95 Blink Langford and other local routes

Scale rendering of the bus stop pole signage next to a human silhouette

Photo of a double-decker bus stopped at a transit station with yellow tactile warning strips

People waiting at a bus stop along a busy multi-lane road

Infrastructure plan map for the Island Highway corridor highlighting areas for signal priority, bus queue jumps, and curb bus lanes

Detailed engineering site plan for transit improvements on the Island Highway near 6 Mile Rd and Atkins Rd