Committee of the Whole/Documents/ACTIVE TRANSPORTATION NETWORK PLAN PRESENTATION STAFF REPORT
Staff Report

ACTIVE TRANSPORTATION NETWORK PLAN PRESENTATION STAFF REPORT

April 11, 2023Pages 250–2511 section

A staff report introducing the draft Active Transportation Network Plan and outlining the timeline for provincial funding requirements.

3 MINUTES OF PREVIOUS MEETINGS, ADOPTION OF
Date: April 5, 2023Provincial funding requirement: Final plan must be completed and adopted by Council by May 31, 2023.Consultant: WATT Consulting Group.

TOWN OF VIEW ROYAL PUBLIC WORKS & TRANSPORTATION REPORT

TO: Committee of the Whole DATE: April 5, 2023 FROM: Ivan Leung, P.Eng, Director of Engineering & Parks MEETING DATE: April 11, 2023

ACTIVE TRANSPORTATION NETWORK PLAN PRESENTATION

RECOMMENDATION:

THAT the Active Transportation Network Plan Presentation by WATT Consulting be received for information.

PURPOSE:

The purpose of this report is to inform Council of the next steps to complete the project, following WATT Consulting’s presentation regarding the Draft Active Transportation Network Plan.

TIME CRITICAL:

The project has upcoming deadlines to meet grant requirements (May 31, 2023). This was extended from the previous deadline (March 31, 2023).

EXECUTIVE SUMMARY:

In order to meet the Provincial funding requirements for this project, the Final Active Transportation Network Plan must be completed and adopted by Council by May 31, 2023.

Following the presentation, the Committee will have the opportunity to provide comment to WATT Consulting and Town staff. Staff would then bring forward a report to Council at the April 19th, 2023 regular Council meeting for the adoption of the Active Transportation Network Plan. The reason for the additional meeting is so that staff and WATT Consulting can meaningfully address the comments that Council has previously provided to the Town.

Funding will be provided in hand to the Town once the Active Transportation Network Plan is finalized. Staff would then subsequently bring forward recommended capital projects to Council during budget deliberations.

CONCURRENCE:

CONCURRENCE: Initials Comments
Chief Administrative Officer KA Recommend Approval

REVIEWED BY:

REVIEWED BY: Initials
Director of Corporate Administration N/A
Director of Finance N/A
Director of Development Services N/A
Director of Engineering and Parks IL
Director of Protective Services N/A

ATTACHMENTS:

Active Transportation Network Plan Presentation

Page 250–251

Document Images

(1)
Document image
Extracted from: 2023 04 11 Committee of the Whole Agenda - Agenda - Pdf