A tracking sheet for non-core projects including administration, information technology, and fire services projects.

Grand Total Project Budget: $681,913Grand Total Project Actual: $59,573

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to May 31, 2023 Meeting Date: June 13, 2023

Page 69

Schedule B – 2023 Non-core Projects

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Admin Buildings
Energy audit - Town Hall 510-04 Dec 2023 $ 8,310 $ 3,063 $ 5,248 63% budget remaining
Administration
Accessible BC Act implementation 140-15 Dec 2023 5,100 - 5,100 100% budget remaining
Truth and Reconciliation awareness 140-11 Dec 2023 10,000 - 10,000 100% budget remaining
Finance
Strategic Asset Management Plan 150-03 Dec 2023 20,000 - 20,000 100% budget remaining
Sustainable Infrastructure Replacement Plan 150-02 Dec 2023 20,300 - 20,300 100% budget remaining
Information Technology
Cyber security policies and process 160-11 Nov 2023 10,000 - 10,000 100% budget remaining
Information security strategic plan 160-10 Oct 2023 8,500 - 8,500 100% budget remaining
Information Technology Coordinator 160-14 Jul 2023 46,725 - 46,725 100% budget remaining
IT asset inventory solution 160-09 Dec 2023 8,500 - 8,500 100% budget remaining
IT disaster recovery plan 160-06 Jan 2023 10,000 2,846 7,154 72% budget remaining
Multi-factor authentication 160-08 Dec 2023 10,000 3,242 6,758 68% budget remaining
Public Relations
Volunteer community improvement program 120-05 Dec 2023 2,500 - 2,500 100% budget remaining
Protective Services
Emergency Program
EOC training and education 230-02 May 2023 5,500 - 5,500 100% budget remaining
Extreme heat risk reduction study 230-06 Oct 2023 30,000 - 30,000 100% budget remaining
Fire Building
Energy audit - Public Safety Building 510-29 Dec 2023 5,550 2,063 3,488 63% budget remaining
Fire General
Community wildfire protection plan update 210-03 Dec 2023 33,000 - 33,000 100% budget remaining
Wildfire fuel management 210-04 Dec 2023 25,000 - 25,000 100% budget remaining
Fire Volunteers
Volunteer firefighter qualifications compensation 211-03 Dec 2023 24,000 - 24,000 100% budget remaining
Transportation Services
Traffic Calming
Stormont Road traffic calming 323-01 Dec 2023 8,000 - 8,000 100% budget remaining
Transportation-General
Active Transportation Network Plan 310-08 May 2023 57,428 48,360 9,069 16% budget remaining
Development Services
Planning and Development Services
Coastal Adaptation Plan 510-28 Dec 2023 60,000 - 60,000 100% budget remaining
Community engagement strategy 510-22 Dec 2023 80,000 - 80,000 100% budget remaining
Official Community Plan review 510-02 Dec 2023 41,000 - 41,000 100% budget remaining
Off-street parking review 510-32 Dec 2023 35,000 - 35,000 100% budget remaining
Parks Services
Parks, Rec & Culture-General
Public art acquisition-mural 710-01 Dec 2023 35,000 - 35,000 100% budget remaining
Urban forestry strategy 310-14 Dec 2023 82,500 - 82,500 100% budget remaining
Grand Total $681,913 $59,573 $622,340 91% budget remaining