Schedule C – 2023 Capital Projects

June 13, 2023Pages 70–712 sections

A tracking sheet for capital infrastructure and equipment projects, including road works, signals, and park developments.

Six Mile Rd roundabout budget: $2,385,000Grand Total Project Budget: $6,460,370Grand Total Project Actual: $429,203

Report to Committee of the Whole Re: Budget Variance and Projects Update Report to May 31, 2023 Meeting Date: June 13, 2023

Page 70–71

Schedule C – 2023 Capital Projects

Project Description CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Administration
Records information management system 1038 Dec 2023 $ 168,000 $ 975 $ 167,025 99% budget remaining
Building Improvements
Council Chambers modifications 1138 Jan 2023 34,200 38,353 (4,153) 12% over budget
Ergonomic workstation replacement 1226 Dec 2023 145,000 - 145,000 100% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Oct 2023 46,700 - 46,700 100% budget remaining
IT workstation ever-greening 1070 Oct 2023 42,500 - 42,500 100% budget remaining
Phone service replacement 1037 Oct 2023 35,000 - 35,000 100% budget remaining
Protective Services
Emerg Prog Equipment
Emergency Operations Centre equipment 0850 Apr 2023 5,000 4,776 224 4% budget remaining
Fire - Buildings
Fire training ground improvements 1149 Dec 2023 50,000 - 50,000 100% budget remaining
Public Safety Building envelope repairs 1032 Oct 2023 100,000 - 100,000 100% budget remaining
Public Safety Building landscaping 1208 Jul 2023 35,000 - 35,000 100% budget remaining
Public Safety Building security gate 1264 Aug 2023 25,000 - 25,000 100% budget remaining
Fire - Furniture and Equipment
Firefighting hose replacement 1150 Jun 2023 25,000 - 25,000 100% budget remaining
SCBA cylinder and battery replacements 1101 Jul 2023 35,000 - 35,000 100% budget remaining
Police Services
RCMP building capital projects 1152 Dec 2023 20,000 1,444 18,556 93% budget remaining
RCMP building design validation 1266 Dec 2023 186,720 - 186,720 100% budget remaining
Transportation Services
Bus Shelters
Bus shelter installation program 0058 Dec 2023 45,000 - 45,000 100% budget remaining
Other Transportation Projects
Intersection safety improvements at trail crossings 1265 Dec 2023 20,000 - 20,000 100% budget remaining
Road Projects
Intersection improvements-Helmcken Rd at Watkiss Way 1085 Dec 2023 60,000 - 60,000 100% budget remaining
Island Hwy upgrades-Helmcken Rd to Beaumont Ave 1111 Dec 2023 100,000 - 100,000 100% budget remaining
Six Mile Rd hydro works 1260 Dec 2023 300,000 1,000 299,000 100% budget remaining
Six Mile Rd roundabout 1252 Dec 2023 2,385,000 7,871 2,377,129 100% budget remaining
Six Mile Road cross-section review 1168 Dec 2023 5,000 5,273 (273) 5% over budget
Sidewalks
Atkins Road sidewalk-Anya Court to Langford border 1234 Dec 2023 30,000 - 30,000 100% budget remaining
Curb & sidewalk replacement-Eagle Creek Village to Helmcken/Burnside 1189 Dec 2023 100,000 - 100,000 100% budget remaining
Jedburgh Rd sidewalk 1204 Dec 2023 28,000 - 28,000 100% budget remaining
Signals
Traffic signal upgrades-collector road intersections 1270 Dec 2023 16,700 - 16,700 100% budget remaining
Traffic signal upgrades-Island Hwy 1261 Dec 2023 68,000 - 68,000 100% budget remaining
Street Lighting
LED lighting upgrade 1194 Dec 2023 30,000 - 30,000 100% budget remaining
Pedestrian lighting improvements 1236 Dec 2023 22,700 - 22,700 100% budget remaining
St. Giles Street lighting improvements 1269 Dec 2023 20,000 - 20,000 100% budget remaining
Environmental Services
Lift Stations
Helmcken Bay pump station upgrade 1211 Apr 2023 272,000 301,497 (29,497) 11% over budget
Packers pump station upgrade 1163 Dec 2023 670,000 888 669,112 100% budget remaining
Parks Services
Park Development
View Royal Park-design 1028 Dec 2023 13,875 9,207 4,669 34% budget remaining
View Royal Park-fencing & garbage receptacles 1268 Dec 2023 78,700 - 78,700 100% budget remaining
View Royal Park-saltwater marsh/wetland 1267 Dec 2023 272,625 - 272,625 100% budget remaining
View Royal Park-soft landscaping 1258 Dec 2023 232,800 - 232,800 100% budget remaining
Watkiss Way Community Park development 1241 Dec 2023 15,000 - 15,000 100% budget remaining
Park Improvements
Centennial Park diamond #4 fencing improvement 1218 Dec 2023 40,250 - 40,250 100% budget remaining
Chancellor Park playground replacement 1254 Dec 2023 300,000 - 300,000 100% budget remaining
Knollwood Park playground replacement 1199 Dec 2023 100,000 - 100,000 100% budget remaining
Stillwater Road waterfront access 1245 Dec 2023 40,000 - 40,000 100% budget remaining
Thomas Road waterfront access 1244 Dec 2023 40,000 1,113 38,887 97% budget remaining
Park Vehicles
1996 Kubota replacement 1067 Apr 2023 81,600 32,779 48,821 60% budget remaining
2007 Chev 1-ton pickup replacement 1271 Dec 2023 85,000 - 85,000 100% budget remaining
Riding mower replacement 1250 Apr 2023 25,000 24,028 972 4% budget remaining
Small trailer with cargo rack 1221 Dec 2023 10,000 - 10,000 100% budget remaining
Grand Total $ 6,460,370 $ 429,203 $ 6,031,167 93% budget remaining