Appendix
Schedule C – 2023 Capital Projects
June 13, 2023Pages 70–712 sections
A tracking sheet for capital infrastructure and equipment projects, including road works, signals, and park developments.
Six Mile Rd roundabout budget: $2,385,000Grand Total Project Budget: $6,460,370Grand Total Project Actual: $429,203
Report to Committee of the Whole Re: Budget Variance and Projects Update Report to May 31, 2023 Meeting Date: June 13, 2023
Page 70–71
Schedule C – 2023 Capital Projects
| Project Description | CC Code | Est. Completion | Project budget | Project actual | Project variance | Variance % |
|---|---|---|---|---|---|---|
| General Government Services | ||||||
| Administration | ||||||
| Records information management system | 1038 | Dec 2023 | $ 168,000 | $ 975 | $ 167,025 | 99% budget remaining |
| Building Improvements | ||||||
| Council Chambers modifications | 1138 | Jan 2023 | 34,200 | 38,353 | (4,153) | 12% over budget |
| Ergonomic workstation replacement | 1226 | Dec 2023 | 145,000 | - | 145,000 | 100% budget remaining |
| Information Technology | ||||||
| IT infrastructure hardware replacements | 1044 | Oct 2023 | 46,700 | - | 46,700 | 100% budget remaining |
| IT workstation ever-greening | 1070 | Oct 2023 | 42,500 | - | 42,500 | 100% budget remaining |
| Phone service replacement | 1037 | Oct 2023 | 35,000 | - | 35,000 | 100% budget remaining |
| Protective Services | ||||||
| Emerg Prog Equipment | ||||||
| Emergency Operations Centre equipment | 0850 | Apr 2023 | 5,000 | 4,776 | 224 | 4% budget remaining |
| Fire - Buildings | ||||||
| Fire training ground improvements | 1149 | Dec 2023 | 50,000 | - | 50,000 | 100% budget remaining |
| Public Safety Building envelope repairs | 1032 | Oct 2023 | 100,000 | - | 100,000 | 100% budget remaining |
| Public Safety Building landscaping | 1208 | Jul 2023 | 35,000 | - | 35,000 | 100% budget remaining |
| Public Safety Building security gate | 1264 | Aug 2023 | 25,000 | - | 25,000 | 100% budget remaining |
| Fire - Furniture and Equipment | ||||||
| Firefighting hose replacement | 1150 | Jun 2023 | 25,000 | - | 25,000 | 100% budget remaining |
| SCBA cylinder and battery replacements | 1101 | Jul 2023 | 35,000 | - | 35,000 | 100% budget remaining |
| Police Services | ||||||
| RCMP building capital projects | 1152 | Dec 2023 | 20,000 | 1,444 | 18,556 | 93% budget remaining |
| RCMP building design validation | 1266 | Dec 2023 | 186,720 | - | 186,720 | 100% budget remaining |
| Transportation Services | ||||||
| Bus Shelters | ||||||
| Bus shelter installation program | 0058 | Dec 2023 | 45,000 | - | 45,000 | 100% budget remaining |
| Other Transportation Projects | ||||||
| Intersection safety improvements at trail crossings | 1265 | Dec 2023 | 20,000 | - | 20,000 | 100% budget remaining |
| Road Projects | ||||||
| Intersection improvements-Helmcken Rd at Watkiss Way | 1085 | Dec 2023 | 60,000 | - | 60,000 | 100% budget remaining |
| Island Hwy upgrades-Helmcken Rd to Beaumont Ave | 1111 | Dec 2023 | 100,000 | - | 100,000 | 100% budget remaining |
| Six Mile Rd hydro works | 1260 | Dec 2023 | 300,000 | 1,000 | 299,000 | 100% budget remaining |
| Six Mile Rd roundabout | 1252 | Dec 2023 | 2,385,000 | 7,871 | 2,377,129 | 100% budget remaining |
| Six Mile Road cross-section review | 1168 | Dec 2023 | 5,000 | 5,273 | (273) | 5% over budget |
| Sidewalks | ||||||
| Atkins Road sidewalk-Anya Court to Langford border | 1234 | Dec 2023 | 30,000 | - | 30,000 | 100% budget remaining |
| Curb & sidewalk replacement-Eagle Creek Village to Helmcken/Burnside | 1189 | Dec 2023 | 100,000 | - | 100,000 | 100% budget remaining |
| Jedburgh Rd sidewalk | 1204 | Dec 2023 | 28,000 | - | 28,000 | 100% budget remaining |
| Signals | ||||||
| Traffic signal upgrades-collector road intersections | 1270 | Dec 2023 | 16,700 | - | 16,700 | 100% budget remaining |
| Traffic signal upgrades-Island Hwy | 1261 | Dec 2023 | 68,000 | - | 68,000 | 100% budget remaining |
| Street Lighting | ||||||
| LED lighting upgrade | 1194 | Dec 2023 | 30,000 | - | 30,000 | 100% budget remaining |
| Pedestrian lighting improvements | 1236 | Dec 2023 | 22,700 | - | 22,700 | 100% budget remaining |
| St. Giles Street lighting improvements | 1269 | Dec 2023 | 20,000 | - | 20,000 | 100% budget remaining |
| Environmental Services | ||||||
| Lift Stations | ||||||
| Helmcken Bay pump station upgrade | 1211 | Apr 2023 | 272,000 | 301,497 | (29,497) | 11% over budget |
| Packers pump station upgrade | 1163 | Dec 2023 | 670,000 | 888 | 669,112 | 100% budget remaining |
| Parks Services | ||||||
| Park Development | ||||||
| View Royal Park-design | 1028 | Dec 2023 | 13,875 | 9,207 | 4,669 | 34% budget remaining |
| View Royal Park-fencing & garbage receptacles | 1268 | Dec 2023 | 78,700 | - | 78,700 | 100% budget remaining |
| View Royal Park-saltwater marsh/wetland | 1267 | Dec 2023 | 272,625 | - | 272,625 | 100% budget remaining |
| View Royal Park-soft landscaping | 1258 | Dec 2023 | 232,800 | - | 232,800 | 100% budget remaining |
| Watkiss Way Community Park development | 1241 | Dec 2023 | 15,000 | - | 15,000 | 100% budget remaining |
| Park Improvements | ||||||
| Centennial Park diamond #4 fencing improvement | 1218 | Dec 2023 | 40,250 | - | 40,250 | 100% budget remaining |
| Chancellor Park playground replacement | 1254 | Dec 2023 | 300,000 | - | 300,000 | 100% budget remaining |
| Knollwood Park playground replacement | 1199 | Dec 2023 | 100,000 | - | 100,000 | 100% budget remaining |
| Stillwater Road waterfront access | 1245 | Dec 2023 | 40,000 | - | 40,000 | 100% budget remaining |
| Thomas Road waterfront access | 1244 | Dec 2023 | 40,000 | 1,113 | 38,887 | 97% budget remaining |
| Park Vehicles | ||||||
| 1996 Kubota replacement | 1067 | Apr 2023 | 81,600 | 32,779 | 48,821 | 60% budget remaining |
| 2007 Chev 1-ton pickup replacement | 1271 | Dec 2023 | 85,000 | - | 85,000 | 100% budget remaining |
| Riding mower replacement | 1250 | Apr 2023 | 25,000 | 24,028 | 972 | 4% budget remaining |
| Small trailer with cargo rack | 1221 | Dec 2023 | 10,000 | - | 10,000 | 100% budget remaining |
| Grand Total | $ 6,460,370 | $ 429,203 | $ 6,031,167 | 93% budget remaining |
Page 70–71
Extracted from: 2023 06 13 Committee of the Whole Agenda - Agenda - Pdf