This site is in beta — data may be incomplete and features are still being added.
Committee of the Whole/Documents/Schedule B – 2023 Non-core Projects
Appendix

Schedule B – 2023 Non-core Projects

December 12, 2023Page 241 section

Tracking sheet for non-core projects including IT upgrades, community engagement, and traffic calming.

Total non-core project budget: $681,913Total non-core project actual spend: $141,281Active Transportation Network Plan budget: $57,428

Schedule B – 2023 Non-core Projects

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Admin Buildings
Energy audit - Town Hall 510-04 Dec 2023 $ 8,310 $ 3,063 $ 5,248 63% budget remaining
Administration
Accessible BC Act implementation 140-15 Dec 2023 5,100 - 5,100 100% budget remaining
Truth and Reconciliation awareness 140-11 Dec 2023 10,000 - 10,000 100% budget remaining
Finance
Strategic Asset Management Plan 150-03 Dec 2023 20,000 3,280 16,720 84% budget remaining
Sustainable Infrastructure Replacement Plan 150-02 Dec 2023 20,300 2,425 17,875 88% budget remaining
Information Technology
Cyber security policies and process 160-11 Dec 2023 10,000 - 10,000 100% budget remaining
Information security strategic plan 160-10 Oct 2023 8,500 9,095 - 595 7% over budget
Information Technology Coordinator 160-14 Jul 2023 46,725 - 46,725 100% budget remaining
IT asset inventory solution 160-09 Dec 2023 8,500 - 8,500 100% budget remaining
IT disaster recovery plan 160-06 Jan 2023 10,000 2,846 7,154 72% budget remaining
Multi-factor authentication 160-08 Dec 2023 10,000 3,242 6,758 68% budget remaining
Public Relations
Volunteer community improvement program 120-05 Dec 2023 2,500 - 2,500 100% budget remaining
Protective Services
Emergency Program
EOC training and education 230-02 May 2023 5,500 3,000 2,500 45% budget remaining
Extreme heat risk reduction study 230-06 Nov 2023 30,000 30,000 - 0% budget remaining
Fire Building
Energy audit - Public Safety Building 510-29 Dec 2023 5,550 2,063 3,488 63% budget remaining
Fire General
Community wildfire protection plan update 210-03 Dec 2023 33,000 - 33,000 100% budget remaining
Wildfire fuel management 210-04 Dec 2023 25,000 - 25,000 100% budget remaining
Fire Volunteers
Volunteer firefighter qualifications compensation 211-03 May 2023 24,000 - 24,000 100% budget remaining
Transportation Services
Traffic Calming
Stormont Road traffic calming 323-01 Dec 2023 8,000 - 8,000 100% budget remaining
Transportation-General
Active Transportation Network Plan 310-08 May 2023 57,428 48,404 9,024 16% budget remaining
Development Services
Planning and Development Services
Coastal Adaptation Plan 510-28 Dec 2023 60,000 - 60,000 100% budget remaining
Community engagement strategy 510-22 Dec 2023 80,000 - 80,000 100% budget remaining
Official Community Plan review 510-02 Dec 2023 41,000 5,502 35,498 87% budget remaining
Off-street parking review 510-32 Dec 2024 35,000 - 35,000 100% budget remaining
Parks Services
Parks, Rec & Culture-General
Public art acquisition-mural 710-01 Oct 2023 35,000 28,361 6,639 19% budget remaining
Urban forestry strategy 310-14 Dec 2023 82,500 - 82,500 100% budget remaining
Grand Total $ 681,913 $ 141,281 $ 540,632 79% budget remaining
Page 24
Extracted from: 2023 12 12 Committee of the Whole Agenda - Agenda - Pdf