Schedule B – Non-core Projects

November 9, 2021Page 521 section

A project status table for non-core initiatives, showing budgets, actual spend to date, and estimated completion dates.

2. APPROVAL OF AGENDA (motion to approve)
Grand Total Project Budget: $455,540Grand Total Project Actual: $76,139

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to October 31, 2021 Meeting Date: November 9, 2021

Schedule B – Non-core Projects

Project / Category CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Finance
Long-term financial plan and sustainability review 150-02 Sep 2022 $49,550 $ 4,050 $ 45,500 92% budget remaining
Information Technology
IT Strategic Plan update 160-01 Nov 2021 20,000 0 20,000 100% budget remaining
Microsoft productivity-business process improvements 160-04 Dec 2021 15,000 1,394 13,606 91% budget remaining
Public Relations - Archives
Electronic access to archives repository 125-01 Dec 2021 5,265 3,510 1,755 33% budget remaining
Protective Services
Bylaw Enforcement
Secondary suites online renewal 220-02 Oct 2021 5,000 0 5,000 100% budget remaining
Emergency Program
Emergency Response and Recovery Plan update 230-04 Dec 2023 20,000 0 20,000 100% budget remaining
EOC equipment and supplies 230-02 Jun 2021 6,500 8,180 (1,680) 26% over budget
Emergency Support Services
ESS equipment and supplies 230-05 Nov 2022 1,500 1,604 (104) 7% over budget
Fire General
Community wildfire protection plan update 210-03 Dec 2022 33,000 0 33,000 100% budget remaining
Fire services volunteer staffing restructure* 211-02 Jul 2021 (6,296) 0 (6,296) 100% budget remaining
Full-time firefighter staff increase* 211-01 Jul 2021 35,725 0 35,725 100% budget remaining
Fire Volunteers
Fire services volunteer staffing restructure* 211-02 Jul 2021 20,296 0 20,296 100% budget remaining
Development Services
Economic Development
Commercial precinct plans 510-15 Jun 2021 55,000 38,439 16,561 30% budget remaining
Planning and Development Services
Community Climate Action Plan 510-27 May 2022 75,000 0 75,000 100% budget remaining
OCP review 510-02 Jun 2022 120,000 18,964 101,036 84% budget remaining
Grand Total $455,540 $ 76,139 $ 379,401 83% budget remaining

* Personnel costs are not individually tracked in the financial system; actual costs will be reported as $0 for the purposes of this report.