Committee of the Whole/Documents/Schedule B – Non-core Projects
Appendix

Schedule B – Non-core Projects

July 13, 2021Page 472 sections

Detailed table of progress and spending for non-core municipal projects.

2. APPROVAL OF AGENDA (motion to approve)
$455,540 total non-core budgetOCP review: $120,000 budget

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to June 30, 2021

Meeting Date: July 13, 2021

Page 47

Schedule B – Non-core Projects

Project / Description CC Code Est Completion Project budget Project actual Project variance Variance %
General Government Services
Finance
Long-term financial plan and sustainability review 150-02 Sep 2022 $49,550 $0 $49,550 100% budget remaining
Information Technology
IT Strategic Plan update 160-01 Oct 2021 20,000 0 20,000 100% budget remaining
Microsoft productivity-business process improvements 160-04 Dec 2021 15,000 0 15,000 100% budget remaining
Public Relations - Archives
Electronic access to archives repository 125-01 Dec 2021 5,265 0 5,265 100% budget remaining
Protective Services
Bylaw Enforcement
Secondary suites online renewal 220-02 Oct 2021 5,000 0 5,000 100% budget remaining
Emergency Program
Emergency Response and Recovery Plan update 230-04 Dec 2023 20,000 0 20,000 100% budget remaining
EOC equipment and supplies 230-02 Jun 2021 6,500 8,180 -1,680 26% over budget
Emergency Support Services
ESS equipment and supplies 230-05 Nov 2022 1,500 0 1,500 100% budget remaining
Fire General
Community wildfire protection plan update 210-03 Dec 2022 33,000 0 33,000 100% budget remaining
Fire services volunteer staffing restructure* 211-02 Jul 2021 -6,296 0 -6,296 100% budget remaining
Full-time firefighter staff increase* 211-01 Jul 2021 35,725 0 35,725 100% budget remaining
Fire Volunteers
Fire services volunteer staffing restructure* 211-02 Jul 2021 20,296 0 20,296 100% budget remaining
Development Services
Economic Development
Commercial precinct plans 510-15 Jun 2021 55,000 22,689 32,311 59% budget remaining
Planning and Development Services
Community Climate Action Plan 510-27 May 2022 $75,000 $0 $75,000 100% budget remaining
OCP review 510-02 Jun 2022 $120,000 $0 $120,000 100% budget remaining
Grand Total $455,540 $30,869 $424,671 93% budget remaining

* Personnel costs are not individually tracked in the financial system; actual costs will be reported as $0 for the purposes of this report.

Page 47