Committee of the Whole/Documents/Schedule B – Non-core Projects
Appendix

Schedule B – Non-core Projects

September 14, 2021Page 801 section

Tracking sheet for one-time or non-recurring project budgets and actual expenditures.

6.2.3.d Budget Variance and Projects Update Report - August 2021
$455,540 total non-core project budget$50,992 total actual spend YTD

Schedule B – Non-core Projects

Row Labels CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Finance
Long-term financial plan and sustainability review 150-02 Sep 2022 $ 49,550 $ 4,050 $ 45,500 92% budget remaining
Information Technology
IT Strategic Plan update 160-01 Oct 2021 20,000 0 20,000 100% budget remaining
Microsoft productivity-business process improvements 160-04 Dec 2021 15,000 306 14,694 98% budget remaining
Public Relations - Archives
Electronic access to archives repository 125-01 Dec 2021 5,265 0 5,265 100% budget remaining
Protective Services
Bylaw Enforcement
Secondary suites online renewal 220-02 Oct 2021 5,000 0 5,000 100% budget remaining
Emergency Program
Emergency Response and Recovery Plan update 230-04 Dec 2023 20,000 0 20,000 100% budget remaining
EOC equipment and supplies 230-02 Jun 2021 6,500 8,180 (1,680) 26% over budget
Emergency Support Services
ESS equipment and supplies 230-05 Nov 2022 1,500 0 1,500 100% budget remaining
Fire General
Community wildfire protection plan update 210-03 Dec 2022 33,000 0 33,000 100% budget remaining
Fire services volunteer staffing restructure* 211-02 Jul 2021 (6,296) 0 (6,296) 100% budget remaining
Full-time firefighter staff increase* 211-01 Jul 2021 35,725 0 35,725 100% budget remaining
Fire Volunteers
Fire services volunteer staffing restructure* 211-02 Jul 2021 20,296 0 20,296 100% budget remaining
Development Services
Economic Development
Commercial precinct plans 510-15 Jun 2021 55,000 38,439 16,561 30% budget remaining
Planning and Development Services
Community Climate Action Plan 510-27 May 2022 75,000 0 75,000 100% budget remaining
OCP review 510-02 Jun 2022 120,000 18 119,982 100% budget remaining
Grand Total $ 455,540 $ 50,992 $ 404,548 89% budget remaining

* Personnel costs are not individually tracked in the financial system; actual costs will be reported as $0 for the purposes of this report.

Page 80