Committee of the Whole/Documents/Schedule C – Capital Projects
Appendix

Schedule C – Capital Projects

September 14, 2021Page 812 sections

Tracking sheet for capital projects including road improvements, sidewalk construction, and vehicle replacements.

2. APPROVAL OF AGENDA
Atkins Road sidewalk: $843,225 budgetSix Mile Road improvements: $289,250 budgetTotal capital budget: $2,609,526

Report to Committee of the Whole Re: Budget Variance and Projects Update Report to September 3, 2021 Meeting Date: September 14, 2021

Page 81

Schedule C – Capital Projects

Schedule C – Capital Projects table showing budget variance and project updates
Schedule C – Capital Projects table showing budget variance and project updates
Project CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Building Improvements
Town Hall lunchroom renovation 1232 Sep 2021 $ 50,000 $ 2,472 $ 47,528 95% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Dec 2021 18,700 0 18,700 100% budget remaining
IT workstation ever-greening 1070 Sep 2021 40,000 18,664 21,336 53% budget remaining
Land Acquisitions
Land acquisition 1054 Jun 2021 150,000 7,743 142,257 95% budget remaining
Protective Services
Emerg Prog Equipment
EOC equipment and supplies 0850 Jun 2023 19,500 0 19,500 100% budget remaining
ESS equipment and supplies 0849 Nov 2021 23,500 0 23,500 100% budget remaining
Fire - Furniture and Equipment
Public Safety Building public art 1227 Sep 2021 52,000 35,857 16,143 31% budget remaining
Fire - Vehicles
Fire services vehicle replacement plan-Ladder 35 upgrade 0845 Oct 2021 75,000 0 75,000 100% budget remaining
Fire services vehicle replacement plan-Marine Unit 34 overhaul and upgrade 1239 Nov 2021 50,000 884 49,116 98% budget remaining
Fire services vehicle replacement plan-rescue truck 1033 Sep 2021 27,000 4,626 22,374 83% budget remaining
Rescue 36 equipment 1209 Jun 2021 8,000 8,000 0 0% over budget
Police Services
RCMP building architectural design 1103 Dec 2021 20,000 0 20,000 100% budget remaining
RCMP building capital projects 1152 Dec 2021 26,880 0 26,880 100% budget remaining
Transportation Services
Road Projects
Six Mile Road improvements 1168 Sep 2021 289,250 69,391 219,860 76% budget remaining
Sidewalks
Atkins Road sidewalk-Anya Court to Langford border 1234 Dec 2022 843,225 0 843,225 100% budget remaining
Street Lighting
Pedestrian lighting improvements 1236 Oct 2021 45,000 0 45,000 100% budget remaining
Environmental Services
Collection Systems
Sewer gravity main upgrade-Fort Victoria 1237 Nov 2021 32,000 1,400 30,600 96% budget remaining
Sewer gravity main upgrade-Pheasant Lane 1238 Nov 2021 32,000 0 32,000 100% budget remaining
Lift Stations
Helmcken Bay pump station upgrade 1211 Nov 2021 32,000 6,243 25,757 80% budget remaining
Thetis Cove pump station upgrade 1162 Jun 2021 190,000 160,029 29,971 16% budget remaining
Parks Services
Park Development
Hart Road Lime Kiln heritage restoration 3400 209,471 0 209,471 100% budget remaining
View Royal Park development 1028 Nov 2021 158,000 0 158,000 100% budget remaining
Park Improvements
Development of road ends 0901 Aug 2021 20,000 0 20,000 100% budget remaining
Parks signage and wayfinding 1175 Dec 2021 10,000 0 10,000 100% budget remaining
Park Vehicles
Parks vehicle replacement plan-1996 Kubota 1067 Oct 2021 81,600 0 81,600 100% budget remaining
Parks vehicle replacement plan-2006 John Deere #2305 1235 Aug 2021 40,000 0 40,000 100% budget remaining
Parks vehicle replacement plan-2007 John Deere #3520 1230 Jun 2021 56,400 49,348 7,052 13% budget remaining
Small trailer with cargo rack 1221 Jul 2021 10,000 0 10,000 100% budget remaining
Grand Total $2,609,526 $364,658 $2,244,868 86% budget remaining