This site is in beta — data may be incomplete and features are still being added.
Committee of the Whole/Documents/Schedule C – Capital Projects
Appendix

Schedule C – Capital Projects

December 14, 2021Page 291 section

Detailed list of status updates and financial tracking for major capital infrastructure projects.

1. CALL TO ORDER (Mayor Screech)
Six Mile Road improvements budget: $289,250Atkins Road sidewalk budget: $843,225Grand total project variance: $1,978,541

Report to Committee of the Whole

Re: Budget Variance and Projects Update Report to December 7, 2021 Meeting Date: December 14, 2021

Schedule C – Capital Projects

Project Description CC Code Est. Completion Project budget Project actual Project variance Variance %
General Government Services
Building Improvements
Town Hall lunchroom renovation 1232 Nov 2021 $50,000 $39,740 $10,260 21% budget remaining
Information Technology
IT infrastructure hardware replacements 1044 Jan 2022 18,700 0 18,700 100% budget remaining
IT workstation ever-greening 1070 Nov 2021 40,000 31,440 8,560 21% budget remaining
Land Acquisitions
Land acquisition 1054 Jun 2021 150,000 127,751 22,249 15% budget remaining
Protective Services
Emerg Prog Equipment
EOC equipment and supplies 0850 Dec 2022 19,500 0 19,500 100% budget remaining
ESS equipment and supplies 0849 Nov 2021 23,500 6,259 17,241 73% budget remaining
Fire - Furniture and Equipment
Public Safety Building public art 1227 May 2022 $52,000 $52,156 ($156) 0% over budget
Fire - Vehicles
Fire services vehicle replacement plan-Ladder 35 upgrade 0845 Dec 2021 $75,000 $24,623 $50,377 67% budget remaining
Fire services vehicle replacement plan-Marine Unit 34 overhaul and upgrade 1239 Nov 2021 50,000 931 49,069 98% budget remaining
Fire services vehicle replacement plan-rescue truck 1033 Nov 2021 27,000 7,928 19,072 71% budget remaining
Rescue 36 equipment 1209 Jun 2021 8,000 8,000 0 0% over budget
Police Services
RCMP building architectural design 1103 Dec 2021 20,000 0 20,000 100% budget remaining
RCMP building capital projects 1152 Dec 2021 26,880 0 26,880 100% budget remaining
Transportation Services
Road Projects
Six Mile Road improvements 1168 Dec 2021 289,250 80,113 209,137 72% budget remaining
Sidewalks
Atkins Road sidewalk-Anya Court to Langford border 1234 Dec 2022 843,225 0 843,225 100% budget remaining
Street Lighting
Pedestrian lighting improvements 1236 Dec 2021 45,000 4,953 40,047 89% budget remaining
Environmental Services
Collection Systems
Sewer gravity main upgrade-Fort Victoria 1237 Nov 2021 32,000 3,500 28,500 89% budget remaining
Sewer gravity main upgrade-Pheasant Lane 1238 Nov 2021 32,000 0 32,000 100% budget remaining
Lift Stations
Helmcken Bay pump station upgrade 1211 Dec 2021 $32,000 $16,410 $15,590 49% budget remaining
Thetis Cove pump station upgrade 1162 Jun 2021 190,000 160,029 29,971 16% budget remaining
Parks Services
Park Development
Hart Road Lime Kiln heritage restoration 3400 209,471 0 209,471 100% budget remaining
View Royal Park development 1028 Apr 2022 158,000 13,788 144,212 91% budget remaining
Park Improvements
Development of road ends 0901 Aug 2021 20,000 4,015 15,985 80% budget remaining
Parks signage and wayfinding 1175 Dec 2021 10,000 0 10,000 100% budget remaining
Park Vehicles
Parks vehicle replacement plan-1996 Kubota 1067 81,600 0 81,600 100% budget remaining
Parks vehicle replacement plan-2006 John Deere #2305 1235 Dec 2021 40,000 0 40,000 100% budget remaining
Parks vehicle replacement plan-2007 John Deere #3520 1230 Nov 2021 56,400 49,348 7,052 13% budget remaining
Small trailer with cargo rack 1221 Dec 2021 10,000 0 10,000 100% budget remaining
Grand Total $2,609,526 $630,985 $1,978,541 76% budget remaining
Page 29
Extracted from: 2021 12 14 Committee of the Whole Agenda - Agenda - Pdf