Committee of the Whole/Documents/Finance and Administration Report - CAPITAL PROJECT UPDATE
Staff Report

Finance and Administration Report - CAPITAL PROJECT UPDATE

June 14, 2016Page 362 sections

Brief update on the status of capital project expenditures and completion dates as of May 31, 2016.

2 APPROVAL OF AGENDA
Report dated June 9, 2016Expenditures are within budget

TOWN OF VIEW ROYAL

Page 36

Finance and Administration Report

TO: Committee of the Whole DATE: June 9, 2016 FROM: Monique Watson, Senior Accountant MEETING DATE: June 14, 2016

CAPITAL PROJECT UPDATE

RECOMMENDATION: THAT the Committee receive the May 2016 Capital Project Update Report for information.

CHIEF ADMINISTRATIVE OFFICER'S COMMENTS: I concur with the recommendation.

PURPOSE OF REPORT: To provide Council with information regarding Capital Project expenditures and projected completion dates.

INFORMATION: The attached report outlines expenditures to May 31, 2016 and current projected completion dates. Year to date expenditures are within budget and we will continue to closely monitor expenditures throughout the year to ensure capital projects are on time and on budget as at the end of the fiscal year.

SUBMITTED BY: M. Dillabaugh, Director of Finance

REVIEWED BY: K. Anema, Chief Administrative Officer