2016 Capital Projects List

June 14, 2016Page 371 section

Tabular listing of 2016 capital projects, their GL accounts, 2016 budgets, and projected completion dates.

2 APPROVAL OF AGENDA
Total 2016 Capital Projects Budget: $2,456,987Fire Engine Replacement: $100,000Burnside Rd West Reconstruction: $145,000

2016 Capital Projects

Transportation

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Road Reconstruction
Watkiss Way at Burnside Road West Intersection Reconstruction (1900 Watkiss Way Dvlpmt) 2-2-11105 1085 39,925 577 39,348 July
Watkiss Way East of Burnside Road West Lot C Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1086 145,000 142,248 2,752 July
Watkiss Way at Eagle Creek Frontage Works (1900 Watkiss Way Dvlpmt) 2-2-11105 1087 57,998 3,076 54,922 September
Burnett Rd-Pheasant Ln (Old Island Hwy to VR Park)-Construction 2-2-11105 1109 350,000 6,488 343,512 December
Island Highway Pedestrian overpass to Shoreline Drive- Design 2-2-11105 1110 35,000 35,000 November
Island Highway Stewart to Beaumont- Design 2-2-11105 1111 35,000 35,000 August
Watkiss Way west of Burnside Road (asphalt curb and paved shoulder) 2-2-11105 1112 15,000 15,000 September
Annual Pavement Rehabilitation
Watkiss Way EB West of Helmcken Road (Eagle Creek) 2-2-11107 1107 55,000 49,915 5,085 Complete
Burnside Rd West: Kami Court to Border with Saanich) 2-2-11107 1114 45,000 45,000 July
Structures
Admirals Safety Improvements 2-2-11105 1072 200,000 200,000 November
Craigflower Bridge Replacement Project (CT) - Land Acquisition 2-2-11109 1013 65,000 65,000 November
Helmcken Rd at Burnside Rd West Traffic Island 2-2-11106 1115 25,000 25,000 September
E & N Trail stairs 2-2-11106 1108 15,000 14,365 635 Complete
Electrical
Seasonal Lighting on Helmcken Road North of TCH and Watkiss 2-2-11103 1093 12,712 12,712 September
Island Highway at Knollwood Rd/Kislingbury Ln UPS 2-2-11106 1116 11,000 11,000 July
Six Mile Road at Chilco Road Flashing Pedestrian Crossing 2-2-11106 1117 22,500 22,500 October
Island Highway at Heddle Ped Crosswalk 2-2-11106 1118 25,000 25,000 October
Kami Court & Burnside Crosswalk 2-2-11108 1119 30,000 30,000 September
Miscellaneous
ECV - To complete Park Trail (to Little Rd at North End) (phase 2) 2-2-11108 1120 15,000 15,000 December
Kayak Launch on Shoreline Drive 2-2-11108 1121 50,000 50,000 December
Quincy Street Pedestrian Access 2-2-11108 1122 1,000 1,000 December
Banners 2-2-11106 1123 5,000 5,000 December
SUB-TOTAL 1,255,135 216,669 1,038,466

Drainage

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
View Royal Avenue (Beaumont Avenue to Stewart Avenue) - Design 2-2-11201 1124 20,000 20,000 October
SUB-TOTAL 20,000 20,000

Sewer

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Price Bay Pump Station Upgrade (cost update) 5-2-11702 1125 425,000 425,000 December
Helmcken Bay and Helmcken Park Pump Station Pumps 5-2-11702 1105 45,000 36,699 8,301 September
SUB-TOTAL 470,000 36,699 433,301

Parks

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Improvements to easements
Dukrill Trail Water Access / Stairs 2013 2-2-11301 1126 12,000 12,000 November
Park improvements
MacLennan Trail Improvements - Paving Trail Sections 2-2-11302 1127 20,000 20,000 September
Fencing - General fencing to start defining the Town's areas 2-2-11302 1128 15,000 15,000 December
Playgrounds - replacement program 2-2-11302 1129 60,000 60,000 November
Robin Hill Park & Edwards Park - RHP - pave entrance from Haagensen Court. EP - pave entrance apron from BamfordCourt 2-2-11302 1130 8,500 8,500 September
Edwards Park Summit fence 2-2-11302 1131 5,000 5,000 October
Park Development
View Royal Park - Implementation of VR Park Plan (Parking Lot Paving and tree irrigation) 2-2-11303 1028 50,000 50,000 August
View Royal Park (Preac) - Fitness Stations/Equipment 2-2-11302 1099 80,000 58,750 21,250 July
Park Vehicles
New 1/2 Ton Pickup and accessories 2-2-11304 1132 30,000 30,000 December
Improvements to Public Buildings
Park Shop Shed Repair 2-2-11401 1133 13,500 13,500 September
SUB-TOTAL 294,000 58,750 235,250

Fire Services / Bylaw / Police Services

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Fire Services - Buildings
Public Safety Building ($256,552 carryforward of approved budget from previous years) 2-2-12101 1032/1061 74,901 256,552 181,651 December
Fire Services - Vehicles
Vehicle Replacement - Fire Engine Replacement 2-2-12102 1033 100,000 16,078 18,000 101,922 November
Bylaw Enforcement
Body Cameras 2-2-12401 1134 3,000 3,000 September
Police Services
RCMP Building - Top Floor Works 2-2-12301 1103 5,000 5,000 December
SUB-TOTAL 108,000 90,979 274,552 291,573

Administration / General Government

Project Name G/L Account Cost Centre # 2016 Budget Preliminary 2016 YTD May 30 Additional Funds Approved 2016 Variance Actual to Budget (over) / under Projected Completion Date
Annual Information Services Replacement Program 2-2-13103 1070 50,000 50,000 December
IT Strategic Plan implementation 2-2-13103 1135 154,852 154,852 First year of three year project
Flag Poles 2-2-13104 1136 2,000 2,000 December
Aerial Photo 2-2-13104 1137 2,000 2,000 December
Land Acquisitions
Misc. Land Acquisition 2-2-13201 1045 100,000 100,000 December
SUB-TOTAL 308,852 308,852

TOTAL 2016 CAPITAL PROJECTS | | | 2,455,987 | 403,098 | 274,552 | 2,327,441 |