Committee of the Whole/Documents/Landscape Cost Estimate - Lillian’s Gate
Appendix

Landscape Cost Estimate - Lillian’s Gate

June 14, 2016Page 1161 section

Itemized breakdown of landscape construction and material costs.

2 APPROVAL OF AGENDA
Hard Landscaping: $142,250Soft Landscaping: $79,996

Landscape Cost Estimate

Lillian's Gate

Description Quantity Unit Cost Total Cost
SOFT LANDSCAPING
Trees
Large, Deciduous 8 $ 750.00 ea. $ 6,000.00
Small, Conifers 28 $ 350.00 ea. $ 9,800.00
Medium, Flowering 15 $ 500.00 ea. $ 7,500.00
Plants
Large Shrubs 108 $ 25.00 ea. $ 2,700.00
Medium Shrubs 362 $ 20.00 ea. $ 7,240.00
Small Shrubs 560 $ 10.00 ea. $ 5,600.00
Ground covers 450 $ 3.50 ea. $ 1,575.00
Sod/Soil
Sod 532 m² $ 8.00 /m² $ 4,256.00
Soil 944 m² $ 25.00 /m² $ 23,600.00
Stormwater Pond 63 m² $ 75.00 /m² $ 4,725.00
Rain garden 67 m² LS $ 7,000.00
SOFT LANDSCAPING $ 79,996.00
HARD LANDSCAPING
Concrete Walkways 50 m² $ 45.00 /m² $ 2,250.00
Basalt Walkway 126 m² $ 25.00 /m² $ 3,150.00
Special Paving - Patios 203 m² $ 75.00 /m² $ 15,225.00
Special Paving - Site 453 m² $ 75.00 /m² $ 33,975.00
Wall Rain Feature LS $ 6,500.00
Wall Rain Feature - small LS $ 4,500.00
Stepped Boulder (4 ft. height) 105 m² $ 190.00 $ 19,950.00
Site Furnishings
Entrance Signage 2 ea. LS $ 8,000.00
Bridge 2 ea. $ 2,500.00 ea. $ 5,000.00
Trellis(on rock wall) LS $ 18,000.00
Trellis (for patios) 6 ea. $ 2,000.00 ea. $ 12,000.00
Pavillion 1 ea. LS $ 8,500.00
Concrete Planter 9 ea. $ 500.00 $ 4,500.00
Bike Rack 1 ea. $ 700.00 $ 700.00
HARD LANDSCAPING $ 142,250.00
IRRIGATION LS $ 18,000.00
TOTAL HARD & SOFT LANDSCAPING COST & IRRIGATION $ 240,246.00

NOTE : Does not include roadworks, parking surfaces or civil engineering elements

Page 116

Document Images

(13)
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Extracted from: 2016 06 14 Committee of the Whole Agenda