Appendix
Schedule B – 2022 Non-core Projects
November 8, 2022Page 432 sections
Status and financial tracking for specific non-core municipal projects.
$716,340 total project budget$316,215 total project actual spent YTD56% budget remaining
Report to Committee of the Whole
Re: Budget Variance and Projects Update Report to October 31, 2022
Meeting Date: November 8, 2022
Page 43
Schedule B – 2022 Non-core Projects

| Project Category | CC Code | Est. Completion | Project budget | Project actual | Project variance | Variance % |
|---|---|---|---|---|---|---|
| General Government Services | ||||||
| Admin Buildings | ||||||
| Energy audit of municipal buildings-Town Hall | 510-04 | Dec 2022 | $15,000 | $0 | $15,000 | 100% budget remaining |
| Administration | ||||||
| Truth and Reconciliation awareness | 140-11 | Dec 2022 | 10,000 | 0 | 10,000 | 100% budget remaining |
| Finance | ||||||
| Long-term financial plan and sustainability review | 150-02 | Sep 2022 | 45,500 | 42,188 | 3,313 | 7% budget remaining |
| Information Technology | ||||||
| Digital signature certificate service | 160-05 | Oct 2022 | $5,000 | $0 | $5,000 | 100% budget remaining |
| Information security mgmt system-business continuity | 160-07 | Dec 2022 | 15,000 | 0 | 15,000 | 100% budget remaining |
| Information security mgmt system-IT asset inventory so | 160-09 | Dec 2022 | 5,000 | 0 | 5,000 | 100% budget remaining |
| Information security mgmt system-IT disaster recovery | 160-06 | Nov 2022 | $20,000 | $0 | $20,000 | 100% budget remaining |
| Information security mgmt system-multi-factor authent | 160-08 | Oct 2022 | $10,000 | $0 | $10,000 | 100% budget remaining |
| Public Relations | ||||||
| Online citizen budget engagement | 120-03 | Apr 2022 | 6,000 | 6,322 | (322) | 5% over budget |
| Protective Services | ||||||
| Emergency Program | ||||||
| Emergency Response and Recovery Plan | 230-04 | Feb 2023 | 20,000 | 0 | 20,000 | 100% budget remaining |
| EOC supplies | 230-02 | Dec 2022 | 7,000 | 0 | 7,000 | 100% budget remaining |
| Hazard risk vulnerability assessment | 230-03 | Sep 2022 | 15,000 | 0 | 15,000 | 100% budget remaining |
| Fire Building | ||||||
| Energy audit of municipal buildings-PSB | 510-29 | Dec 2022 | 15,000 | 0 | 15,000 | 100% budget remaining |
| Public Safety Building public art | 215-02 | May 2022 | 15,000 | 9,134 | 5,866 | 39% budget remaining |
| Fire General | ||||||
| Community Wildfire Protection Plan | 210-03 | Dec 2022 | 33,000 | 0 | 33,000 | 100% budget remaining |
| Protective Inspections | ||||||
| Energy Step Code implementation | 241-01 | Dec 2022 | 12,000 | 14,862 | (2,862) | 24% over budget |
| RCMP | ||||||
| Additional RCMP members* | 800-06 | Dec 2022 | 23,200 | 0 | 23,200 | 100% budget remaining |
| Transportation Services | ||||||
| Transportation-General | ||||||
| Active Transportation Plan | 310-08 | Dec 2022 | 145,000 | 64,047 | 80,953 | 56% budget remaining |
| Development Services | ||||||
| Planning and Development Services | ||||||
| Community Climate Action Plan | 510-27 | May 2022 | 25,000 | 12,091 | 12,909 | 52% budget remaining |
| OCP review | 510-02 | Jul 2022 | 94,640 | 89,719 | 4,921 | 5% budget remaining |
| Parks Services | ||||||
| Centennial Park | ||||||
| Helmcken Centennial Park Master Plan | 722-03 | Dec 2022 | 55,000 | 0 | 55,000 | 100% budget remaining |
| Park Trees | ||||||
| Replacement tree water bags | 730-02 | Dec 2022 | 5,000 | 4,713 | 288 | 6% budget remaining |
| Resident tree planting program | 730-01 | Dec 2022 | 10,000 | 0 | 10,000 | 100% budget remaining |
| Parks, Rec & Culture-General | ||||||
| Public art acquisition | 710-01 | Jul 2023 | $35,000 | $5,661 | $29,340 | 84% budget remaining |
| Small Parks & Greenspaces | ||||||
| Greater Victoria Green Team program expansion | 720-02 | Dec 2022 | 7,000 | 0 | 7,000 | 100% budget remaining |
| Recreation & Culture Services | ||||||
| Recreation Services | ||||||
| WSPR skatepark contribution | 750-01 | Oct 2022 | $68,000 | $67,480 | $520 | 1% budget remaining |
| Grand Total | $716,340 | $ 316,215 | $400,125 | 56% budget remaining |
Page 43
Extracted from: 2022 11 08 Committee of the Whole Agenda - Agenda - Pdf