Schedule B – Non-core Projects
January 11, 2022Page 261 section
Detailed financial status and completion estimates for non-core municipal projects.
Total project budget for non-core items: $455,540OCP review actual spend: $45,362Commercial precinct plans actual spend: $38,439
Schedule B – Non-core Projects
| Project | CC Code | Est. Completion | Project budget | Project actual | Project variance | Variance % |
|---|---|---|---|---|---|---|
| General Government Services | ||||||
| Finance | ||||||
| Long-term financial plan and sustainability review | 150-02 | Sep 2022 | $49,550 | $ 4,050 | $ 45,500 | 92% budget remaining |
| Information Technology | ||||||
| IT Strategic Plan update | 160-01 | Nov 2021 | 20,000 | 18,457 | 1,543 | 8% budget remaining |
| Microsoft productivity-business process improvements | 160-04 | Dec 2021 | 15,000 | 1,394 | 13,606 | 91% budget remaining |
| Public Relations - Archives | ||||||
| Electronic access to archives repository | 125-01 | Feb 2022 | 5,265 | 6,060 | -795 | 15% over budget |
| Protective Services | ||||||
| Bylaw Enforcement | ||||||
| Secondary suites online renewal | 220-02 | Jul 2022 | 5,000 | 0 | 5,000 | 100% budget remaining |
| Emergency Program | ||||||
| Emergency Response and Recovery Plan update | 230-04 | Dec 2023 | 20,000 | 0 | 20,000 | 100% budget remaining |
| EOC equipment and supplies | 230-02 | Jun 2021 | 6,500 | 8,180 | (1,680) | 26% over budget |
| Emergency Support Services | ||||||
| ESS equipment and supplies | 230-05 | Dec 2021 | 1,500 | 1,604 | -104 | 7% over budget |
| Fire General | ||||||
| Community wildfire protection plan update | 210-03 | Dec 2022 | 33,000 | 0 | 33,000 | 100% budget remaining |
| Fire services volunteer staffing restructure* | 211-02 | Jul 2021 | (6,296) | 0 | (6,296) | 100% budget remaining |
| Full-time firefighter staff increase* | 211-01 | Jul 2021 | 35,725 | 0 | 35,725 | 100% budget remaining |
| Fire Volunteers | ||||||
| Fire services volunteer staffing restructure* | 211-02 | Jul 2021 | 20,296 | 0 | 20,296 | 100% budget remaining |
| Development Services | ||||||
| Economic Development | ||||||
| Commercial precinct plans | 510-15 | Jun 2021 | 55,000 | 38,439 | 16,561 | 30% budget remaining |
| Planning and Development Services | ||||||
| Community Climate Action Plan | 510-27 | May 2022 | 75,000 | 42,419 | 32,581 | 43% budget remaining |
| OCP review | 510-02 | Jun 2022 | 120,000 | 45,362 | 74,638 | 62% budget remaining |
| Grand Total | $455,540 | $ 165,964 | $ 289,576 | 64% budget remaining |
* Personnel costs are not individually tracked in the financial system; actual costs will be reported as $0 for the purposes of this report.