Council Meeting/Documents/HELMCKEN SIDEWALK EAGLE CREEK TO ASPIRE PROJECT UPDATE
Staff Report

HELMCKEN SIDEWALK EAGLE CREEK TO ASPIRE PROJECT UPDATE

March 18, 2025Pages 63–662 sections

Staff recommendation to not award the sidewalk project for Helmcken Road and to remove it from the Five-Year Financial Plan.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 7:00 p.m.
March 11, 2025Unitii Corporation quoted $94,757.85 net of GSTStaff recommend cancellation as existing 1.5m sidewalk is in good conditionProject C-054

TOWN OF VIEW ROYAL COUNCIL REPORT

TO: Council FROM: Ivan Leung, P.Eng, Director of Engineering DATE: March 11, 2025 MEETING DATE: March 18, 2025

Page 63–66

HELMCKEN SIDEWALK EAGLE CREEK TO ASPIRE PROJECT UPDATE

RECOMMENDATION:

THAT Council not award the “Curb and Sidewalk Replacement – Helmcken-Eagle Creek Village to Burnside Road West” Project (C-054) to Unitii Corporation in the amount of $105,000, net of GST;

AND THAT this project be removed from the 2024-2028 Five-Year Financial Plan.

ALTERNATIVE OPTIONS:

Option #2: THAT Council award the Helmcken Sidewalk Upgrades – Eagle Creek to Aspire to Unitii Corporation in the amount up to $105,000 net of GST and that the construction be pre-approved in the budget for construction in 2025.

Option #3: THAT Council direct staff to undergo the public bid process in accordance with the Purchasing Policy 1600-021 and that the construction be pre-approved in the budget for construction in 2025.

Staff do not recommend this option as doing so will likely result in higher project costs and additional coordination work being required.

PURPOSE:

To seek Council direction on the construction phase of the Helmcken Sidewalk Eagle Creek to Aspire project (Project C-054 of the 2024-2028 Financial Plan, attached).

BACKGROUND:

The timing of this project is planned to be simultaneous and in partnership with the Aspire development (3 Helmcken Road) – doing so would reduce construction disruptions to residents and commuters while lowering overall construction costs.

The Aspire development’s General Contractor, Unitii Corporation, has quoted a price of $94,757.85 (net of GST) to complete this project. The works would be scheduled with Aspire’s own frontage construction work.

DISCUSSION:

In an effort to receive good value for tax dollars and considering significant Casino Revenue usage for capital projects over the next five years, staff recommend cancelling this project to focus efforts on priorities elsewhere within the Town (that do not currently have sidewalks or have more substandard pedestrian infrastructure). This recommendation is put forward by staff for the following reasons:

  • There already exists a 1.5m wide separated concrete sidewalk, in good condition, within the project area. While the sidewalk upgrades would increase the sidewalk width by 0.3m to 1.8m (current bylaw), the separation distance of the sidewalk to the roadway will remain the same. There is also evidence of 1.5m sidewalks elsewhere within the Town;
  • ICBC crash data identifies one pedestrian related incident over the last five years. More focus can be applied to capital projects with higher conflict areas and other roadways that completely lack sidewalks, including sidewalks on Helmcken Road across the street from this project;
  • No recent complaints or comments from nearby residents were found regarding the existing sidewalk;
  • The Town would replace asphalt curb only on a case-by-case basis. Replacement ‘as and when’ could be a cost-effective asset replacement approach (the curb has lasted for 20 years).
Old versus new sidewalk view looking north from Eagle Creek Village on Helmcken Road
Old versus new sidewalk view looking north from Eagle Creek Village on Helmcken Road

Figure 1: Old versus new, looking north from Eagle Creek Village (Google Streetview, Nov. 2022, Retrieved Mar. 11, 2025)

Alternatively, should Council wish to proceed with the project, staff recommend a direct award to Unitii Corporation as it is considered best value for money spent (Purchasing Policy 1600-021 Sections 2.2 and 2.6). Staff recommend applying a 10% contingency amount to the direct construction costs, thus totalling $105,000 net of GST. This amount is well within the project budget.

ANALYSIS:

Impacts and implications can be summarized as follows:

Impact Category Analysis
Community Impact: While wider sidewalks will help improve accessibility and provide a uniform pedestrian corridor along the west side of Helmcken Road, the benefit of the upgrade is considered low due to the presence of the existing sidewalk. Higher benefits may be apparent by focusing on priority corridors with no sidewalks.
Financial Implication: Should the project be deferred or cancelled, the Casino Revenue for this project ($200,000) could be used to fund higher priority sidewalk projects.

ALIGNMENT:

The recommended option aligns with the Town’s following core guiding documents as follows:

Document Alignment
Strategic Plan: Priority D Goal 1: Confidence in the fiscal health and financial sustainability of the Town.
Other Policy Documents: Active Transportation Network Plan: Focusing efforts on priority projects identified in the ATNP.

PUBLIC PARTICIPATION GOAL:

The desired level of public participation for the recommended option is: Inform

TIME CRITICAL:

Frontage improvements for the Aspire development may occur during the spring 2025. It is important for Council to provide direction to staff prior to commencement of the works for contractual purposes (or to notify the developer not to mobilize for project C-054).

CONCURRENCE:

Role Initials Comments
Chief Administrative Officer SS

REVIEWED BY:

Role Initials
Director of Corporate Administration/Deputy CAO N/R
Director of Finance & Technology N/R
Director of Development Services N/R
Director of Engineering
Director of Protective Services N/R

ATTACHMENTS:

  1. Project Summary C-054 (2024-2028 Financial Plan)
Page 63–66