This site is in beta — data may be incomplete and features are still being added.
Council Meeting/Documents/Project Summary C-054: Curb and sidewalk replacement – Helmcken-Eagle Creek Village to Burnside Rd
Appendix

Project Summary C-054: Curb and sidewalk replacement – Helmcken-Eagle Creek Village to Burnside Rd

March 18, 2025Pages 67–682 sections

Project summary document for project C-054 including costs, benefits, and a location map.

1 CALL TO ORDER- Mayor Tobias called the meeting to order at 7:00 p.m.
Total 2024 Budget: $225,000Project covers infill on the north side of Helmcken Road

Project Summary

Project Name: Curb and sidewalk replacement – Helmcken-Eagle Creek Village to Burnside Rd 2-2-11101-310 CC1189 / 1-2-03310-630 CC 331-01

Project Number: C-054 Financial Plan: 2024 – 2028 Priority: Optimal

Submitted by: Ivan Leung, Director of Engineering

Executive Summary

This project was included in the 2022-2026 Financial Plan. Carried over from 2023 to time with the 3 Helmcken frontage works. Asphalt curb was installed along Helmcken in 1990’s. The curb has degraded and is ready for replacement. Surrounding developments have been required to install concrete curb, gutter and sidewalk. This section of infill would complete the north side of Helmcken from Burnside Rd W to Watkiss and could tie in with the 3 Helmcken development frontage works.

Business problem and opportunity

The 3 Helmcken development is expected to complete their frontage works in 2024/2025. Installing these sidewalks simultaneously or in partnership with this development could reduce future construction disruption while also closing the gap in concrete sidewalks from Burnside Road to Watkiss Way. Doing so increases safety for pedestrians and cyclists while also reduces costs for mobilization / demobilization and traffic control works.

The FY1 costs are based on Dec. 18, 2023 cost estimates by the Engineering consultant, and includes inspection, contract administration (for partnering with the development work) and contingency.

Proposed project objectives

The project should be completed during 3 Helmcken’s development’s off-site construction to minimize construction disruption of traffic.

Business risks

Budget has been increased to reflect current unit rates

Proposed sources of funding

Capital: DCCs up to $23,206, Casino revenue Operational: Taxation

Costs and benefits

Costs FY1 FY2 FY3 FY4 FY5 5-year Total
Capital 225,000 0 0 0 0 225,000
Operational 0 500 500 500 500 2,000
Total 225,000 500 500 500 500 227,000
Benefits
Tangible Improved pedestrian infrastructure
Intangible Closing the concrete sidewalk gap on Helmcken Road

Recommendation

THAT the Committee recommend the 2024-2028 Financial Plan include curb and sidewalk replacement – Eagle Creek Village to Helmcken/Burnside Rd in 2024 to be funded by DCCs and Casino revenue.


Page 67–68

Additional Information

Aerial map showing the north-western portion of the project site on Helmcken Road
Aerial map showing the north-western portion of the project site on Helmcken Road
Aerial map showing a section of Helmcken Road with residential properties and the start of a red line indicating new curb and sidewalk work
Aerial map showing a section of Helmcken Road with residential properties and the start of a red line indicating new curb and sidewalk work
Aerial map showing the central portion of Helmcken Road with property boundaries and a label for "Helmcken Rd"
Aerial map showing the central portion of Helmcken Road with property boundaries and a label for "Helmcken Rd"
Aerial map showing the north-eastern portion of the project site at the intersection of Helmcken Road and Burnside Road West
Aerial map showing the north-eastern portion of the project site at the intersection of Helmcken Road and Burnside Road West
Aerial map showing residential properties on the south side of Helmcken Road
Aerial map showing residential properties on the south side of Helmcken Road
Aerial map showing the junction of Helmcken Road, Camden Avenue, and Conard Street
Aerial map showing the junction of Helmcken Road, Camden Avenue, and Conard Street
Aerial map showing the south-eastern project area including properties on Quincy Street
Aerial map showing the south-eastern project area including properties on Quincy Street

Carryforward Information:

  • 2023 Budget: $100,000
  • 2023 Budget Used: $8,077 (design)
  • Carryforward to 2024: $91,925
  • Additional required for project: $133,075
  • Total 2024 Budget: $225,000
Page 67–68

Document Images

(23)
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Document image
Extracted from: 2025 03 18 Council Agenda - Agenda - Pdf