Attachment 16: DP3.2 - North Building Exterior Elevations (North & West)
Architectural elevation drawings for the north and west faces of the building.
NORTH BUILDING EXTERIOR ELEVATIONS
Project Information
Consultant: OMICRON ARCHITECTURE ENGINEERING LTD. Address: Fifth Floor, Canadian Centre, 833 - 4th Avenue SW, Calgary, AB T2P 3T5 CANADA Phone: 403 262 9733 Toll-free: 1 877 632 3350 Fax: 403 262 9750 Website: www.omicronaec.com
Project: Eagle Creek Village, Phase 2 - North Bldg Location: Town of View Royal, British Columbia Project Number: 11 14 032 Sheet Number: DP3.2
Issued Table
| # | Date | Remarks |
|---|---|---|
| 1 | NOV. 16, 2016 | ISSUED FOR DP |
| 2 | JAN. 25, 2017 | ISSUED FOR TENDER |
| 3 | FEB. 8, 2017 | CONC. FACADE/LANDSCAPE REV. |
Drawings
* * Scale: 1:150
* * Scale: 1:150
* * Scale: 1:50 * Detail Notes: Primed/painted steel angle; Stainless steel cables; 2000mm width; 5000mm max height; 3000mm min height.
Keynote Legend
- CEMENTITIOUS BOARD & BATTEN SIDING, COLOUR: JAMES HARDIE MONTEREY TAUPE
- CEMENTITIOUS LAP SIDING TYPE 2 - 150mm EXPOSURE, COLOUR: JAMES HARDIE WOODSTOCK BROWN
- CULTURED STONE VENEER, COLOUR: CHARCOAL MIST LEDGESTONE
- ENTRY CANOPY - EXPRESSED TIMBER STRUCTURE W/ WOOD GRAIN TEXTURE SOFFIT.
- RESERVED
- CEMENTITIOUS TRIM BOARD 19 x 140 CEDAR OR WOOD GRAIN TEXTURE, COLOUR: TO MATCH JAMES HARDIE ARCTIC WHITE
- CEMENTITIOUS TRIM BOARD 19 x 285 CEDAR OR WOOD GRAIN TEXTURE, COLOUR: BLACK
- PARKADE EXHAUST LOUVER
- MANUFACTURED STONE LINTEL
- STRUCTURAL COLUMN CLAD W/ CEMENTITIOUS TRIM BOARD, COLOUR: BLACK
- OVERHEAD SECURITY GRILLE
- PREFINISHED METAL FLASHING CAP, COLOUR: BLACK
- OVERHEAD METAL DOOR
- WOOD OR REPLICA WOOD CLADDING
- PVC FRAME WINDOW, FRAME COLOUR: WHITE
- GLASS PATIO DOOR
- ALUMINUM CLEAR GLASS DOOR, FRAME COLOUR: CLEAR ANODIZED
- INSULATED METAL DOOR
- POWDERCOATED ALUMINUM GUARDRAIL, COLOUR: BLACK
- ALUMINUM WINDOW, FRAME COLOUR: CLEAR ANODIZED
- CONCRETE, COLORFLEX ELASTOMERIC COATING C/W CAST IN PLACE REVEALS AT CRITICAL O.C. COLOUR: LINEN
- FINISH GRADE/PAVING TO SLOPE AWAY FROM BUILDING
- BALCONY EDGE FLASHING, COLOUR: BLACK
- CANOPY SOFFIT - WOOD OR REPLICA WOOD
- TRELLIS PLANTING WITHIN ROCK GARDEN - SEE SITE SECTION DETAILS
- FIRE DEPARTMENT CONNECTION
- ENTERPHONE
- CEMENTITIOUS SHINGLE SIDING TYPE 3, COLOUR: TO MATCH JAMES HARDIE NIGHT GRAY
- PARKADE ROOF
Sheet Notes
A. ALL ELEVATIONS ARE FROM DATUM ELEVATION PARKADE LEVEL - 100.00 B. SOFFITS AND OTHER VISIBLE EXTERIOR FINISH ELEMENTS NOT FULLY SHOWN OR DETAILED ON THE PLANS SHALL BE FINISHED IN THE SAME CHARACTER AS FOR SIMILAR CONDITIONS. REFER TO WALLS SECTIONS & DETAILS FOR MATERIALS. C. REFER TO ELECTRICAL & LANDSCAPE DRAWINGS FOR EXTERIOR LIGHTING. D. SEE KEY NOTES FOR FINISH MATERIALS AND COLORS. E. LANDSCAPE ARCHITECT'S DRAWINGS SHALL TAKE PRECEDENCE IN MATTERS OFF ALL FINISH GRADE ELEVATIONS AND PROFILE. F. ALL GUTTERS, DOWN SPOUTS, FLASHINGS, VENTS, ELECTRICAL CONDUITS, ETC. SHALL BE PRE-FINISHED TO MATCH THE COLOR OF THE ADJACENT SURFACE, U.O.N. G. ALL DOORS AND WINDOWS EXPOSED TO AMBIENT CONDITIONS AND IN UNCONDITIONED SPACES SHALL BE GASKETED, WEATHER STRIPPED OR OTHERWISE TREATED TO LIMIT AIR INFILTRATION. H. ALL EXPOSED WOOD ELEMENTS SHOWN TO BE PRESSURE TREATED. I. ALL FIBER-CEMENT SIDING (HARDI BOARD) BUTT JOINTS BACKED WITH 25 GAUGE PREFINISHED METAL FLASHING. J. PROVIDE PREFINISHED METAL FLASHING AT ALL ROOF/WALL JOINTS.
Elevation and Building Height Data
- T.O. Sixth Floor: 115.71
- T.O. Fifth Floor Concrete Topping: 112.62
- T.O. Fourth Floor Concrete Topping: 109.53
- T.O. Third Floor Concrete Topping: 106.44
- T.O. Second Floor Concrete Topping: 103.35
- T.O. Main Floor / Main Level Parking Plan Slab on Grade: 100.00
- Average Calculated Grade: 24.99m
- Maximum Building Height (20m): 44.99m
- Actual Building Height Above Calculated Avg. Grade: 21.96m
Consultant General Notes
OMICRON ARCHITECTURE ENGINEERING LTD. This drawing is a copyright instrument of service and remains the property of the Consultant. All information shown on this drawing is copyright material and is for use on the named project only. Information contained herein may not be used or reproduced in anyway without written permission. Drawings shall not be scaled. The Contractor shall verify and be responsible for all dimensions, datum, and elevations pertinent to executing the work. Discrepancies and variations shall be reported to the Consultant prior to commencing construction. In all cases, the latest issue of the drawing shall be used in the execution of the work. The Contractor shall ensure that all previous issues of this drawing are marked "Superseded", with reference to the latest issue, and used for reference purposes only.
All work shall conform to the latest editions of local Building Codes, jurisdictional codes and local ordinances. Drawing sheet numbers are prefixed as follows:
- A = Architectural
- S = Structural
- M = Mechanical/HVAC
- P = Plumbing
- E = Electrical
- FP = Fire Protection
- L = Landscape
- C = Civil